Share June 26, 2025 on Facebook
Share June 26, 2025 on Linkedin
Email June 26, 2025 link
- Phase 1 – Eagle and Lake Hazel Intersection.
- Lake Hazel and Eagle Intersection opening July 1st in the East/West Direction.
- Conduits and pole foundations being placed. Concrete buffer being placed. Concrete paving completed until soundwall installed. Paving ongoing until June 30th.
- Phase 2 anticipated starting July 1st. Lake Hazel to Amity closed for duration of 2nd phase. Milling Starting July 1st – 3rd. Utilities will be relocating services.
Share June 20, 2025 on Facebook
Share June 20, 2025 on Linkedin
Email June 20, 2025 link
- Lake Hazel and Eagle Intersection closed
- Wall A and other miscellaneous walls ongoing
- Conduits and pole foundations being placed
- Placing road base
- Sidewalk being placed
- Concrete Paving completed until Soundwall installed
- Preparing road for asphalt
- Paving anticipated June 26th
- Phase 2 Anticipated starting first week of July
- Lake Hazel to Amity closed for duration of 2nd phase
- Lake Hazel & Eagle Intersection will be open in the East/West direction.
Share June 13, 2025 on Facebook
Share June 13, 2025 on Linkedin
Email June 13, 2025 link
- Lake Hazel and Eagle Intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Concrete paving started June 2nd and will be on-going through June 18th.
- South and West legs complete.
Share June 6, 2025 on Facebook
Share June 6, 2025 on Linkedin
Email June 6, 2025 link
- Lake Hazel and Eagle Intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Concrete paving June 2nd and will be on-going through June 18th.
Share May 30, 2025 on Facebook
Share May 30, 2025 on Linkedin
Email May 30, 2025 link
- Lake Hazel and Eagle intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Concrete paving anticipated starting June 2nd – 18th.
Share May 23, 2025 on Facebook
Share May 23, 2025 on Linkedin
Email May 23, 2025 link
- Lake Hazel and Eagle intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
- Concrete paving anticipated starting June 2nd – 18th.
Share May 16, 2025 on Facebook
Share May 16, 2025 on Linkedin
Email May 16, 2025 link
- Lake Hazel and Eagle intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
Share May 8, 2025 on Facebook
Share May 8, 2025 on Linkedin
Email May 8, 2025 link
- Lake Hazel and Eagle intersection closed.
- Wall installation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk being placed.
Share May 2, 2025 on Facebook
Share May 2, 2025 on Linkedin
Email May 2, 2025 link
- Lake Hazel and Eagle Intersection closed.
- Walls ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk prep ongoing.
Share April 25, 2025 on Facebook
Share April 25, 2025 on Linkedin
Email April 25, 2025 link
- Lake Hazel and Eagle Intersection closed.
- Wall construction ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk prep ongoing.