Ustick Road, Ten Mile Road to Linder Road

Share Ustick Road, Ten Mile Road to Linder Road on Facebook Share Ustick Road, Ten Mile Road to Linder Road on X (formerly Twitter) Share Ustick Road, Ten Mile Road to Linder Road on Linkedin Email Ustick Road, Ten Mile Road to Linder Road link

The Ada County Highway District (ACHD) is widening Ustick Road, Ten Mile Road to Linder Road. The purpose of this project is to improve traffic flow and increase safety for all users. Work is expected to be complete in late 2026.*

Project Description

  • Widen Ustick Road, Ten Mile to Linder, to two travel lanes in each direction with a continuous center turn lane.
  • Raised medians will be located within the center lane in areas where they do not restrict access from public streets and/or driveways.
  • Construct a 10-foot, multi-use pathway on the north and south sides of Ustick Road.
  • Install a traffic signal at the intersection of Ustick Road and Towerbridge Way.
  • Construct a new pedestrian bridge crossing over Five Mile Creek to provide a connection with the multi-use pathway.
  • The multi-use pathway will transition to bike lanes and attached sidewalks at the Ustick Road and Ten Mile Road intersection.

Traffic and Construction Impacts

  • Road closures are expected during construction
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts and maintain access

*Construction schedules may change

The Ada County Highway District (ACHD) is widening Ustick Road, Ten Mile Road to Linder Road. The purpose of this project is to improve traffic flow and increase safety for all users. Work is expected to be complete in late 2026.*

Project Description

  • Widen Ustick Road, Ten Mile to Linder, to two travel lanes in each direction with a continuous center turn lane.
  • Raised medians will be located within the center lane in areas where they do not restrict access from public streets and/or driveways.
  • Construct a 10-foot, multi-use pathway on the north and south sides of Ustick Road.
  • Install a traffic signal at the intersection of Ustick Road and Towerbridge Way.
  • Construct a new pedestrian bridge crossing over Five Mile Creek to provide a connection with the multi-use pathway.
  • The multi-use pathway will transition to bike lanes and attached sidewalks at the Ustick Road and Ten Mile Road intersection.

Traffic and Construction Impacts

  • Road closures are expected during construction
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts and maintain access

*Construction schedules may change

  • July 9, 2026

    Share July 9, 2026 on Facebook Share July 9, 2026 on X (formerly Twitter) Share July 9, 2026 on Linkedin Email July 9, 2026 link
    • Ustick Road closure started December 1st.
    • Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
    • Contactor has completed the installation of the retaining wall.
    • Contractor has completed the subgrade excavation from east to west along Ustick, and has started importing base material.
    • City of Meridian water work is ongoing – Mainline is complete, services to follow.
    • Seepage bed installation work is complete.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing – complete.
    • First placement of the moment slab along the retaining wall was placed this week.
    • Ustick Road closure started December 1st.
    • Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
    • Contactor has completed the installation of the retaining wall.
    • Contractor has completed the subgrade excavation from east to west along Ustick, and has started importing base material.
    • City of Meridian water work is ongoing – Mainline is complete, services to follow.
    • Seepage bed installation work is complete.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing – complete.
    • First placement of the moment slab along the retaining wall was placed this week.
  • July 1, 2026

    Share July 1, 2026 on Facebook Share July 1, 2026 on X (formerly Twitter) Share July 1, 2026 on Linkedin Email July 1, 2026 link
    • Contactor has completed the installation of the retaining wall.
    • Contractor has completed the subgrade excavation from east to west along Ustick, and has started importing base material.
    • City of Meridian water work is ongoing – Mainline is complete, services to follow.
    • Seepage bed installation work is complete.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing – nearly complete.
    • First placement of the moment slab along the retaining wall is scheduled to be placed next week.
    • Contactor has completed the installation of the retaining wall.
    • Contractor has completed the subgrade excavation from east to west along Ustick, and has started importing base material.
    • City of Meridian water work is ongoing – Mainline is complete, services to follow.
    • Seepage bed installation work is complete.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing – nearly complete.
    • First placement of the moment slab along the retaining wall is scheduled to be placed next week.
  • June 26, 2026

    Share June 26, 2026 on Facebook Share June 26, 2026 on X (formerly Twitter) Share June 26, 2026 on Linkedin Email June 26, 2026 link
    • Ustick Road closure started December 1st.
    • Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
    • Contactor has completed the installation of the retaining wall.
    • Contractor continues to subgrade from east to west along Ustick. City of Meridian water work is ongoing – Mainline is complete, services to follow.
    • Seepage bed installation work is ongoing.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing.
    • First placement of the moment slab along the retaining wall is scheduled to be placed this week.
    • Ustick Road closure started December 1st.
    • Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
    • Contactor has completed the installation of the retaining wall.
    • Contractor continues to subgrade from east to west along Ustick. City of Meridian water work is ongoing – Mainline is complete, services to follow.
    • Seepage bed installation work is ongoing.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing.
    • First placement of the moment slab along the retaining wall is scheduled to be placed this week.
  • June 18, 2026

    Share June 18, 2026 on Facebook Share June 18, 2026 on X (formerly Twitter) Share June 18, 2026 on Linkedin Email June 18, 2026 link
    • Contactor has completed the installation of the retaining wall.
    • Contractor continues to subgrade from east to west along Ustick.
    • City of Meridian water work is ongoing – Mainline is complete, services to follow.
    • Seepage bed installation work is ongoing.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing.
    • Contactor has completed the installation of the retaining wall.
    • Contractor continues to subgrade from east to west along Ustick.
    • City of Meridian water work is ongoing – Mainline is complete, services to follow.
    • Seepage bed installation work is ongoing.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing.
  • June 12, 2026

