2022 Pavement and Pedestrian Improvements

Share 2022 Pavement and Pedestrian Improvements on Facebook Share 2022 Pavement and Pedestrian Improvements on Twitter Share 2022 Pavement and Pedestrian Improvements on Linkedin Email 2022 Pavement and Pedestrian Improvements link

This project is substantially complete. 

The Ada County Highway District (ACHD) will be reconstructing several streets in Ada County as part of a federal aid project to improve pavement conditions and upgrade the streets for all users.

Work could include:

  • Reconstructing streets or removing and replacing pavement to improve roadway conditions
  • Filling in sidewalk gaps to increase connectivity
  • Adding bulb-outs and signalized pedestrian crossings where appropriate to improve safety
  • Installing Accessible Pedestrian Signals (APS) and pedestrian push buttons.
  • Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA).

Street Segments:

  • 9th St., Idaho St. to Bannock St. - Replace existing asphalt with concrete; install pedestrian bulb outs; replace existing pedestrian ramps; replace existing driveway approaches and traffic signals.
  • 20th St., Lemp St. to Irene St. - Reconstruct roadway; replace existing pedestrian ramps; replace damaged sidewalk
  • Amity Rd., Enterprise St. to Production St. - Reconstruct roadway
  • Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
  • Castle Hill Way, Castle Dr. to Drawbridge Dr. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps; replace existing driveway approach
  • Drawbridge Dr., West End to Castle Hill Way - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
  • Enterprise St., Amity Rd. to Commerce Ave. - Reconstruct roadway; replace existing pedestrian ramp
  • Maple Grove Rd., I-84 Bridge to Franklin Rd. - Remove and replace pavement; install a pedestrian hybrid beacon at Maple Grove and Shoup; replace existing pedestrian ramps
  • Morris Hill Rd., west of Liberty St. to Hartman St. - Reconstruct roadway; replace existing pedestrian ramps
  • Roosevelt St., Emerald St. to Irving St. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps; install new sidewalk to fill gaps; replace existing driveway approaches; rebuild existing speed humps
  • Spaulding St., Phillippi St. to Orchard St. - Reconstruct roadway; install bulb-outs; replace existing pedestrian ramps; rebuild existing speed humps
  • Turret Way, Drawbridge Dr. to Castle Dr. - Reconstruct roadway; install bulb-outs; replace existing pedestrian ramps

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

The Ada County Highway District (ACHD) will be reconstructing several streets in Ada County as part of a federal aid project to improve pavement conditions and upgrade the streets for all users.

Work could include:

  • Reconstructing streets or removing and replacing pavement to improve roadway conditions
  • Filling in sidewalk gaps to increase connectivity
  • Adding bulb-outs and signalized pedestrian crossings where appropriate to improve safety
  • Installing Accessible Pedestrian Signals (APS) and pedestrian push buttons.
  • Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA).

Street Segments:

  • 9th St., Idaho St. to Bannock St. - Replace existing asphalt with concrete; install pedestrian bulb outs; replace existing pedestrian ramps; replace existing driveway approaches and traffic signals.
  • 20th St., Lemp St. to Irene St. - Reconstruct roadway; replace existing pedestrian ramps; replace damaged sidewalk
  • Amity Rd., Enterprise St. to Production St. - Reconstruct roadway
  • Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
  • Castle Hill Way, Castle Dr. to Drawbridge Dr. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps; replace existing driveway approach
  • Drawbridge Dr., West End to Castle Hill Way - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
  • Enterprise St., Amity Rd. to Commerce Ave. - Reconstruct roadway; replace existing pedestrian ramp
  • Maple Grove Rd., I-84 Bridge to Franklin Rd. - Remove and replace pavement; install a pedestrian hybrid beacon at Maple Grove and Shoup; replace existing pedestrian ramps
  • Morris Hill Rd., west of Liberty St. to Hartman St. - Reconstruct roadway; replace existing pedestrian ramps
  • Roosevelt St., Emerald St. to Irving St. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps; install new sidewalk to fill gaps; replace existing driveway approaches; rebuild existing speed humps
  • Spaulding St., Phillippi St. to Orchard St. - Reconstruct roadway; install bulb-outs; replace existing pedestrian ramps; rebuild existing speed humps
  • Turret Way, Drawbridge Dr. to Castle Dr. - Reconstruct roadway; install bulb-outs; replace existing pedestrian ramps

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

This project is substantially complete. 

