Eagle Road, Lake Hazel Road to Amity Road
The Ada County Highway District will be reconstructing Eagle Road between Lake Hazel and Amity. The purpose of this project is to improve traffic flow and increase safety for all users.
Roadway Description
- Widen Eagle Road from Lake Hazel Road to Amity Road to two lanes in each direction with a center turn lane and center medians to calm traffic.
- Construct a multi-lane roundabout at the intersection of Eagle Road and Taconic Drive.
- Add a multi-use pathway on each side of Eagle Road and at the Lake Hazel intersection for bicyclists and pedestrians.
Eagle and Lake Hazel Intersection Description
- Widen and signalize the Lake Hazel and Eagle intersection
- Add dual left-turn lanes on most approaches
- Include additional thru lanes
- Add dedicated right turn lanes on two approaches
- Install a multi-use pathway for bicyclists and pedestrians
- Include painted crosswalks
The Ada County Highway District will be reconstructing Eagle Road between Lake Hazel and Amity. The purpose of this project is to improve traffic flow and increase safety for all users.
Roadway Description
- Widen Eagle Road from Lake Hazel Road to Amity Road to two lanes in each direction with a center turn lane and center medians to calm traffic.
- Construct a multi-lane roundabout at the intersection of Eagle Road and Taconic Drive.
- Add a multi-use pathway on each side of Eagle Road and at the Lake Hazel intersection for bicyclists and pedestrians.
Eagle and Lake Hazel Intersection Description
- Widen and signalize the Lake Hazel and Eagle intersection
- Add dual left-turn lanes on most approaches
- Include additional thru lanes
- Add dedicated right turn lanes on two approaches
- Install a multi-use pathway for bicyclists and pedestrians
- Include painted crosswalks
-
November 1, 2024
Share November 1, 2024 on Facebook Share November 1, 2024 on Twitter Share November 1, 2024 on Linkedin Email November 1, 2024 link- Lake Hazel and Eagle intersection closed.
- Cut and fill ongoing at Lake Hazel intersection.
- Wall excavation ongoing.
- Wall blocks started October 31st.
- Idaho Power relocating poles.
- Communication utilities will relocate after poles.
- Lake Hazel and Eagle intersection closed.
- Cut and fill ongoing at Lake Hazel intersection.
- Wall excavation ongoing.
- Wall blocks started October 31st.
- Idaho Power relocating poles.
- Communication utilities will relocate after poles.
-
October 24, 2024
Share October 24, 2024 on Facebook Share October 24, 2024 on Twitter Share October 24, 2024 on Linkedin Email October 24, 2024 link- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing at Lake Hazel intersection.
- Installation of wall ongoing.
- Idaho Power relocating poles.
- Communication utilities will relocate after poles.
- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing at Lake Hazel intersection.
- Installation of wall ongoing.
- Idaho Power relocating poles.
- Communication utilities will relocate after poles.
-
October 17, 2024
Share October 17, 2024 on Facebook Share October 17, 2024 on Twitter Share October 17, 2024 on Linkedin Email October 17, 2024 linkLake Hazel and Eagle Intersection closed
- Cut and fill ongoing at Lake Hazel intersection.
- Retaining wall construction started October 16th.
- Idaho Power relocating poles.
- Communication utilities will relocate after poles.
Lake Hazel and Eagle Intersection closed
- Cut and fill ongoing at Lake Hazel intersection.
- Retaining wall construction started October 16th.
- Idaho Power relocating poles.
- Communication utilities will relocate after poles.
-
October 10, 2024
Share October 10, 2024 on Facebook Share October 10, 2024 on Twitter Share October 10, 2024 on Linkedin Email October 10, 2024 link- Lake Hazel and Eagle intersection closed.
- Cut and fill ongoing at Lake Hazel intersection.
- Retaining wall construction is beginning October 16th.
- Lake Hazel and Eagle intersection closed.
- Cut and fill ongoing at Lake Hazel intersection.
- Retaining wall construction is beginning October 16th.
-
October 4, 2024
Share October 4, 2024 on Facebook Share October 4, 2024 on Twitter Share October 4, 2024 on Linkedin Email October 4, 2024 link- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing.
- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing.
-
September 26, 2024
Share September 26, 2024 on Facebook Share September 26, 2024 on Twitter Share September 26, 2024 on Linkedin Email September 26, 2024 link- Lake Hazel and Eagle Intersection closed.
- Removing asphalt pavement on Sept 17th – 20th.
- Excavation afterwards.
- Clearing and grubbing.
- Lake Hazel and Eagle Intersection closed.
- Removing asphalt pavement on Sept 17th – 20th.
- Excavation afterwards.
- Clearing and grubbing.
-
September 20, 2024
Share September 20, 2024 on Facebook Share September 20, 2024 on Twitter Share September 20, 2024 on Linkedin Email September 20, 2024 link- Road closure started Sept 16th.
- Removing asphalt pavement on Sept 17th – 20th.
- Excavation afterwards.
- Road closure started Sept 16th.
- Removing asphalt pavement on Sept 17th – 20th.
- Excavation afterwards.
-
Traffic Advisory Information
Share Traffic Advisory Information on Facebook Share Traffic Advisory Information on Twitter Share Traffic Advisory Information on Linkedin Email Traffic Advisory Information linkTraffic Advisory
Eagle Road, Lake Hazel to Amity Project Begins
Next Week
ADA COUNTY — Work will begin next week on ACHD’s Eagle Road, Lake Hazel Road to Amity Road project.
