2022 Pavement and Pedestrian Improvements

Share 2022 Pavement and Pedestrian Improvements on Facebook Share 2022 Pavement and Pedestrian Improvements on Twitter Share 2022 Pavement and Pedestrian Improvements on Linkedin Email 2022 Pavement and Pedestrian Improvements link

This project is substantially complete. 

The Ada County Highway District (ACHD) will be reconstructing several streets in Ada County as part of a federal aid project to improve pavement conditions and upgrade the streets for all users.

Work could include:

  • Reconstructing streets or removing and replacing pavement to improve roadway conditions
  • Filling in sidewalk gaps to increase connectivity
  • Adding bulb-outs and signalized pedestrian crossings where appropriate to improve safety
  • Installing Accessible Pedestrian Signals (APS) and pedestrian push buttons.
  • Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA).

Street Segments:

  • 9th St., Idaho St. to Bannock St. - Replace existing asphalt with concrete; install pedestrian bulb outs; replace existing pedestrian ramps; replace existing driveway approaches and traffic signals.
  • 20th St., Lemp St. to Irene St. - Reconstruct roadway; replace existing pedestrian ramps; replace damaged sidewalk
  • Amity Rd., Enterprise St. to Production St. - Reconstruct roadway
  • Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
  • Castle Hill Way, Castle Dr. to Drawbridge Dr. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps; replace existing driveway approach
  • Drawbridge Dr., West End to Castle Hill Way - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
  • Enterprise St., Amity Rd. to Commerce Ave. - Reconstruct roadway; replace existing pedestrian ramp
  • Maple Grove Rd., I-84 Bridge to Franklin Rd. - Remove and replace pavement; install a pedestrian hybrid beacon at Maple Grove and Shoup; replace existing pedestrian ramps
  • Morris Hill Rd., west of Liberty St. to Hartman St. - Reconstruct roadway; replace existing pedestrian ramps
  • Roosevelt St., Emerald St. to Irving St. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps; install new sidewalk to fill gaps; replace existing driveway approaches; rebuild existing speed humps
  • Spaulding St., Phillippi St. to Orchard St. - Reconstruct roadway; install bulb-outs; replace existing pedestrian ramps; rebuild existing speed humps
  • Turret Way, Drawbridge Dr. to Castle Dr. - Reconstruct roadway; install bulb-outs; replace existing pedestrian ramps

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

The Ada County Highway District (ACHD) will be reconstructing several streets in Ada County as part of a federal aid project to improve pavement conditions and upgrade the streets for all users.

Work could include:

  • Reconstructing streets or removing and replacing pavement to improve roadway conditions
  • Filling in sidewalk gaps to increase connectivity
  • Adding bulb-outs and signalized pedestrian crossings where appropriate to improve safety
  • Installing Accessible Pedestrian Signals (APS) and pedestrian push buttons.
  • Upgrading and/or installing pedestrian ramps to meet modern standards and the Americans with Disabilities Act (ADA).

Street Segments:

  • 9th St., Idaho St. to Bannock St. - Replace existing asphalt with concrete; install pedestrian bulb outs; replace existing pedestrian ramps; replace existing driveway approaches and traffic signals.
  • 20th St., Lemp St. to Irene St. - Reconstruct roadway; replace existing pedestrian ramps; replace damaged sidewalk
  • Amity Rd., Enterprise St. to Production St. - Reconstruct roadway
  • Bluegrass Ave., Ellen's Ferry Dr. to Castle Dr. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
  • Castle Hill Way, Castle Dr. to Drawbridge Dr. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps; replace existing driveway approach
  • Drawbridge Dr., West End to Castle Hill Way - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps
  • Enterprise St., Amity Rd. to Commerce Ave. - Reconstruct roadway; replace existing pedestrian ramp
  • Maple Grove Rd., I-84 Bridge to Franklin Rd. - Remove and replace pavement; install a pedestrian hybrid beacon at Maple Grove and Shoup; replace existing pedestrian ramps
  • Morris Hill Rd., west of Liberty St. to Hartman St. - Reconstruct roadway; replace existing pedestrian ramps
  • Roosevelt St., Emerald St. to Irving St. - Remove and replace pavement; install bulb-outs; replace existing pedestrian ramps; install new sidewalk to fill gaps; replace existing driveway approaches; rebuild existing speed humps
  • Spaulding St., Phillippi St. to Orchard St. - Reconstruct roadway; install bulb-outs; replace existing pedestrian ramps; rebuild existing speed humps
  • Turret Way, Drawbridge Dr. to Castle Dr. - Reconstruct roadway; install bulb-outs; replace existing pedestrian ramps

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

This project is substantially complete. 