  • December 1, 2023

    Share December 1, 2023 on Facebook Share December 1, 2023 on Twitter Share December 1, 2023 on Linkedin Email December 1, 2023 link
    • 9th Street, Idaho Street to Bannock Street
      • Waterline work by Veolia is complete.
      • ACHD’s project will be postponed to 2024.
    • 20th Street, Lemp Street to Irene Street
      • Asphalt paving complete.
      • Minor work remains.
    • Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
      • Complete.
    • Castle Hill Way, Castle Drive to Drawbridge Drive
      • Complete.
    • Drawbridge Drive, west of Crimson Drive to Turret Way
      • Complete.
    • Turret Way, Drawbridge Drive to Castle Drive
      • Complete.
    • Morris Hill Road, west of Liberty Street to Hartman Street
      • Complete.
    • Spaulding Street, Philippi Street to Orchard Street
      • Complete.
    • Roosevelt Street, Emerald Street to Irving Street
      • Complete
    • Maple Grove Road, I-84 Overpass to Franklin Road
      • Concrete work is complete.
      • Roadway work is delayed to spring 2024.
    • Amity Road, Enterprise Street to Production Avenue
      • Complete.
    • Enterprise Street, Amity Road to Commerce Avenue
      • Complete.
  • November 22, 2023

    Share November 22, 2023 on Facebook Share November 22, 2023 on Twitter Share November 22, 2023 on Linkedin Email November 22, 2023 link
    • 9th Street, Idaho Street to Bannock Street
      • Waterline work by Veolia is complete.
      • ACHD’s project will be postponed to 2024.
    • 20th Street, Lemp Street to Irene Street
      • Asphalt paving between Hazel and Irene was completed on November 1st.
      • Minor work remains.
      • Roadway work between Lemp and Hazel is on-going. Asphalt paving is scheduled for November 20th.
    • Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
      • Complete.
    • Castle Hill Way, Castle Drive to Drawbridge Drive
      • Complete.
    • Drawbridge Drive, west of Crimson Drive to Turret Way
      • Complete.
    • Turret Way, Drawbridge Drive to Castle Drive
      • Complete.
    • Morris Hill Road, west of Liberty Street to Hartman Street
      • Complete.
    • Spaulding Street, Philippi Street to Orchard Street
      • Complete.
    • Roosevelt Street, Emerald Street to Irving Street
      • Complete
    • Maple Grove Road, I-84 Overpass to Franklin Road
      • Concrete work is complete.
      • Roadway work is delayed to spring 2024.
    • Amity Road, Enterprise Street to Production Avenue
      • Complete.
    • Enterprise Street, Amity Road to Commerce Avenue
      • Complete.
  • November 17, 2023

    Share November 17, 2023 on Facebook Share November 17, 2023 on Twitter Share November 17, 2023 on Linkedin Email November 17, 2023 link
    • 9th Street, Idaho Street to Bannock Street
      • Waterline work by Veolia is complete.
      • ACHD’s project will be postponed to 2024.
    • 20th Street, Lemp Street to Irene Street
      • Asphalt paving between Hazel and Irene was completed on November 1st.
      • Minor work remains.
      • Roadway work between Lemp and Hazel is on-going. Asphalt paving is scheduled for November 20th.
    • Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
      • Complete.
    • Castle Hill Way, Castle Drive to Drawbridge Drive
      • Complete.
    • Drawbridge Drive, west of Crimson Drive to Turret Way
      • Complete.
    • Turret Way, Drawbridge Drive to Castle Drive
      • Complete.
    • Morris Hill Road, west of Liberty Street to Hartman Street
      • Complete.
    • Spaulding Street, Philippi Street to Orchard Street
      • Complete.
    • Roosevelt Street, Emerald Street to Irving Street
      • Complete
    • Maple Grove Road, I-84 Overpass to Franklin Road
      • Concrete work is complete.
      • Roadway work is delayed to spring 2024.
    • Amity Road, Enterprise Street to Production Avenue
      • Complete.
    • Enterprise Street, Amity Road to Commerce Avenue
      • Complete.
  • November 9, 2023

    Share November 9, 2023 on Facebook Share November 9, 2023 on Twitter Share November 9, 2023 on Linkedin Email November 9, 2023 link
    • 9th St., Idaho St. to Bannock St. - Waterline work by Veolia is complete. ACHD's project will be postponed to 2024.
    • 20th St., Lemp St. to Irene St. - Waterline work by Veolia is complete. Pipework complete. Concrete work is ongoing. Asphalt paving between Hazel and Irene was completed on November 1st. Minor work remains. Roadway work between Lemp and Hazel is ongoing.
    • Amity Rd., Enterprise St. to Production St. - Complete.
    • Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Complete.
    • Castle Hill Way, Castle Dr. to Drawbridge Dr. - Complete.
    • Drawbridge Dr., West End to Castle Hill Way - Complete.
    • Enterprise St., Amity Rd. to Commerce Ave. - Complete.
    • Maple Grove Rd., I-84 Bridge to Franklin Rd. - Concrete work is complete. Roadway work is delayed to Spring 2024.
    • Morris Hill Rd., west of Liberty St. to Hartman St. - Complete.
    • Roosevelt St., Emerald St. to Irving St. - Complete.
    • Spaulding St., Phillippi St. to Orchard St. - Complete.
    • Turret Way, Drawbridge Dr. to Castle Dr. - Complete.
  • November 3, 2023

