Eagle Road, Lake Hazel Road to Amity Road

Share Eagle Road, Lake Hazel Road to Amity Road on Facebook Share Eagle Road, Lake Hazel Road to Amity Road on Twitter Share Eagle Road, Lake Hazel Road to Amity Road on Linkedin Email Eagle Road, Lake Hazel Road to Amity Road link

The Ada County Highway District will be reconstructing Eagle Road between Lake Hazel and Amity. The purpose of this project is to improve traffic flow and increase safety for all users.

Roadway Description

  • Widen Eagle Road from Lake Hazel Road to Amity Road to two lanes in each direction with a center turn lane and center medians to calm traffic.
  • Construct a multi-lane roundabout at the intersection of Eagle Road and Taconic Drive.
  • Add a multi-use pathway on each side of Eagle Road and at the Lake Hazel intersection for bicyclists and pedestrians.

Eagle and Lake Hazel Intersection Description

  • Widen and signalize the Lake Hazel and Eagle intersection
  • Add dual left-turn lanes on most approaches
  • Include additional thru lanes
  • Add dedicated right turn lanes on two approaches
  • Install a multi-use pathway for bicyclists and pedestrians
  • Include painted crosswalks

The Ada County Highway District will be reconstructing Eagle Road between Lake Hazel and Amity. The purpose of this project is to improve traffic flow and increase safety for all users.

Roadway Description

  • Widen Eagle Road from Lake Hazel Road to Amity Road to two lanes in each direction with a center turn lane and center medians to calm traffic.
  • Construct a multi-lane roundabout at the intersection of Eagle Road and Taconic Drive.
  • Add a multi-use pathway on each side of Eagle Road and at the Lake Hazel intersection for bicyclists and pedestrians.

Eagle and Lake Hazel Intersection Description

  • Widen and signalize the Lake Hazel and Eagle intersection
  • Add dual left-turn lanes on most approaches
  • Include additional thru lanes
  • Add dedicated right turn lanes on two approaches
  • Install a multi-use pathway for bicyclists and pedestrians
  • Include painted crosswalks
  • November 22, 2024

    Share November 22, 2024 on Facebook Share November 22, 2024 on Twitter Share November 22, 2024 on Linkedin Email November 22, 2024 link
    22 Nov 2024
    • Lake Hazel and Eagle Intersection closed.
    • Cut and fill ongoing at Lake Hazel Intersection.
    • Wall excavation ongoing.
    • Wall blocks ongoing.
    • City of Meridian water ongoing.
    • Irrigation will start after City of Meridian water is complete.
  • November 15, 2024

    Share November 15, 2024 on Facebook Share November 15, 2024 on Twitter Share November 15, 2024 on Linkedin Email November 15, 2024 link
    15 Nov 2024
    • Lake Hazel and Eagle Intersection closed.
    • Cut and fill ongoing at Lake Hazel Intersection.
    • Wall excavation ongoing.
    • Wall blocks ongoing.
    • Idaho Power relocating poles.
    • Communication utilities will relocate after poles.
  • November 7, 2024

    Share November 7, 2024 on Facebook Share November 7, 2024 on Twitter Share November 7, 2024 on Linkedin Email November 7, 2024 link
    07 Nov 2024
    • Lake Hazel and Eagle Intersection closed.
    • Cut and fill ongoing at Lake Hazel Intersection.
    • Wall excavation ongoing - Wall blocks ongoing.
    • Idaho Power relocating poles.
    • Communication utilities will relocate after poles.
  • November 1, 2024

    Share November 1, 2024 on Facebook Share November 1, 2024 on Twitter Share November 1, 2024 on Linkedin Email November 1, 2024 link
    01 Nov 2024
    • Lake Hazel and Eagle intersection closed.
    • Cut and fill ongoing at Lake Hazel intersection.
    • Wall excavation ongoing.
    • Wall blocks started October 31st.
    • Idaho Power relocating poles.
    • Communication utilities will relocate after poles.
  • October 24, 2024

    Share October 24, 2024 on Facebook Share October 24, 2024 on Twitter Share October 24, 2024 on Linkedin Email October 24, 2024 link
    24 Oct 2024
    • Lake Hazel and Eagle Intersection closed.
    • Cut and fill ongoing at Lake Hazel intersection.
    • Installation of wall ongoing.
    • Idaho Power relocating poles.
    • Communication utilities will relocate after poles.
  • October 17, 2024

    Share October 17, 2024 on Facebook Share October 17, 2024 on Twitter Share October 17, 2024 on Linkedin Email October 17, 2024 link
    17 Oct 2024

    Lake Hazel and Eagle Intersection closed

    • Cut and fill ongoing at Lake Hazel intersection.
    • Retaining wall construction started October 16th.
    • Idaho Power relocating poles.
    • Communication utilities will relocate after poles.
  • October 10, 2024

    Share October 10, 2024 on Facebook Share October 10, 2024 on Twitter Share October 10, 2024 on Linkedin Email October 10, 2024 link
    10 Oct 2024
    • Lake Hazel and Eagle intersection closed.
    • Cut and fill ongoing at Lake Hazel intersection.
    • Retaining wall construction is beginning October 16th.
  • October 4, 2024

    Share October 4, 2024 on Facebook Share October 4, 2024 on Twitter Share October 4, 2024 on Linkedin Email October 4, 2024 link
    04 Oct 2024
    • Lake Hazel and Eagle Intersection closed.
    • Cut and fill ongoing.
  • September 26, 2024

    Share September 26, 2024 on Facebook Share September 26, 2024 on Twitter Share September 26, 2024 on Linkedin Email September 26, 2024 link
    26 Sep 2024
    • Lake Hazel and Eagle Intersection closed.
    • Removing asphalt pavement on Sept 17th – 20th.
    • Excavation afterwards.
    • Clearing and grubbing.
  • September 20, 2024

    Share September 20, 2024 on Facebook Share September 20, 2024 on Twitter Share September 20, 2024 on Linkedin Email September 20, 2024 link
    20 Sep 2024
    • Road closure started Sept 16th.
    • Removing asphalt pavement on Sept 17th – 20th.
    • Excavation afterwards.
Page last updated: 25 Apr 2025, 09:15 AM