As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culverts on Munger Road, south of New Hope Road, starting the beginning of January.* Construction is expected to be complete in summer 2026.
Project Highlights
- Removing and replacing the existing bridges on Munger Road
- Reconstructing the roadway
- Filling in the sidewalk gap on the east side of Munger Road, between W. Shortcreek Street and N. Catamaran Way, including new curb, gutter, and pedestrian ramps
- Improving stormwater facilities to enhance drainage
Construction Impacts
- Munger Road will be closed during construction
- Pedestrian detours and sidewalk closures
- Lane restrictions with flaggers
- Neighborhood traffic calming will be in place to discourage cut-through traffic on residential streets
- General construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts
As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culverts on Munger Road, south of New Hope Road, starting the beginning of January.* Construction is expected to be complete in summer 2026.
Project Highlights
- Removing and replacing the existing bridges on Munger Road
- Reconstructing the roadway
- Filling in the sidewalk gap on the east side of Munger Road, between W. Shortcreek Street and N. Catamaran Way, including new curb, gutter, and pedestrian ramps
- Improving stormwater facilities to enhance drainage
Construction Impacts
- Munger Road will be closed during construction
- Pedestrian detours and sidewalk closures
- Lane restrictions with flaggers
- Neighborhood traffic calming will be in place to discourage cut-through traffic on residential streets
- General construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts
-
May 13, 2026
Share May 13, 2026 on Facebook Share May 13, 2026 on Twitter Share May 13, 2026 on Linkedin Email May 13, 2026 link- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Paved. Signs and Stripes remaining. Landscaping ongoing.
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Paved. Signs and Stripes remaining. Landscaping ongoing.
-
May 8, 2026
Share May 8, 2026 on Facebook Share May 8, 2026 on Twitter Share May 8, 2026 on Linkedin Email May 8, 2026 link- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Sidewalk and curb being placed. Asphalt paving is scheduled for May 11th.
- South Bridge #1005 complete.
- Bridge #2001 complete.
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Sidewalk and curb being placed. Asphalt paving is scheduled for May 11th.
- South Bridge #1005 complete.
- Bridge #2001 complete.
-
May 1, 2026
Share May 1, 2026 on Facebook Share May 1, 2026 on Twitter Share May 1, 2026 on Linkedin Email May 1, 2026 link- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Sidewalk and curb being placed. Asphalt paving is scheduled for May 11th.
- South Bridge #1005 complete.
- Bridge #2001 complete.
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Sidewalk and curb being placed. Asphalt paving is scheduled for May 11th.
- South Bridge #1005 complete.
- Bridge #2001 complete.
-
April 24, 2026
Share April 24, 2026 on Facebook Share April 24, 2026 on Twitter Share April 24, 2026 on Linkedin Email April 24, 2026 link- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Base placed. Prepping for curb & sidewalk.
- South Bridge #1005 complete.
- Bridge #2001 complete.
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Base placed. Prepping for curb & sidewalk.
- South Bridge #1005 complete.
- Bridge #2001 complete.
-
April 16, 2026
Share April 16, 2026 on Facebook Share April 16, 2026 on Twitter Share April 16, 2026 on Linkedin Email April 16, 2026 link- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Base placed. Prepping for curb & sidewalk.
- South Bridge #1005 complete.
- Bridge #2001 complete.
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Base placed. Prepping for curb & sidewalk.
- South Bridge #1005 complete.
- Bridge #2001 complete.
-
April 10, 2026
Share April 10, 2026 on Facebook Share April 10, 2026 on Twitter Share April 10, 2026 on Linkedin Email April 10, 2026 link- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Base placed. Prepping for curb & sidewalk.
- South Bridge #1005 - complete.
- Bridge #2001 - complete.
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Base placed. Prepping for curb & sidewalk.
- South Bridge #1005 - complete.
- Bridge #2001 - complete.
-
April 2, 2026
Share April 2, 2026 on Facebook Share April 2, 2026 on Twitter Share April 2, 2026 on Linkedin Email April 2, 2026 link- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Munger Road - Excavating for road base.
- South Bridge - precast placed. Backfilled.
- Installing Bridge #2001 - Backfilling. Removing dewatering set up. Replacing irrigation pipe.
- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Munger Road - Excavating for road base.
- South Bridge - precast placed. Backfilled.
- Installing Bridge #2001 - Backfilling. Removing dewatering set up. Replacing irrigation pipe.
-
March 26, 2026
Share March 26, 2026 on Facebook Share March 26, 2026 on Twitter Share March 26, 2026 on Linkedin Email March 26, 2026 link- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- Munger Road - Excavating for road base.
- South Bridge precast placed. Backfilled.
- Installing Bridge #2001 - Backfilling. Removing dewatering set up.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- Munger Road - Excavating for road base.
- South Bridge precast placed. Backfilled.
- Installing Bridge #2001 - Backfilling. Removing dewatering set up.
-
March 19, 2026
Share March 19, 2026 on Facebook Share March 19, 2026 on Twitter Share March 19, 2026 on Linkedin Email March 19, 2026 link- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- South Bridge precast placed.
- Backfilling and placing riprap.
- Installing Bridge #2001. Excavated. Precast installed. Grouting and forming for closure pour.
- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- South Bridge precast placed.
- Backfilling and placing riprap.
- Installing Bridge #2001. Excavated. Precast installed. Grouting and forming for closure pour.
-
March 13, 2026
Share March 13, 2026 on Facebook Share March 13, 2026 on Twitter Share March 13, 2026 on Linkedin Email March 13, 2026 link- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- South Bridge precast placed. Backfilling and placing riprap.
- Installing Bridge #2001. Excavated. Precast installed. Grouting and forming for closure pour.
- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- South Bridge precast placed. Backfilling and placing riprap.
- Installing Bridge #2001. Excavated. Precast installed. Grouting and forming for closure pour.
Page last updated: 13 May 2026, 04:37 PM
Follow Project
Stay informed
Subscribe for project updates
21 members of your community are following this project
Who's Listening
-
Project Manager
Phone 208-387-6100 Email connect@achdidaho.org -
Construction Coordinator
Phone 208-387-6100 Email connect@achdidaho.org