  • September 15, 2023

    Share September 15, 2023 on Facebook Share September 15, 2023 on Twitter Share September 15, 2023 on Linkedin Email September 15, 2023 link

    9th Street, Idaho Street to Bannock Street

    • Waterline work by Veolia started September 5th. 9th Street will be closed during the work.

    20th Street, Lemp Street to Irene Street

    • Waterline work by Veolia is complete. ▪ ACHD’s contractor started pipe work on September 5th.
    • The road will remain closed.

    Bluegrass Avenue, Ellens Ferry Drive to Castle Drive

    • Complete.

    Castle Hill Way, Castle Drive to Drawbridge Drive

    • Paving is complete.
    • Minor work remains.

    Turret Way, Drawbridge Drive to Castle Drive

    • Pipe and storm drain work is complete.
    • Concrete work is nearly complete.
    • The road will be closed for reconstruction beginning August 28th through mid-September. Asphalt paving is scheduled for the week of September 18th.

    Drawbridge Drive, west of Crimson Drive to Turret Way

    • Concrete work is on-going.

    Morris Hill Road, west of Liberty Street to Hartman Street

    • Complete.

    Spaulding Street, Philippi Street to Orchard Street

    • Complete.

    Roosevelt Street, Emerald Street to Irving Street

    • Complete

    Maple Grove Road, I-84 Overpass to Franklin Road

    • Concrete work is complete.
    • Roadway work is delayed until Spring 2024.

    Amity Road, Enterprise Street to Production Avenue

    • Asphalt paving is complete. Minor work remains.

    Enterprise Street, Amity Road to Commerce Avenue

    • Asphalt paving is complete. Minor work remains.
  • September 8, 2023

    Share September 8, 2023 on Facebook Share September 8, 2023 on Twitter Share September 8, 2023 on Linkedin Email September 8, 2023 link

    9th Street, Idaho Street to Bannock Street

    • Waterline work by Veolia started September 5th. 9th Street will be closed during the work.

    20th Street, Lemp Street to Irene Street

    • Waterline work by Veolia is complete. ▪ ACHD’s contractor started pipe work on September 5th.
    • The road will remain closed.

    Bluegrass Avenue, Ellens Ferry Drive to Castle Drive

    • Complete.

    Castle Hill Way, Castle Drive to Drawbridge Drive

    • Paving is complete.
    • Minor work remains.

    Turret Way, Drawbridge Drive to Castle Drive

    • Pipe and storm drain work is complete.
    • Concrete work is nearly complete.
    • The road will be closed for reconstruction beginning August 28th through mid-September.

    Drawbridge Drive, west of Crimson Drive to Turret Way

    • Concrete work is on-going.

    Morris Hill Road, west of Liberty Street to Hartman Street

    • Complete.

    Spaulding Street, Philippi Street to Orchard Street

    • Complete.

    Roosevelt Street, Emerald Street to Irving Street

    • Complete

    Maple Grove Road, I-84 Overpass to Franklin Road

    • Concrete work is complete.
    • Roadway work is delayed until Spring 2024.

    Amity Road, Enterprise Street to Production Avenue

    • Asphalt paving is complete. Minor work remains.

    Enterprise Street, Amity Road to Commerce Avenue

    • Asphalt paving is complete. Minor work remains, including manhole adjustments and permanent pavement markings.
  • August 31, 2023

    Share August 31, 2023 on Facebook Share August 31, 2023 on Twitter Share August 31, 2023 on Linkedin Email August 31, 2023 link

    9th Street, Idaho Street to Bannock Street

    • Waterline work by Veolia is anticipated to start September 5th. 9th Street will be closed during the work.

