Munger Road Bridges
As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culverts on Munger Road, south of New Hope Road, starting the beginning of January.* Construction is expected to be complete in summer 2026.
Project Highlights
- Removing and replacing the existing bridges on Munger Road
- Reconstructing the roadway
- Filling in the sidewalk gap on the east side of Munger Road, between W. Shortcreek Street and N. Catamaran Way, including new curb, gutter, and pedestrian ramps
- Improving stormwater facilities to enhance drainage
Construction Impacts
- Munger Road will be closed during construction
- Pedestrian detours and sidewalk closures
- Lane restrictions with flaggers
- Neighborhood traffic calming will be in place to discourage cut-through traffic on residential streets
- General construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts
As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culverts on Munger Road, south of New Hope Road, starting the beginning of January.* Construction is expected to be complete in summer 2026.
Project Highlights
- Removing and replacing the existing bridges on Munger Road
- Reconstructing the roadway
- Filling in the sidewalk gap on the east side of Munger Road, between W. Shortcreek Street and N. Catamaran Way, including new curb, gutter, and pedestrian ramps
- Improving stormwater facilities to enhance drainage
Construction Impacts
- Munger Road will be closed during construction
- Pedestrian detours and sidewalk closures
- Lane restrictions with flaggers
- Neighborhood traffic calming will be in place to discourage cut-through traffic on residential streets
- General construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts
-
March 6, 2026
Share March 6, 2026 on Facebook Share March 6, 2026 on Twitter Share March 6, 2026 on Linkedin Email March 6, 2026 link- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- South Bridge precast placed.
- Forming and placing aprons.
- Installing Bridge #2001. Excavated. Precast installed. Grouting and forming for closure pour.
- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- South Bridge precast placed.
- Forming and placing aprons.
- Installing Bridge #2001. Excavated. Precast installed. Grouting and forming for closure pour.
-
February 27, 2026
Share February 27, 2026 on Facebook Share February 27, 2026 on Twitter Share February 27, 2026 on Linkedin Email February 27, 2026 link- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- South bridge removed.
- South Bridge precast placed.
- Forming footings and wingwalls.
- Installing Bridge #2001 - Excavated. Placing precast week of the February 23rd.
- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- South bridge removed.
- South Bridge precast placed.
- Forming footings and wingwalls.
- Installing Bridge #2001 - Excavated. Placing precast week of the February 23rd.
-
February 19, 2026
Share February 19, 2026 on Facebook Share February 19, 2026 on Twitter Share February 19, 2026 on Linkedin Email February 19, 2026 link- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- South bridge removed.
- South Bridge precast placed. Forming footings and wingwalls.
- Installing Bridge #2001. Excavated. Placing precast week of the February 23rd.
- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- South bridge removed.
- South Bridge precast placed. Forming footings and wingwalls.
- Installing Bridge #2001. Excavated. Placing precast week of the February 23rd.
-
February 12, 2026
Share February 12, 2026 on Facebook Share February 12, 2026 on Twitter Share February 12, 2026 on Linkedin Email February 12, 2026 link- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- South bridge removed.
- Preparing for bridge placement.
- Installing Bridge #2001 mid February.
- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- South bridge removed.
- Preparing for bridge placement.
- Installing Bridge #2001 mid February.
-
February 5, 2026
Share February 5, 2026 on Facebook Share February 5, 2026 on Twitter Share February 5, 2026 on Linkedin Email February 5, 2026 link- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- South bridge removed.
- Preparing for bridge placement.
- Installing Bridge #2001 mid February.
- Sewer work started February 2nd.
- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- South bridge removed.
- Preparing for bridge placement.
- Installing Bridge #2001 mid February.
- Sewer work started February 2nd.
-
January 30, 2026
Share January 30, 2026 on Facebook Share January 30, 2026 on Twitter Share January 30, 2026 on Linkedin Email January 30, 2026 link- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Dewatering measures installed.
- South bridge removed.
- Prepping for bridge placement.
- Installing Bridge #2001 mid February.
- Starting sewer work February 2nd.
- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Dewatering measures installed.
- South bridge removed.
- Prepping for bridge placement.
- Installing Bridge #2001 mid February.
- Starting sewer work February 2nd.
-
January 23, 2026
Share January 23, 2026 on Facebook Share January 23, 2026 on Twitter Share January 23, 2026 on Linkedin Email January 23, 2026 link- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Dewatering measures installed.
- South bridge removed.
- Prepping for bridge placement.
- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Dewatering measures installed.
- South bridge removed.
- Prepping for bridge placement.
-
January 16, 2026
Share January 16, 2026 on Facebook Share January 16, 2026 on Twitter Share January 16, 2026 on Linkedin Email January 16, 2026 link- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Dewatering measures being set up.
- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Dewatering measures being set up.
-
January 9, 2026
Share January 9, 2026 on Facebook Share January 9, 2026 on Twitter Share January 9, 2026 on Linkedin Email January 9, 2026 link- Munger Road closed during bridge replacement.
- Speed bumps installed in the adjacent neighborhoods.
- Dewatering measures being set up.
- Munger Road closed during bridge replacement.
- Speed bumps installed in the adjacent neighborhoods.
- Dewatering measures being set up.
-
December 30, 2025 - Detour Map and Information
Share December 30, 2025 - Detour Map and Information on Facebook Share December 30, 2025 - Detour Map and Information on Twitter Share December 30, 2025 - Detour Map and Information on Linkedin Email December 30, 2025 - Detour Map and Information linkBeginning Monday, January 5, Munger Road will be closed between Floating Feather Road and Streamview Drive. Only local traffic will be allowed on Munger Road between Streamview and New Hope Road. Commuters should use Brandon Road as a detour during the closure (see detour map). The road is expected to remain closed until summer 2026. The closure is part of ACHD's Munger Road Bridges project, which includes removing and replacing the existing bridges, among other improvements.

Beginning Monday, January 5, Munger Road will be closed between Floating Feather Road and Streamview Drive. Only local traffic will be allowed on Munger Road between Streamview and New Hope Road. Commuters should use Brandon Road as a detour during the closure (see detour map). The road is expected to remain closed until summer 2026. The closure is part of ACHD's Munger Road Bridges project, which includes removing and replacing the existing bridges, among other improvements.