2022 Pavement and Pedestrian Improvements
This project is substantially complete.
The Ada County Highway District (ACHD) will be reconstructing several streets in Ada County as part of a federal aid project to improve pavement conditions and upgrade the streets for all users.
Work could include:
- Reconstructing streets or removing and replacing pavement to improve roadway conditions
- Filling in sidewalk gaps to increase connectivity
- Adding bulb-outs and signalized pedestrian crossings where appropriate to improve safety
- Installing Accessible Pedestrian Signals (APS) and pedestrian push buttons.
- Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA).
Street Segments:
- 9th St., Idaho St. to Bannock St. - Replace existing asphalt with concrete; install pedestrian bulb outs; replace existing pedestrian ramps; replace existing driveway approaches and traffic signals.
- 20th St., Lemp St. to Irene St. - Reconstruct roadway; replace existing pedestrian ramps; replace damaged sidewalk
- Amity Rd., Enterprise St. to Production St. - Reconstruct roadway
- Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
- Castle Hill Way, Castle Dr. to Drawbridge Dr. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps; replace existing driveway approach
- Drawbridge Dr., West End to Castle Hill Way - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
- Enterprise St., Amity Rd. to Commerce Ave. - Reconstruct roadway; replace existing pedestrian ramp
- Maple Grove Rd., I-84 Bridge to Franklin Rd. - Remove and replace pavement; install a pedestrian hybrid beacon at Maple Grove and Shoup; replace existing pedestrian ramps
- Morris Hill Rd., west of Liberty St. to Hartman St. - Reconstruct roadway; replace existing pedestrian ramps
- Roosevelt St., Emerald St. to Irving St. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps; install new sidewalk to fill gaps; replace existing driveway approaches; rebuild existing speed humps
- Spaulding St., Phillippi St. to Orchard St. - Reconstruct roadway; install bulb-outs; replace existing pedestrian ramps; rebuild existing speed humps
- Turret Way, Drawbridge Dr. to Castle Dr. - Reconstruct roadway; install bulb-outs; replace existing pedestrian ramps
Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.
The Ada County Highway District (ACHD) will be reconstructing several streets in Ada County as part of a federal aid project to improve pavement conditions and upgrade the streets for all users.
Work could include:
- Reconstructing streets or removing and replacing pavement to improve roadway conditions
- Filling in sidewalk gaps to increase connectivity
- Adding bulb-outs and signalized pedestrian crossings where appropriate to improve safety
- Installing Accessible Pedestrian Signals (APS) and pedestrian push buttons.
- Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA).
Street Segments:
- 9th St., Idaho St. to Bannock St. - Replace existing asphalt with concrete; install pedestrian bulb outs; replace existing pedestrian ramps; replace existing driveway approaches and traffic signals.
- 20th St., Lemp St. to Irene St. - Reconstruct roadway; replace existing pedestrian ramps; replace damaged sidewalk
- Amity Rd., Enterprise St. to Production St. - Reconstruct roadway
- Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
- Castle Hill Way, Castle Dr. to Drawbridge Dr. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps; replace existing driveway approach
- Drawbridge Dr., West End to Castle Hill Way - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
- Enterprise St., Amity Rd. to Commerce Ave. - Reconstruct roadway; replace existing pedestrian ramp
- Maple Grove Rd., I-84 Bridge to Franklin Rd. - Remove and replace pavement; install a pedestrian hybrid beacon at Maple Grove and Shoup; replace existing pedestrian ramps
- Morris Hill Rd., west of Liberty St. to Hartman St. - Reconstruct roadway; replace existing pedestrian ramps
- Roosevelt St., Emerald St. to Irving St. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps; install new sidewalk to fill gaps; replace existing driveway approaches; rebuild existing speed humps
- Spaulding St., Phillippi St. to Orchard St. - Reconstruct roadway; install bulb-outs; replace existing pedestrian ramps; rebuild existing speed humps
- Turret Way, Drawbridge Dr. to Castle Dr. - Reconstruct roadway; install bulb-outs; replace existing pedestrian ramps
Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.
This project is substantially complete.
-
July 7, 2023
Share July 7, 2023 on Facebook Share July 7, 2023 on Twitter Share July 7, 2023 on Linkedin Email July 7, 2023 link-
20th Street, Lemp Street to Irene Street
- Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron to Irene will be closed first, after which the segment between Ridenbaugh to Hazel will be closed.