    20th Street, Lemp Street to Irene Street

    • Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron is complete.
    • The segment between Ridenbaugh to Hazel is currently closed.

    Bluegrass Avenue, Ellens Ferry Drive to Castle Drive

    • Complete.

    Castle Hill Way, Castle Drive to Drawbridge Drive

    • Pipe work is complete.
    • Concrete is complete.
    • Milling and paving is complete.
    • Minor work remains.

    Turret Way, Drawbridge Drive to Castle Drive

    • Pipe and storm drain work is complete.
    • Concrete work is nearly complete.
    • Removal of asphalt is scheduled for August 25th.
    • The road will be closed for reconstruction beginning August 28th.

    Morris Hill Road, west of Liberty Street to Hartman Street

    • Complete.

    Spaulding Street, Philippi Street to Orchard Street

    • Complete.

    Roosevelt Street, Emerald Street to Irving Street

    • Complete

    Maple Grove Road, I-84 Overpass to Franklin Road

    • Concrete work is complete.
    • Roadway work is delayed until Spring 2024.

    Amity Road, Enterprise Street to Production Avenue

    • Asphalt paving is complete. Minor work remains.

    Enterprise Street, Amity Road to Commerce Avenue

    • Asphalt paving is complete. Minor work remains, including manhole adjustments and permanent pavement markings.
  • August 25, 2023

    Share August 25, 2023 on Facebook Share August 25, 2023 on Twitter Share August 25, 2023 on Linkedin Email August 25, 2023 link

    9th Street, Idaho Street to Bannock Street

    • Waterline work by Veolia is anticipated to start September 5th. 9th Street will be closed during the work.

    20th Street, Lemp Street to Irene Street

    • Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron is complete.
    • The segment between Ridenbaugh to Hazel is currently closed.

    Bluegrass Avenue, Ellens Ferry Drive to Castle Drive

    • Complete.

    Castle Hill Way, Castle Drive to Drawbridge Drive

    • Pipe work is complete.
    • Concrete is complete.
    • Milling and paving is complete.
    • Minor work remains.

    Turret Way, Drawbridge Drive to Castle Drive

    • Pipe and storm drain work is complete.
    • Concrete work is nearly complete.
    • Removal of asphalt is scheduled for August 25th.
    • The road will be closed for reconstruction beginning August 28th.

    Morris Hill Road, west of Liberty Street to Hartman Street

    • Complete.

    Spaulding Street, Philippi Street to Orchard Street

    • Complete.

    Roosevelt Street, Emerald Street to Irving Street

    • Complete

    Maple Grove Road, I-84 Overpass to Franklin Road

    • Concrete work is complete.
    • Roadway work is delayed until Spring 2024.

    Amity Road, Enterprise Street to Production Avenue

    • Asphalt paving is complete. Minor work remains.

    Enterprise Street, Amity Road to Commerce Avenue

    • Asphalt paving is complete. Minor work remains, including manhole adjustments and permanent pavement markings.
  • August 18, 2023

    Share August 18, 2023 on Facebook Share August 18, 2023 on Twitter Share August 18, 2023 on Linkedin Email August 18, 2023 link

    9th Street, Idaho Street to Bannock Street

    • Waterline work by Veolia is anticipated to start September 5th. 9th Street will be closed during the work.

    20th Street, Lemp Street to Irene Street

    • Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron is complete.
    • The segment between Ridenbaugh to Hazel is currently closed.

    Bluegrass Avenue, Ellens Ferry Drive to Castle Drive

    • Complete.

    Castle Hill Way, Castle Drive to Drawbridge Drive

    • Pipe work is complete.
    • Concrete work on-going.
    • Milling is scheduled for August 21-22
    • Asphalt paving is scheduled for August 23-24

    Turret Way, Drawbridge Drive to Castle Drive

    • Pipe and storm drain work is complete.
    • Concrete work is nearly complete.
    • Removal of asphalt is scheduled for August 25th.

