The Ada County Highway District will be reconstructing Eagle Road between Lake Hazel and Amity. The purpose of this project is to improve traffic flow and increase safety for all users.
Roadway Description
- Widen Eagle Road from Lake Hazel Road to Amity Road to two lanes in each direction with a center turn lane and center medians to calm traffic.
- Construct a multi-lane roundabout at the intersection of Eagle Road and Taconic Drive.
- Add a multi-use pathway on each side of Eagle Road and at the Lake Hazel intersection for bicyclists and pedestrians.
Eagle and Lake Hazel Intersection Description
- Widen and signalize the Lake Hazel and Eagle intersection
- Add dual left-turn lanes on most approaches
- Include additional thru lanes
- Add dedicated right turn lanes on two approaches
- Install a multi-use pathway for bicyclists and pedestrians
- Include painted crosswalks
The Ada County Highway District will be reconstructing Eagle Road between Lake Hazel and Amity. The purpose of this project is to improve traffic flow and increase safety for all users.
Roadway Description
- Widen Eagle Road from Lake Hazel Road to Amity Road to two lanes in each direction with a center turn lane and center medians to calm traffic.
- Construct a multi-lane roundabout at the intersection of Eagle Road and Taconic Drive.
- Add a multi-use pathway on each side of Eagle Road and at the Lake Hazel intersection for bicyclists and pedestrians.
Eagle and Lake Hazel Intersection Description
- Widen and signalize the Lake Hazel and Eagle intersection
- Add dual left-turn lanes on most approaches
- Include additional thru lanes
- Add dedicated right turn lanes on two approaches
- Install a multi-use pathway for bicyclists and pedestrians
- Include painted crosswalks
-
April 11, 2025
Share April 11, 2025 on Facebook Share April 11, 2025 on Twitter Share April 11, 2025 on Linkedin Email April 11, 2025 link- Lake Hazel and Eagle Intersection closed.
- Wall excavation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk anticipated starting April 21st.
- Lake Hazel and Eagle Intersection closed.
- Wall excavation ongoing.
- Conduits and pole foundations being placed.
- Placing road base.
- Sidewalk anticipated starting April 21st.
-
April 4, 2025
Share April 4, 2025 on Facebook Share April 4, 2025 on Twitter Share April 4, 2025 on Linkedin Email April 4, 2025 link- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing at Lake Hazel Intersection.
- Wall excavation ongoing.
- Conduits and pole foundations being placed.
- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing at Lake Hazel Intersection.
- Wall excavation ongoing.
- Conduits and pole foundations being placed.
-
March 28, 2025
Share March 28, 2025 on Facebook Share March 28, 2025 on Twitter Share March 28, 2025 on Linkedin Email March 28, 2025 link- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing at Lake Hazel intersection.
- Wall excavation ongoing.
- Conduits being placed.
- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing at Lake Hazel intersection.
- Wall excavation ongoing.
- Conduits being placed.
-
March 20, 2025
Share March 20, 2025 on Facebook Share March 20, 2025 on Twitter Share March 20, 2025 on Linkedin Email March 20, 2025 link- Lake Hazel and Eagle intersection closed.
- Cut and fill ongoing at Lake Hazel intersection.
- Wall excavation ongoing.
- Storm drain being installed.
- Conduits being placed.
- Lake Hazel and Eagle intersection closed.
- Cut and fill ongoing at Lake Hazel intersection.
- Wall excavation ongoing.
- Storm drain being installed.
- Conduits being placed.
-
March 14, 2025
Share March 14, 2025 on Facebook Share March 14, 2025 on Twitter Share March 14, 2025 on Linkedin Email March 14, 2025 link- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing at Lake Hazel intersection.
- Wall excavation ongoing.
- Wall construction ongoing.
- Storm drain is being installed.
- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing at Lake Hazel intersection.
- Wall excavation ongoing.
- Wall construction ongoing.
- Storm drain is being installed.
-
March 6, 2025
Share March 6, 2025 on Facebook Share March 6, 2025 on Twitter Share March 6, 2025 on Linkedin Email March 6, 2025 link- Lake Hazel and Eagle intersection closed.
- Cut and fill ongoing at Lake Hazel intersection.
- Wall excavation ongoing.
- Other irrigation work ongoing.
- Electrical conduits being installed.
- Lake Hazel and Eagle intersection closed.
- Cut and fill ongoing at Lake Hazel intersection.
- Wall excavation ongoing.
- Other irrigation work ongoing.
- Electrical conduits being installed.
-
February 28, 2025
Share February 28, 2025 on Facebook Share February 28, 2025 on Twitter Share February 28, 2025 on Linkedin Email February 28, 2025 link- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing at Lake Hazel Intersection.
- Wall excavation ongoing.
- Irrigation complete.
- Other irrigation work ongoing.
- Electrical conduits being installed.
- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing at Lake Hazel Intersection.
- Wall excavation ongoing.
- Irrigation complete.
- Other irrigation work ongoing.
- Electrical conduits being installed.
-
February 20, 2025
Share February 20, 2025 on Facebook Share February 20, 2025 on Twitter Share February 20, 2025 on Linkedin Email February 20, 2025 link- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing at Lake Hazel Intersection.
- Wall excavation ongoing.
- Wall blocks ongoing.
- City of Meridian water ongoing.
- Storm drain ongoing.
- Irrigation work started January 20th and is on-going.
- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing at Lake Hazel Intersection.
- Wall excavation ongoing.
- Wall blocks ongoing.
- City of Meridian water ongoing.
- Storm drain ongoing.
- Irrigation work started January 20th and is on-going.
-
February 14, 2025
Share February 14, 2025 on Facebook Share February 14, 2025 on Twitter Share February 14, 2025 on Linkedin Email February 14, 2025 link- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing at Lake Hazel Intersection.
- Wall excavation ongoing.
- Wall blocks ongoing.
- City of Meridian water ongoing.
- Storm drain ongoing.
- Irrigation work started January 20th and is on-going.
- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing at Lake Hazel Intersection.
- Wall excavation ongoing.
- Wall blocks ongoing.
- City of Meridian water ongoing.
- Storm drain ongoing.
- Irrigation work started January 20th and is on-going.
-
February 7, 2025
Share February 7, 2025 on Facebook Share February 7, 2025 on Twitter Share February 7, 2025 on Linkedin Email February 7, 2025 link- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing at Lake Hazel Intersection.
- Wall excavation ongoing.
- Wall blocks ongoing.
- City of Meridian water ongoing.
- Storm drain ongoing.
- Irrigation work started January 20th and is on-going.
- Lake Hazel and Eagle Intersection closed.
- Cut and fill ongoing at Lake Hazel Intersection.
- Wall excavation ongoing.
- Wall blocks ongoing.
- City of Meridian water ongoing.
- Storm drain ongoing.
- Irrigation work started January 20th and is on-going.
Page last updated: 21 May 2026, 09:47 AM
Follow Project
Stay informed
Subscribe for project updates
254 members of your community are following this project
Who's Listening
-
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org -
Supervisor, Capital Projects
Phone 208-387-6100 Email connect@achdidaho.org