-
Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
- Pipe work is complete.
- Concrete work is nearly complete.
- Milling and paving is scheduled for the week of July 10th.
-
Castle Hill Way, Castle Drive to Drawbridge Drive
- Pipe work is complete. Concrete work started July 3rd and in on-going.
-
Turret Way, Drawbridge Drive to Castle Drive
- Pipe and storm drain work is complete.
-
Morris Hill Road, west of Liberty Street to Hartman Street
- Complete.
-
Spaulding Street, Philippi Street to Orchard Street
- Complete.
-
Roosevelt Street, Emerald Street to Irving Street
- Complete.
-
Maple Grove Road, I-84 Overpass to Franklin Road
- Concrete work is complete.
-
Amity Road, Enterprise Street to Production Avenue
- Roadway work started July 6th. Amity Road will be closed during the work, which is expected to last a month.
-
Enterprise Street, Amity Road to Commerce Avenue
- Concrete and pipe work are complete.
-
20th Street, Lemp Street to Irene Street
-
June 30, 2023
Share June 30, 2023 on Facebook Share June 30, 2023 on Twitter Share June 30, 2023 on Linkedin Email June 30, 2023 link-
20th Street, Lemp Street to Irene Street
- Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron to Irene will be closed first, after which the segment between Ridenbaugh to Hazel will be closed.
-
Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
- Pipe work is complete.
- Concrete work is nearly complete.
- Milling and paving is scheduled for the week of July 10th.
-
Castle Hill Way, Castle Drive to Drawbridge Drive
- Pipe work is complete. Concrete work anticipated to start the week of July 3rd.
-
Turret Way, Drawbridge Drive to Castle Drive
- Pipe and storm drain work began June 12th. Turret Way will be closed between Kennecott St and Hallmark Street during the work.
-
Morris Hill Road, west of Liberty Street to Hartman Street
- Complete.
-
Spaulding Street, Philippi Street to Orchard Street
- Complete.
-
Roosevelt Street, Emerald Street to Irving Street
- Complete.
-
Maple Grove Road, I-84 Overpass to Franklin Road
- Concrete work is complete.
-
Amity Road, Enterprise Street to Production Avenue
- Roadway work is anticipated to start July 6th. Amity Road will be closed during the work, which is expected to last a month.
-
Enterprise Street, Amity Road to Commerce Avenue
- Concrete and pipe work are complete.
-
20th Street, Lemp Street to Irene Street
-
June 23, 2023
Share June 23, 2023 on Facebook Share June 23, 2023 on Twitter Share June 23, 2023 on Linkedin Email June 23, 2023 link-
20th Street, Lemp Street to Irene Street
- Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron to Irene will be close first, after which the segment between Ridenbaugh to Hazel will be closed.
-
Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
- Pipe work is complete.
- Concrete started May 29th and is on-going
-
Castle Hill Way, Castle Drive to Drawbridge Drive
- Pipe work is complete. Concrete work anticipated to start the week of June 26th.
-
Turret Way, Drawbridge Drive to Castle Drive
- Pipe and storm drain work began Jun 12th. Turret Way will be closed between Kennecott St and Hallmark Street during the work.
-
Morris Hill Road, west of Liberty Street to Hartman Street
- Complete.
-
Spaulding Street, Philippi Street to Orchard Street
- Complete.
-
Roosevelt Street, Emerald Street to Irving Street
- Complete.
-
Maple Grove Road, I-84 Overpass to Franklin Road
- Concrete work is complete.
-
Amity Road, Enterprise Street to Production Avenue
- Roadway work is anticipated to start July 6th. Amity Road will be closed during the work, which is expected to last a month.
-
Enterprise Street, Amity Road to Commerce Avenue
- Concrete and pipe work are complete.
-
20th Street, Lemp Street to Irene Street
-
June 16, 2023
Share June 16, 2023 on Facebook Share June 16, 2023 on Twitter Share June 16, 2023 on Linkedin Email June 16, 2023 link-
20th Street, Lemp Street to Irene Street
- Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron to Irene will be close first, after which the segment between Ridenbaugh to Hazel will be closed.
-
Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
- Pipe work is complete.