    Share November 3, 2023 on Facebook Share November 3, 2023 on Twitter Share November 3, 2023 on Linkedin Email November 3, 2023 link
    • 9th St., Idaho St. to Bannock St. - Waterline work by Veolia is complete. ACHD's project will be postponed to 2024.
    • 20th St., Lemp St. to Irene St. - Waterline work by Veolia is complete. Pipework complete. Concrete work is ongoing. Asphalt paving between Hazel and Irene was completed on November 1st. Minor work remains. Roadway work between Lemp and Hazel will follow, weather dependent.
    • Amity Rd., Enterprise St. to Production St. - Complete.
    • Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Complete.
    • Castle Hill Way, Castle Dr. to Drawbridge Dr. - Complete.
    • Drawbridge Dr., West End to Castle Hill Way - Complete.
    • Enterprise St., Amity Rd. to Commerce Ave. - Complete.
    • Maple Grove Rd., I-84 Bridge to Franklin Rd. - Concrete work is complete. Roadway work is delayed to Spring 2024.
    • Morris Hill Rd., west of Liberty St. to Hartman St. - Complete.
    • Roosevelt St., Emerald St. to Irving St. - Complete.
    • Spaulding St., Phillippi St. to Orchard St. - Complete.
    • Turret Way, Drawbridge Dr. to Castle Dr. - Complete.
  • October 20, 2023

    Share October 20, 2023 on Facebook Share October 20, 2023 on Twitter Share October 20, 2023 on Linkedin Email October 20, 2023 link
    • 9th St., Idaho St. to Bannock St. - Waterline work by Veolia is complete. ACHD's project will be postponed to 2024.
    • 20th St., Lemp St. to Irene St. - Waterline work by Veolia is complete. Pipework complete. Concrete work is ongoing. Roadway work between Hazel and Irene will begin October 16th and is expected to take two weeks. Roadway work between Lemp and Hazel will follow.
    • Amity Rd., Enterprise St. to Production St. - Complete.
    • Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Complete.
    • Castle Hill Way, Castle Dr. to Drawbridge Dr. - Complete.
    • Drawbridge Dr., West End to Castle Hill Way - Complete.
    • Enterprise St., Amity Rd. to Commerce Ave. - Complete.
    • Maple Grove Rd., I-84 Bridge to Franklin Rd. - Concrete work is complete. Roadway work is delayed to Spring 2024.
    • Morris Hill Rd., west of Liberty St. to Hartman St. - Complete.
    • Roosevelt St., Emerald St. to Irving St. - Complete.
    • Spaulding St., Phillippi St. to Orchard St. - Complete.
    • Turret Way, Drawbridge Dr. to Castle Dr. - Complete.
  • October 12, 2023

    Share October 12, 2023 on Facebook Share October 12, 2023 on Twitter Share October 12, 2023 on Linkedin Email October 12, 2023 link
    • 9th St., Idaho St. to Bannock St. - Waterline work by Veolia is complete. ACHD's project will be postponed to 2024.
    • 20th St., Lemp St. to Irene St. - Waterline work by Veolia is complete. Pipework complete. Concrete work is ongoing. Roadway work between Hazel and Irene will begin October 16th. Roadway work between Lemp and Hazel will follow.
    • Amity Rd., Enterprise St. to Production St. - Complete.
    • Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Complete.
    • Castle Hill Way, Castle Dr. to Drawbridge Dr. - Complete.
    • Drawbridge Dr., West End to Castle Hill Way - Concrete work is complete. Milling and paving is scheduled for October 9 -10.
    • Enterprise St., Amity Rd. to Commerce Ave. - Asphalt paving is complete. Minor work remains.
    • Maple Grove Rd., I-84 Bridge to Franklin Rd. - Concrete work is complete. Roadway work is delayed to Spring 2024.
    • Morris Hill Rd., west of Liberty St. to Hartman St. - Complete.
    • Roosevelt St., Emerald St. to Irving St. - Complete.
    • Spaulding St., Phillippi St. to Orchard St. - Complete.
    • Turret Way, Drawbridge Dr. to Castle Dr. - Complete.
  • October 6, 2023