Starting Monday, the intersection of Eagle and Lake Hazel Roads will be closed. Eagle Road will also be closed between Lake Hazel Road and Taconic Drive.
For the first phase of construction, the intersection at Eagle and Taconic will remain open. Construction at the Eagle and Taconic intersection is scheduled for summer 2025.
During construction, temporary stop signs will be installed at several local intersections along Taconic Drive and Arable Drive. Non-local traffic should use Amity Road to the north, Columbia Road to the south, Locust Grove Road to the west, and Cloverdale Road to the east to get around the closures.
The roadwork is part of ACHD’s Eagle Road, Lake Hazel Road to Amity Road project, which includes widening and signalizing the intersection of Eagle and Lake Hazel, installing a multi-lane roundabout at Eagle and Taconic, widening Eagle Road, and adding a multi-use pathway for bicyclists and pedestrians. The entire project is expected to be complete in November 2025.
Residents can learn more and sign up for project updates on ACHD’s website.
Traffic Advisory
Eagle Road, Lake Hazel to Amity Project Begins
Next Week
ADA COUNTY — Work will begin next week on ACHD’s Eagle Road, Lake Hazel Road to Amity Road project.
Starting Monday, the intersection of Eagle and Lake Hazel Roads will be closed. Eagle Road will also be closed between Lake Hazel Road and Taconic Drive.
For the first phase of construction, the intersection at Eagle and Taconic will remain open. Construction at the Eagle and Taconic intersection is scheduled for summer 2025.
During construction, temporary stop signs will be installed at several local intersections along Taconic Drive and Arable Drive. Non-local traffic should use Amity Road to the north, Columbia Road to the south, Locust Grove Road to the west, and Cloverdale Road to the east to get around the closures.
The roadwork is part of ACHD’s Eagle Road, Lake Hazel Road to Amity Road project, which includes widening and signalizing the intersection of Eagle and Lake Hazel, installing a multi-lane roundabout at Eagle and Taconic, widening Eagle Road, and adding a multi-use pathway for bicyclists and pedestrians. The entire project is expected to be complete in November 2025.
Residents can learn more and sign up for project updates on ACHD’s website.
-
September 13, 2024
Share September 13, 2024 on Facebook Share September 13, 2024 on Twitter Share September 13, 2024 on Linkedin Email September 13, 2024 link- Road closure starting Sept 16th.
- Removing asphalt pavement on Sept 17th.
- Road closure starting Sept 16th.
- Removing asphalt pavement on Sept 17th.
-
September 11, 2024 - Construction and Detour Map Information
Share September 11, 2024 - Construction and Detour Map Information on Facebook Share September 11, 2024 - Construction and Detour Map Information on Twitter Share September 11, 2024 - Construction and Detour Map Information on Linkedin Email September 11, 2024 - Construction and Detour Map Information linkThe Eagle Road, Lake Hazel to Amity project will begin construction Monday, September 16th. Originally scheduled for January 2024, the project was delayed due to an unresponsive and void construction bid. Work is now expected to be complete by November 2025.
DURING PHASE I:
- The Eagle Rd. and Taconic Dr. pedestrian crossing will not be impacted.
- Eagle Rd and Lake Hazel Rd. intersection will be closed.
- ACHD will close Eagle Rd between Lake Hazel Rd. and Taconic Dr.
(keeping the Taconic Dr. intersection and pedestrian crossing open) -
ACHD is working closely with the West Ada School District to ensure
safe school commutes for all.
SAFETY IS OUR TOP PRIORITY:
With safety top of mind, and after thorough evaluation, ACHD staff has identified eight intersections where we will install temporary all-way stops with stop bars during construction.
West side of Eagle Rd:
- Taconic/Montague
- Taconic/Lodge Trail
- Taconic/Cyanite
- Taconic/Cyanite/Jado
East side of Eagle Rd:
- Taconic/Woodville
- Arable/Woodville
- Arable/Mardia
- Arable/Collingwood

The Eagle Road, Lake Hazel to Amity project will begin construction Monday, September 16th. Originally scheduled for January 2024, the project was delayed due to an unresponsive and void construction bid. Work is now expected to be complete by November 2025.
DURING PHASE I:
- The Eagle Rd. and Taconic Dr. pedestrian crossing will not be impacted.
- Eagle Rd and Lake Hazel Rd. intersection will be closed.
- ACHD will close Eagle Rd between Lake Hazel Rd. and Taconic Dr.
(keeping the Taconic Dr. intersection and pedestrian crossing open) -
ACHD is working closely with the West Ada School District to ensure
safe school commutes for all.
SAFETY IS OUR TOP PRIORITY:
With safety top of mind, and after thorough evaluation, ACHD staff has identified eight intersections where we will install temporary all-way stops with stop bars during construction.
West side of Eagle Rd:
- Taconic/Montague
- Taconic/Lodge Trail
- Taconic/Cyanite
- Taconic/Cyanite/Jado
East side of Eagle Rd:
- Taconic/Woodville
- Arable/Woodville
- Arable/Mardia
- Arable/Collingwood

Follow Project
Who's Listening
-
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org -
Supervisor, Capital Projects
Phone 208-387-6100 Email connect@achdidaho.org