- Concrete started May 29th and is on-going
-
Castle Hill Way, Castle Drive to Drawbridge Drive
- Pipe work is complete.
-
Turret Way, Drawbridge Drive to Castle Drive
- Pipe and storm drain work began Jun 12th. Turret Way will be closed between Kennecott St and Hallmark Street during the work.
-
Morris Hill Road, west of Liberty Street to Hartman Street
- Roadway work is substantially complete. Minor work remains, including manhole adjustments and permanent striping.
-
Spaulding Street, Philippi Street to Orchard Street
- Roadway work is substantially complete. Minor work remains, including manhole adjustments and permanent striping.
-
Roosevelt Street, Emerald Street to Irving Street
- Concrete work is complete.
- Milling and paving started June 14th. Paving is scheduled to be complete on June 16th.
-
Maple Grove Road, I-84 Overpass to Franklin Road
- Concrete work is complete.
-
Amity Road, Enterprise Street to Production Avenue
- Roadway work is anticipated to start July 6th. Amity Road will be closed during the work, which is expected to last a month.
-
Enterprise Street, Amity Road to Commerce Avenue
- Concrete and pipe work are complete.
-
20th Street, Lemp Street to Irene Street
-
June 9, 2023
Share June 9, 2023 on Facebook Share June 9, 2023 on Twitter Share June 9, 2023 on Linkedin Email June 9, 2023 link- 9th St., Idaho St. to Bannock St. - Replace existing asphalt with concrete; install pedestrian bulb outs; replace existing pedestrian ramps; replace existing driveway approaches
- 20th St., Lemp St. to Irene St. - Waterline work by Veolia anticipated to start June 12th. 20th Street will be closed during the work, which is expected to last two months.
- Amity Rd., Enterprise St. to Production St. - Reconstruct roadway
- Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Pipe work is complete. Concrete work started May 29th and is ongoing.
- Castle Hill Way, Castle Dr. to Drawbridge Dr. - Pipe work is expected to be completed June 9th.
- Drawbridge Dr., West End to Castle Hill Way - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
- Enterprise St., Amity Rd. to Commerce Ave. - Pipe work is complete. Concrete work is complete.
- Maple Grove Rd., I-84 Bridge to Franklin Rd. - Concrete work is complete.
- Morris Hill Rd., west of Liberty St. to Hartman St. - Concrete work is complete. Pipework is complete. Roadway work began May 30th. Morris Hill Road will be closed during the construction work, which is anticipated to last six weeks.
- Roosevelt St., Emerald St. to Irving St. - Concrete work is complete. Milling and paving is scheduled for the week of June 12th.
- Spaulding St., Phillippi St. to Orchard St. - Concrete work is complete. Pipe work is complete. Asphalt paving is complete. Minor work remains including speed hump installation, manhole adjustments, and permanent striping.
- Turret Way, Drawbridge Dr. to Castle Dr. - Pipe and storm drain work is scheduled to begin June 12th. Turret Way will be closed between Kennecott Street and Hallmark Street during the work.
-
June 2, 2023
Share June 2, 2023 on Facebook Share June 2, 2023 on Twitter Share June 2, 2023 on Linkedin Email June 2, 2023 link- 9th St., Idaho St. to Bannock St. - Replace existing asphalt with concrete; install pedestrian bulb outs; replace existing pedestrian ramps; replace existing driveway approaches
- 20th St., Lemp St. to Irene St. - Waterline work by Veolia anticipated to start June 12th. 20th Street will be closed during the work, which is expected to last two months.
- Amity Rd., Enterprise St. to Production St. - Reconstruct roadway
- Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Pipe work is complete. Concrete work started May 29th and is ongoing.
- Castle Hill Way, Castle Dr. to Drawbridge Dr. - Pipe work is scheduled to begin June 5th. Castle Hill Way will be closed during the work.
- Drawbridge Dr., West End to Castle Hill Way - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
- Enterprise St., Amity Rd. to Commerce Ave. - Pipe work is complete. Concrete work is complete.
- Maple Grove Rd., I-84 Bridge to Franklin Rd. - Concrete work is complete.
- Morris Hill Rd., west of Liberty St. to Hartman St. - Concrete work is complete. Pipework is complete. Roadway work began may 30th. Morris Hill Road will be closed during the construction work, which is anticipated to last six weeks.