    Morris Hill Road, west of Liberty Street to Hartman Street

    • Complete.

    Spaulding Street, Philippi Street to Orchard Street

    • Complete.

    Roosevelt Street, Emerald Street to Irving Street

    • Complete

    Maple Grove Road, I-84 Overpass to Franklin Road

    • Concrete work is complete.
    • Roadway work is delayed until Spring 2024.

    Amity Road, Enterprise Street to Production Avenue

    • Asphalt paving is complete. Minor work remains.

    Enterprise Street, Amity Road to Commerce Avenue

    • Enterprise between Boeing and Commerce will be done over two weekends beginning August 18th. The road will be closed from 6:00 pm. on Friday night through 6:00 a.m. on Monday morning.

  • August 11, 2023

    Share August 11, 2023 on Facebook Share August 11, 2023 on Twitter Share August 11, 2023 on Linkedin Email August 11, 2023 link

    9th Street, Idaho Street to Bannock Street

    • Waterline work by Veolia is anticipated to start September 5th. 9th Street will be closed during the work.

    20th Street, Lemp Street to Irene Street

    • Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron is complete.
    • The segment between Ridenbaugh to Hazel is currently closed.

    Bluegrass Avenue, Ellens Ferry Drive to Castle Drive

    • Complete.

    Castle Hill Way, Castle Drive to Drawbridge Drive

    • Pipe work is complete.
    • Concrete work on-going.

    Turret Way, Drawbridge Drive to Castle Drive

    • Pipe and storm drain work is complete.
    • Concrete work is on-going.

    Morris Hill Road, west of Liberty Street to Hartman Street

    • Complete.

    Spaulding Street, Philippi Street to Orchard Street

    • Complete.

    Roosevelt Street, Emerald Street to Irving Street

    • Complete

    Maple Grove Road, I-84 Overpass to Franklin Road

    • Concrete work is complete.

    Amity Road, Enterprise Street to Production Avenue

    • Asphalt paving is complete. Minor work remains.

    Enterprise Street, Amity Road to Commerce Avenue

    • Enterprise between Boeing and Commerce will be done over two weekends beginning August 18th. The road will be closed from 6:00 pm. on Friday night through 6:00 a.m. on Monday morning.
  • August 4, 2023

    Share August 4, 2023 on Facebook Share August 4, 2023 on Twitter Share August 4, 2023 on Linkedin Email August 4, 2023 link

    9th Street, Idaho Street to Bannock Street

    • Waterline work by Veolia is anticipated to start in September. 9th Street will be closed during the work.

    20th Street, Lemp Street to Irene Street

    • Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron is complete.
    • The segment between Ridenbaugh to Hazel is currently closed.

    Bluegrass Avenue, Ellens Ferry Drive to Castle Drive

    • Complete.

    Castle Hill Way, Castle Drive to Drawbridge Drive

    • Pipe work is complete.
    • Concrete work on-going.

    Turret Way, Drawbridge Drive to Castle Drive

    • Pipe and storm drain work is complete.
    • Concrete work is on-going.

    Morris Hill Road, west of Liberty Street to Hartman Street

    • Complete.

    Spaulding Street, Philippi Street to Orchard Street

    • Complete.

    Roosevelt Street, Emerald Street to Irving Street

    • Complete

    Maple Grove Road, I-84 Overpass to Franklin Road

    • Concrete work is complete.

    Amity Road, Enterprise Street to Production Avenue

    • Asphalt paving is complete. Minor work remains.

    Enterprise Street, Amity Road to Commerce Avenue

    • Concrete and pipe work are complete. Roadway work started July 31st.. Enterprise Street will be closed between Amity and Boeing during the work, which is expected to last a month. Enterprise Street between Boeing and Commerce will be done over two weekends beginning August 18th.
  • July 28, 2023

    Share July 28, 2023 on Facebook Share July 28, 2023 on Twitter Share July 28, 2023 on Linkedin Email July 28, 2023 link

    9th Street, Idaho Street to Bannock Street

    • Waterline work by Veolia is anticipated to start in mid-August. 9th Street will be closed during the work.