    Share October 6, 2023 on Facebook Share October 6, 2023 on Twitter Share October 6, 2023 on Linkedin Email October 6, 2023 link
    • 9th St., Idaho St. to Bannock St. - Waterline work by Veolia is complete. ACHD's project will be postponed to 2024.
    • 20th St., Lemp St. to Irene St. - Waterline work by Veolia is complete. ACHD's contractor started pipe work on September 5th. The road will remain closed. Concrete work is ongoing.
    • Amity Rd., Enterprise St. to Production St. - Reconstruct roadway
    • Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Complete.
    • Castle Hill Way, Castle Dr. to Drawbridge Dr. - Complete.
    • Drawbridge Dr., West End to Castle Hill Way - Concrete work is complete. Milling and paving is scheduled for October 9 -10.
    • Enterprise St., Amity Rd. to Commerce Ave. - Asphalt paving is complete. Minor work remains.
    • Maple Grove Rd., I-84 Bridge to Franklin Rd. - Concrete work is complete. Roadway work is delayed to Spring 2024.
    • Morris Hill Rd., west of Liberty St. to Hartman St. - Complete.
    • Roosevelt St., Emerald St. to Irving St. - Complete.
    • Spaulding St., Phillippi St. to Orchard St. - Complete.
    • Turret Way, Drawbridge Dr. to Castle Dr. - Complete.
  • September 29, 2023

    Share September 29, 2023 on Facebook Share September 29, 2023 on Twitter Share September 29, 2023 on Linkedin Email September 29, 2023 link

    9th Street, Idaho Street to Bannock Street

    • Waterline work by Veolia started September 5th. 9th Street will be closed during the work.

    20th Street, Lemp Street to Irene Street

    • Waterline work by Veolia is complete. ACHD’s contractor started pipe work on September 5th.
    • The road will remain closed.
    • Concrete work ongoing.

    Bluegrass Avenue, Ellens Ferry Drive to Castle Drive

    • Complete.

    Castle Hill Way, Castle Drive to Drawbridge Drive

    • Complete.

    Turret Way, Drawbridge Drive to Castle Drive

    • Asphalt paving is complete. Minor work remains.

    Drawbridge Drive, west of Crimson Drive to Turret Way

    • Concrete work is complete.
    • Milling and paving is scheduled for October 9-10th.

    Morris Hill Road, west of Liberty Street to Hartman Street

    • Complete.

    Spaulding Street, Philippi Street to Orchard Street

    • Complete.

    Roosevelt Street, Emerald Street to Irving Street

    • Complete

    Maple Grove Road, I-84 Overpass to Franklin Road

    • Concrete work is complete.
    • Roadway work is delayed until Spring 2024.

    Amity Road, Enterprise Street to Production Avenue

    • Asphalt paving is complete. Minor work remains.

    Enterprise Street, Amity Road to Commerce Avenue

    • Asphalt paving is complete. Minor work remains.
  • September 22, 2023

    Share September 22, 2023 on Facebook Share September 22, 2023 on Twitter Share September 22, 2023 on Linkedin Email September 22, 2023 link

    9th Street, Idaho Street to Bannock Street

    • Waterline work by Veolia started September 5th. 9th Street will be closed during the work.

    20th Street, Lemp Street to Irene Street

    • Waterline work by Veolia is complete. ACHD’s contractor started pipe work on September 5th.
    • The road will remain closed.
    • Concrete work ongoing.

    Bluegrass Avenue, Ellens Ferry Drive to Castle Drive

    • Complete.

    Castle Hill Way, Castle Drive to Drawbridge Drive

    • Complete.

    Turret Way, Drawbridge Drive to Castle Drive

    • Pipe and storm drain work is complete.
    • Concrete work is complete.
    • The road will be closed for reconstruction beginning August 28th through mid-September. Asphalt paving is scheduled for September 25-26th.

    Drawbridge Drive, west of Crimson Drive to Turret Way

    • Concrete work is complete.
    • Milling and paving is scheduled for October 9-10th.

    Morris Hill Road, west of Liberty Street to Hartman Street

    • Complete.

    Spaulding Street, Philippi Street to Orchard Street

    • Complete.

    Roosevelt Street, Emerald Street to Irving Street

    • Complete

    Maple Grove Road, I-84 Overpass to Franklin Road

    • Concrete work is complete.
    • Roadway work is delayed until Spring 2024.

    Amity Road, Enterprise Street to Production Avenue

    • Asphalt paving is complete. Minor work remains.

    Enterprise Street, Amity Road to Commerce Avenue

    • Asphalt paving is complete. Minor work remains.