- Roosevelt St., Emerald St. to Irving St. - Concrete work is complete.
- Spaulding St., Phillippi St. to Orchard St. - Concrete work is complete. Pipe work is complete. Spaulding Street will be closed during the work, which is anticipated to last a month. Asphalt paving is scheduled to be complete the week of June 5th.
- Turret Way, Drawbridge Dr. to Castle Dr. - Waterline work by Veolia started May 4th. Turret Way will be closed during Veolia's work through June 4th.
-
May 26, 2023
Share May 26, 2023 on Facebook Share May 26, 2023 on Twitter Share May 26, 2023 on Linkedin Email May 26, 2023 link- 9th St., Idaho St. to Bannock St. - Replace existing asphalt with concrete; install pedestrian bulb outs; replace existing pedestrian ramps; replace existing driveway approaches
- 20th St., Lemp St. to Irene St. - Waterline work by Veolia anticipated to start June 12th. 20th Street will be closed during the work, which is expected to last two months.
- Amity Rd., Enterprise St. to Production St. - Reconstruct roadway
- Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Pipe work is complete. Concrete work is anticipated to start the week of May 29th.
- Castle Hill Way, Castle Dr. to Drawbridge Dr. - Pipe work is scheduled to begin June 5th. Castle Hill Way will be closed during the work.
- Drawbridge Dr., West End to Castle Hill Way - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
- Enterprise St., Amity Rd. to Commerce Ave. - Pipe work is complete. Concrete started May 22nd and is ongoing.
- Maple Grove Rd., I-84 Bridge to Franklin Rd. - Concrete work is complete.
- Morris Hill Rd., west of Liberty St. to Hartman St. - Concrete work is complete. Pipework is complete. Roadway work is scheduled to begin May 30th. Morris Hill Road will be closed during the construction work, which is anticipated to last six weeks.
- Roosevelt St., Emerald St. to Irving St. - Concrete work is nearly complete.
- Spaulding St., Phillippi St. to Orchard St. - Concrete work is complete. Pipe work is complete. Roadway work started on May 8th. Spaulding Street will be closed during the work, which is anticipated to last a month. Asphalt paving is scheduled for May 26th, weather dependent.
- Turret Way, Drawbridge Dr. to Castle Dr. - Waterline work by Veolia started May 4th. Turret Way will be closed during Veolia's work through June 4th.
-
May 19, 2023
Share May 19, 2023 on Facebook Share May 19, 2023 on Twitter Share May 19, 2023 on Linkedin Email May 19, 2023 link- 9th St., Idaho St. to Bannock St. - Replace existing asphalt with concrete; install pedestrian bulb outs; replace existing pedestrian ramps; replace existing driveway approaches
- 20th St., Lemp St. to Irene St. - Reconstruct roadway; replace existing pedestrian ramps; replace damaged sidewalk
- Amity Rd., Enterprise St. to Production St. - Reconstruct roadway
- Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Pipework complete.
- Castle Hill Way, Castle Dr. to Drawbridge Dr. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps; replace existing driveway approach
- Drawbridge Dr., West End to Castle Hill Way - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
- Enterprise St., Amity Rd. to Commerce Ave. - Reconstruct roadway; replace existing pedestrian ramp
- Maple Grove Rd., I-84 Bridge to Franklin Rd. - Concrete work is complete. Roadway work is scheduled to begin late June. Maple Grove will be closed during the work which is anticipated to last a month.
- Morris Hill Rd., west of Liberty St. to Hartman St. - Concrete work is complete. Pipework is complete.
- Roosevelt St., Emerald St. to Irving St. - Concrete work started May 9th.
- Spaulding St., Phillippi St. to Orchard St. - Concrete work is complete. Pipework is complete. Roadway work started May 8th. Spaulding will be closed during the work - anticipated to last a month.
- Turret Way, Drawbridge Dr. to Castle Dr. - Waterline work by Veolia started May 4th. Turret Way will be closed during Veolia's work.
-
May 12, 2023
Share May 12, 2023 on Facebook Share May 12, 2023 on Twitter Share May 12, 2023 on Linkedin Email May 12, 2023 link- 9th Street, Idaho Street to Bannock Street
- 20th Street, Lemp Street to Irene Street
-
Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
- Pipe work is complete.