    Share June 12, 2026 on Facebook Share June 12, 2026 on X (formerly Twitter) Share June 12, 2026 on Linkedin Email June 12, 2026 link
    • Contactor has completed the installation of the retaining wall.
    • Contractor has started subgrading from east to west along Ustick.
    • City of Meridian water work started this week.
    • Seepage bed installation work is ongoing.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing.
    • Contactor has completed the installation of the retaining wall.
    • Contractor has started subgrading from east to west along Ustick.
    • City of Meridian water work started this week.
    • Seepage bed installation work is ongoing.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing.
  • June 5, 2026

    Share June 5, 2026 on Facebook Share June 5, 2026 on X (formerly Twitter) Share June 5, 2026 on Linkedin Email June 5, 2026 link
    • Contactor has completed the installation of the retaining wall.
    • Contractor has started subgrading from east to west along Ustick.
    • City of Meridian water work started this week.
    • Seepage bed installation work is ongoing.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing.
    • Contactor has completed the installation of the retaining wall.
    • Contractor has started subgrading from east to west along Ustick.
    • City of Meridian water work started this week.
    • Seepage bed installation work is ongoing.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing.
  • May 29, 2026

    Share May 29, 2026 on Facebook Share May 29, 2026 on X (formerly Twitter) Share May 29, 2026 on Linkedin Email May 29, 2026 link
    • Ustick Road closure started December 1st.
    • Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
    • Contactor continues excavating/backfilling from the east for the retaining wall along Five Mile Creek.
    • Contractor continues setting baskets for the retaining wall.
    • Contractor is now above ordinary high water.
    • Contractor has started subgrading from east to west along Ustick.
    • City of Meridian water work is expected to start this week.
    • Seepage bed installation work is ongoing.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing.
    • Ustick Road closure started December 1st.
    • Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
    • Contactor continues excavating/backfilling from the east for the retaining wall along Five Mile Creek.
    • Contractor continues setting baskets for the retaining wall.
    • Contractor is now above ordinary high water.
    • Contractor has started subgrading from east to west along Ustick.
    • City of Meridian water work is expected to start this week.
    • Seepage bed installation work is ongoing.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing.
  • May 21, 2026

    Share May 21, 2026 on Facebook Share May 21, 2026 on X (formerly Twitter) Share May 21, 2026 on Linkedin Email May 21, 2026 link
    • Roadway milling/removal is complete for a portion of Ustick.
    • Contactor continues excavating/backfilling from the east for the retaining wall along Five Mile Creek.
    • Contractor continues setting baskets for the retaining wall.
    • Contractor is now above ordinary high water.
    • Clearing and grubbing work is ongoing.
    • Seepage bed installation work is ongoing.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing.
    • Roadway milling/removal is complete for a portion of Ustick.
    • Contactor continues excavating/backfilling from the east for the retaining wall along Five Mile Creek.
    • Contractor continues setting baskets for the retaining wall.
    • Contractor is now above ordinary high water.
    • Clearing and grubbing work is ongoing.
    • Seepage bed installation work is ongoing.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing.
  • May 13, 2026

    Share May 13, 2026 on Facebook Share May 13, 2026 on X (formerly Twitter) Share May 13, 2026 on Linkedin Email May 13, 2026 link
    • Ustick Road closure started December 1st.
    • Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
    • Roadway milling/removal is complete for a portion of Ustick.
    • Contactor continues excavating/backfilling from the east for the retaining wall along Five Mile Creek.
    • Contractor continues setting baskets for the retaining wall.
    • Contractor is now above ordinary high water.
    • Clearing and grubbing work is ongoing.
    • Seepage bed installation work is ongoing.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing.
    • Ustick Road closure started December 1st.
    • Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
    • Roadway milling/removal is complete for a portion of Ustick.
    • Contactor continues excavating/backfilling from the east for the retaining wall along Five Mile Creek.
    • Contractor continues setting baskets for the retaining wall.
    • Contractor is now above ordinary high water.
    • Clearing and grubbing work is ongoing.
    • Seepage bed installation work is ongoing.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing.
  • May 8, 2026

    Share May 8, 2026 on Facebook Share May 8, 2026 on X (formerly Twitter) Share May 8, 2026 on Linkedin Email May 8, 2026 link
    • Ustick Road closure started December 1st.
    • Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
    • Roadway milling/removal is complete for a portion of Ustick.
    • Contactor continues excavating/backfilling from the east for the retaining wall along Five Mile Creek.
    • Contractor continues setting baskets for the retaining wall.
    • Contractor is now above ordinary high water.
    • Clearing and grubbing work is ongoing.
    • Seepage bed installation work is ongoing.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing.
    • Ustick Road closure started December 1st.
    • Message boards, traffic calming throughout the adjacent neighborhoods, etc. have been installed.
    • Roadway milling/removal is complete for a portion of Ustick.
    • Contactor continues excavating/backfilling from the east for the retaining wall along Five Mile Creek.
    • Contractor continues setting baskets for the retaining wall.
    • Contractor is now above ordinary high water.
    • Clearing and grubbing work is ongoing.
    • Seepage bed installation work is ongoing.
    • Contractor continues placement of sidewalk/MUP on the east end of the project.
    • Utility relocations are ongoing.
Page last updated: 09 Jul 2026, 03:36 PM