    20th Street, Lemp Street to Irene Street

    • Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron to is complete.
    • The segment between Ridenbaugh to Hazel is currently closed.

    Bluegrass Avenue, Ellens Ferry Drive to Castle Drive

    • Complete.

    Castle Hill Way, Castle Drive to Drawbridge Drive

    • Pipe work is complete.
    • Concrete work on-going.

    Turret Way, Drawbridge Drive to Castle Drive

    • Pipe and storm drain work is complete.
    • Concrete work is on-going.

    Morris Hill Road, west of Liberty Street to Hartman Street

    • Complete.

    Spaulding Street, Philippi Street to Orchard Street

    • Complete.

    Roosevelt Street, Emerald Street to Irving Street

    • Complete

    Maple Grove Road, I-84 Overpass to Franklin Road

    • Concrete work is complete.

    Amity Road, Enterprise Street to Production Avenue

    • Roadway work started July 6th. Amity Road will be closed during the work, which is expected to last a month. Asphalt paving is scheduled to be complete on July 28th.

    Enterprise Street, Amity Road to Commerce Avenue

    • Concrete and pipe work are complete. Roadway work will begin after Amity is complete, anticipated for July 31st. Enterprise Street will be closed between Amity and Boeing during the work, which is expected to last a month.
  • July 21, 2023

    Share July 21, 2023 on Facebook Share July 21, 2023 on Twitter Share July 21, 2023 on Linkedin Email July 21, 2023 link
    • 20th Street, Lemp Street to Irene Street
      • Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron i is complete. The segment between Ridenbaugh to Hazel is currently closed.
    • Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
      • Complete.
    • Castle Hill Way, Castle Drive to Drawbridge Drive
      • Pipe work is complete. Concrete work on-going.
    • Turret Way, Drawbridge Drive to Castle Drive
      • Pipe work and storm drain work complete. Concrete work ongoing.
    • Morris Hill Road, west of Liberty Street to Hartman Street
      • Complete.
    • Spaulding Street, Philippi Street to Orchard Street
      • Complete.
    • Roosevelt Street, Emerald Street to Irving Street
      • Complete.
    • Maple Grove Road, I-84 Overpass to Franklin Road
      • Concrete work is complete.
    • Amity Road, Enterprise Street to Production Avenue
      • Roadway work started July 6th. Amity Road will be closed during the work, which is expected to last a month. Paving is expected July 24th.
    • Enterprise Street, Amity Road to Commerce Avenue
      • Concrete and pipe work are complete. Roadway work will begin after Amity is complete, anticipated for July 31st. Enterprise Street will be closed during the work, which is expected to last a month.
  • July 14, 2023

    Share July 14, 2023 on Facebook Share July 14, 2023 on Twitter Share July 14, 2023 on Linkedin Email July 14, 2023 link
    • 20th Street, Lemp Street to Irene Street
      • Waterline work by Veolia started start June 12th. 20th Street will be closed during the work, which is expected to last two months. The segment from Heron to Irene will be closed first, after which the segment between Ridenbaugh to Hazel will be closed.
    • Bluegrass Avenue, Ellens Ferry Drive to Castle Drive
      • Pipe work is complete.
      • Concrete work is nearly complete.
      • Milling is complete. Paving is anticipated to be complete by July 14th.
    • Castle Hill Way, Castle Drive to Drawbridge Drive
      • Pipe work is complete. Concrete work started July 3rd and in on-going.
    • Turret Way, Drawbridge Drive to Castle Drive
      • Pipe and storm drain work is complete. Concrete work is on-going.
    • Morris Hill Road, west of Liberty Street to Hartman Street
      • Complete.
    • Spaulding Street, Philippi Street to Orchard Street
      • Complete.
    • Roosevelt Street, Emerald Street to Irving Street
      • Complete.
    • Maple Grove Road, I-84 Overpass to Franklin Road
      • Concrete work is complete.
    • Amity Road, Enterprise Street to Production Avenue
      • Roadway work started July 6th. Amity Road will be closed during the work, which is expected to last a month.
    • Enterprise Street, Amity Road to Commerce Avenue
      • Concrete and pipe work are complete.