- Castle Hill Way, Castle Drive to Drawbridge Drive
- Drawbridge Drive, west of Crimson Drive to Turret Way
-
Turret Way, Drawbridge Drive to Castle Drive
- Waterline work by Veolia started May 4th.
- Turret Way will be closed during Veolia’s work.
-
Morris Hill Road, west of Liberty Street to Hartman Street
- Concrete work is ongoing.
- Pipe work is complete.
-
Spaulding Street, Philippi Street to Orchard Street
- Pipe work is complete.
- Concrete work is complete.
- Roadway work started May 8th. Spaulding Street will be closed during the work, which is anticipated to last a month.
-
Roosevelt Street, Emerald Street to Irving Street
- Concrete work started May 9th.
-
Maple Grove Road, I-84 Overpass to Franklin Road
- Concrete work is complete.
- Roadway work is scheduled to begin June 8th. Maple Grove Road will be closed during the work, which is anticipated to last a month.
- Amity Road, Enterprise Street to Production Avenue
- Enterprise Street, Amity Road to Commerce Avenue
-
May 5, 2022
Share May 5, 2022 on Facebook Share May 5, 2022 on Twitter Share May 5, 2022 on Linkedin Email May 5, 2022 link- 9th Street, Idaho Street to Bannock Street
- 20th Street, Lemp Street to Irene Street
-
Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
- Pipe work is complete.
- Castle Hill Way, Castle Drive to Drawbridge Drive
- Drawbridge Drive, west of Crimson Drive to Turret Way
-
Turret Way, Drawbridge Drive to Castle Drive
- Waterline work by Veolia started May 4th.
- Turret Way will be closed during Veolia’s work.
-
Morris Hill Road, west of Liberty Street to Hartman Street
- Concrete work is ongoing.
- Pipe work is complete.
-
Spaulding Street, Philippi Street to Orchard Street
- Concrete work is complete.
- Pipe work is complete.
- Roadway work is anticipated to start May 8th. Spaulding Street will be closed during the work, which is anticipated to last a month.
-
Roosevelt Street, Emerald Street to Irving Street
- Concrete work is anticipated to start the week of May 8th.
-
Maple Grove Road, I-84 Overpass to Franklin Road
- Concrete work started April 5th. Lane restrictions will be in place for the duration of the work.
- Roadway work is scheduled to begin June 8th. Maple Grove Road will be closed during the work, which is anticipated to last a month.
- Amity Road, Enterprise Street to Production Avenue
- Enterprise Street, Amity Road to Commerce Avenue
Who's Listening
-
Construction Supervisor
Phone 208-387-6100 Email projects@achdidaho.org -
Community and Business Relations Coordinator
Phone 208-387-6100 Email projects@achdidaho.org
Documents
- Fall 2021 Public Outreach
-
Project Designs
- 9th St., Idaho St. to Bannock St. Design (440 KB) (pdf)
- 20th St., Lemp St. to Irene St. Design (942 KB) (pdf)
- Amity Rd., Enterprise St. to Production St. Design (577 KB) (pdf)
- Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. Design (653 KB) (pdf)
- Castle Hill Way, Castle Dr. to Drawbridge Dr. Design (740 KB) (pdf)
- Drawbridge Dr., West End to Castle Hill Way Design (634 KB) (pdf)
- Enterprise St., Amity Rd. to Commerce Ave. Design (562 KB) (pdf)
- Maple Grove Rd., I-84 Bridge to Franklin Rd. Design (647 KB) (pdf)
- Morris Hill Rd., west of Liberty St. to Hartman St. Design (435 KB) (pdf)
- Spaulding St., Phillippi St. to Orchard St. Design (536 KB) (pdf)
- Roosevelt St., Emerald St. to Irving St. Design (499 KB) (pdf)
- Turret Way, Drawbridge Dr. to Castle Dr. Design (694 KB) (pdf)
Timeline
-
2021
2022 Pavement and Pedestrian Improvements has finished this stageDesign started
-
Fall 2021
2022 Pavement and Pedestrian Improvements has finished this stageSeek public feedback
-
2022
2022 Pavement and Pedestrian Improvements has finished this stageFinalize design
-
2022/2023
2022 Pavement and Pedestrian Improvements is currently at this stageConstruction