Eagle Road, Lake Hazel Road to Amity Road

Share Eagle Road, Lake Hazel Road to Amity Road on Facebook Share Eagle Road, Lake Hazel Road to Amity Road on Twitter Share Eagle Road, Lake Hazel Road to Amity Road on Linkedin Email Eagle Road, Lake Hazel Road to Amity Road link

The Ada County Highway District will be reconstructing Eagle Road between Lake Hazel and Amity. The purpose of this project is to improve traffic flow and increase safety for all users.

Roadway Description

  • Widen Eagle Road from Lake Hazel Road to Amity Road to two lanes in each direction with a center turn lane and center medians to calm traffic.
  • Construct a multi-lane roundabout at the intersection of Eagle Road and Taconic Drive.
  • Add a multi-use pathway on each side of Eagle Road and at the Lake Hazel intersection for bicyclists and pedestrians.

Eagle and Lake Hazel Intersection Description

  • Widen and signalize the Lake Hazel and Eagle intersection
  • Add dual left-turn lanes on most approaches
  • Include additional thru lanes
  • Add dedicated right turn lanes on two approaches
  • Install a multi-use pathway for bicyclists and pedestrians
  • Include painted crosswalks

The Ada County Highway District will be reconstructing Eagle Road between Lake Hazel and Amity. The purpose of this project is to improve traffic flow and increase safety for all users.

Roadway Description

  • Widen Eagle Road from Lake Hazel Road to Amity Road to two lanes in each direction with a center turn lane and center medians to calm traffic.
  • Construct a multi-lane roundabout at the intersection of Eagle Road and Taconic Drive.
  • Add a multi-use pathway on each side of Eagle Road and at the Lake Hazel intersection for bicyclists and pedestrians.

Eagle and Lake Hazel Intersection Description

  • Widen and signalize the Lake Hazel and Eagle intersection
  • Add dual left-turn lanes on most approaches
  • Include additional thru lanes
  • Add dedicated right turn lanes on two approaches
  • Install a multi-use pathway for bicyclists and pedestrians
  • Include painted crosswalks
  • September 11, 2024 - Construction and Detour Map Information

    Share September 11, 2024 - Construction and Detour Map Information on Facebook Share September 11, 2024 - Construction and Detour Map Information on Twitter Share September 11, 2024 - Construction and Detour Map Information on Linkedin Email September 11, 2024 - Construction and Detour Map Information link

    The Eagle Road, Lake Hazel to Amity project will begin construction Monday, September 16th. Originally scheduled for January 2024, the project was delayed due to an unresponsive and void construction bid. Work is now expected to be complete by November 2025.

    DURING PHASE I:

    • The Eagle Rd. and Taconic Dr. pedestrian crossing will not be impacted.
    • Eagle Rd and Lake Hazel Rd. intersection will be closed.
    • ACHD will close Eagle Rd between Lake Hazel Rd. and Taconic Dr.
      (keeping the Taconic Dr. intersection and pedestrian crossing open)
    • ACHD is working closely with the West Ada School District to ensure
      safe school commutes for all.

    SAFETY IS OUR TOP PRIORITY:

    With safety top of mind, and after thorough evaluation, ACHD staff has identified eight intersections where we will install temporary all-way stops with stop bars during construction.

    West side of Eagle Rd:

    • Taconic/Montague
    • Taconic/Lodge Trail
    • Taconic/Cyanite
    • Taconic/Cyanite/Jado

    East side of Eagle Rd:

    • Taconic/Woodville
    • Arable/Woodville
    • Arable/Mardia
    • Arable/Collingwood





  • Construction to start in September

    Share Construction to start in September on Facebook Share Construction to start in September on Twitter Share Construction to start in September on Linkedin Email Construction to start in September link

    The Ada County Highway District (ACHD) is pleased to announce that the Eagle Road, Lake Hazel to Amity project will begin construction starting as early as mid-September 2024. Originally scheduled for January 2024, the project was delayed due to an unresponsive and void construction bid. Work is now expected to be complete by November 2025.

    Traffic and Construction Impacts

    • Short-term road closures
    • Eagle and Lake Hazel intersection closure for several months
    • Lane restrictions with flaggers
    • General construction noise, dust, equipment backup alarms and ground vibration
    • Crews may work from 7 a.m. to 7 p.m. unless otherwise approved
    • The contractor will work with property owners to minimize construction impacts and maintain access


  • Project Update- February 14, 2024

    Share Project Update- February 14, 2024 on Facebook Share Project Update- February 14, 2024 on Twitter Share Project Update- February 14, 2024 on Linkedin Email Project Update- February 14, 2024 link

    The Eagle Road, Lake Hazel to Amity Road project has been delayed until fall of 2024 due to a licensing issue which resulted in an unresponsive and void construction bid and contract.

    In December, ACHD awarded the bid for the project, with construction scheduled to begin in February. However, before construction began, it was discovered that a designated electrical subcontractor associated with the project was improperly licensed when the contractor accepted the subcontractor’s bid and when the contractor named the subcontractor in its bid to ACHD. This statutory violation caused the contractor’s bid to be unresponsive and void, and therefore the contract between ACHD and the contractor, to be void.

    On Wednesday, February 14, the ACHD Board of Commissioners voted to re-bid the project, which will happen in the coming months. A new construction start date will be announced after the project’s new bid is awarded.

  • December 22, 2023

    Share December 22, 2023 on Facebook Share December 22, 2023 on Twitter Share December 22, 2023 on Linkedin Email December 22, 2023 link
    • Pre-Construction Meeting TBD.
    • Notice to Proceed is scheduled for January.
  • Construction to start mid-January 2024

    Share Construction to start mid-January 2024 on Facebook Share Construction to start mid-January 2024 on Twitter Share Construction to start mid-January 2024 on Linkedin Email Construction to start mid-January 2024 link

    The Ada County Highway District (ACHD) will be constructing improvements to Eagle Road, Lake Hazel to Amity starting as early as mid-January*. Work is expected to be complete by Spring 2025.

    Traffic and Construction Impacts

    • Short-term road closures
    • Eagle and Lake Hazel intersection closure for several months
    • Lane restrictions with flaggers
    • General construction noise, dust, equipment backup alarms and ground vibration
    • Crews may work from 7 a.m. to 7 p.m. unless otherwise approved
    • The contractor will work with property owners to minimize construction impacts and maintain access

    *Due to contractor staffing issues and supply-chain shortages, the construction schedule could change.


Page last updated: 07 Nov 2024, 02:30 PM