Boise Avenue Bridge

Share Boise Avenue Bridge on Facebook Share Boise Avenue Bridge on Twitter Share Boise Avenue Bridge on Linkedin Email Boise Avenue Bridge link

As part of the Ada County Highway District’s (ACHD) Bridge Preventative Maintenance Program, ACHD will perform routine maintenance on the Boise Avenue bridge (formerly Healey Road) over the New York Canal.

This planned work includes preventative deck maintenance to extend the life of the structure and ensure it remains safe and reliable. The improvements will help maintain a smooth, durable driving surface for all users.

Construction Impacts

  • Lane restrictions
  • General construction noise, dust, equipment backup alarms, and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved

Construction schedules may change due to high demand for contractors, labor, and supplies.

As part of the Ada County Highway District’s (ACHD) Bridge Preventative Maintenance Program, ACHD will perform routine maintenance on the Boise Avenue bridge (formerly Healey Road) over the New York Canal.

This planned work includes preventative deck maintenance to extend the life of the structure and ensure it remains safe and reliable. The improvements will help maintain a smooth, durable driving surface for all users.

Construction Impacts

  • Lane restrictions
  • General construction noise, dust, equipment backup alarms, and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved

Construction schedules may change due to high demand for contractors, labor, and supplies.

  • April 24, 2026

    Share April 24, 2026 on Facebook Share April 24, 2026 on Twitter Share April 24, 2026 on Linkedin Email April 24, 2026 link
    • Substructure repairs are complete.
    • Deck work started March 16th. Half the bridge will be done at a time.
    • The road will remain open to one lane with a temporary signal.
    • Traffic was swapped on April 9th and work began on the second half of the bridge.
    • Substructure repairs are complete.
    • Deck work started March 16th. Half the bridge will be done at a time.
    • The road will remain open to one lane with a temporary signal.
    • Traffic was swapped on April 9th and work began on the second half of the bridge.
  • April 16, 2026

    Share April 16, 2026 on Facebook Share April 16, 2026 on Twitter Share April 16, 2026 on Linkedin Email April 16, 2026 link
    • Substructure repairs are complete.
    • Deck work started March 16th.
    • Half the bridge will be done at a time.
    • The road will remain open to one lane with a temporary signal.
    • Traffic was swapped on April 9th and work began on the second half of the bridge.
    • Substructure repairs are complete.
    • Deck work started March 16th.
    • Half the bridge will be done at a time.
    • The road will remain open to one lane with a temporary signal.
    • Traffic was swapped on April 9th and work began on the second half of the bridge.
  • April 10, 2026

    Share April 10, 2026 on Facebook Share April 10, 2026 on Twitter Share April 10, 2026 on Linkedin Email April 10, 2026 link
    • Substructure repairs are complete.
    • Deck work started March 16th. Half the bridge will be done at a time. The road will remain open to one lane with a temporary signal.
    • Traffic was swapped on April 9th and work began on the second half of the bridge.
    • Substructure repairs are complete.
    • Deck work started March 16th. Half the bridge will be done at a time. The road will remain open to one lane with a temporary signal.
    • Traffic was swapped on April 9th and work began on the second half of the bridge.
  • April 2, 2026

    Share April 2, 2026 on Facebook Share April 2, 2026 on Twitter Share April 2, 2026 on Linkedin Email April 2, 2026 link
    • Substructure repairs are complete.
    • Deck work started March 16th.
    • Half the bridge will be done at a time.
    • The road will remain open to one lane with a temporary signal.
    • Concrete for the first half was placed on March 27th.
    • Substructure repairs are complete.
    • Deck work started March 16th.
    • Half the bridge will be done at a time.
    • The road will remain open to one lane with a temporary signal.
    • Concrete for the first half was placed on March 27th.
  • March 26, 2026

    Share March 26, 2026 on Facebook Share March 26, 2026 on Twitter Share March 26, 2026 on Linkedin Email March 26, 2026 link
    • Substructure repairs are complete.
    • Deck work started March 16th.
    • Half the bridge will be done at a time.
    • The road will remain open to one lane with a temporary signal.
    • Concrete for the first half was placed on March 27th.
    • Substructure repairs are complete.
    • Deck work started March 16th.
    • Half the bridge will be done at a time.
    • The road will remain open to one lane with a temporary signal.
    • Concrete for the first half was placed on March 27th.
  • March 19, 2026

    Share March 19, 2026 on Facebook Share March 19, 2026 on Twitter Share March 19, 2026 on Linkedin Email March 19, 2026 link
    • Substructure repairs are complete.
    • Deck work started March 16th. Half the bridge will be done at a time.
    • The road will remain open to one lane with a temporary signal.
    • Substructure repairs are complete.
    • Deck work started March 16th. Half the bridge will be done at a time.
    • The road will remain open to one lane with a temporary signal.
  • March 13, 2026

    Share March 13, 2026 on Facebook Share March 13, 2026 on Twitter Share March 13, 2026 on Linkedin Email March 13, 2026 link
    • Contractor working on substructure repairs, nearly complete.
    • Deck work anticipated to start March 16th. Half the bridge will be done at a time. The road will remain open to one lane with a temporary signal.
    • Contractor working on substructure repairs, nearly complete.
    • Deck work anticipated to start March 16th. Half the bridge will be done at a time. The road will remain open to one lane with a temporary signal.
  • March 6, 2026

    Share March 6, 2026 on Facebook Share March 6, 2026 on Twitter Share March 6, 2026 on Linkedin Email March 6, 2026 link
    • Contractor working on substructure repairs.
    • Deck work anticipated to start March 16th.
    • Half the bridge will be done at a time. The road will remain open to one lane with a temporary signal.
    • Contractor working on substructure repairs.
    • Deck work anticipated to start March 16th.
    • Half the bridge will be done at a time. The road will remain open to one lane with a temporary signal.
  • February 27, 2026

    Share February 27, 2026 on Facebook Share February 27, 2026 on Twitter Share February 27, 2026 on Linkedin Email February 27, 2026 link
    • Contractor working on substructure repairs.
    • Deck work anticipated to start in late March.
    • Contractor working on substructure repairs.
    • Deck work anticipated to start in late March.
  • February 19, 2026

    Share February 19, 2026 on Facebook Share February 19, 2026 on Twitter Share February 19, 2026 on Linkedin Email February 19, 2026 link
    • Contractor working on substructure repairs.
    • Contractor working on substructure repairs.