Downtown Eagle Mobility Improvements: Eagle Road and State Street
This project is substantially complete.
The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.
The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.
Goals
The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.
The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.
The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.
Goals
The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.
This project is substantially complete.
-
January 31, 2025
Share January 31, 2025 on Facebook Share January 31, 2025 on Twitter Share January 31, 2025 on Linkedin Email January 31, 2025 linkEagle Road in front of Albertsons
- Culvert ongoing.
- Swale ongoing.
Phase 2
- Clearing and grubbing Aikens Street for utilities to relocate lines.
- Veolia working on Aikens installing new waterline.
- Eagle Sewer starting Feb 3rd on 2nd Street.
Eagle Road in front of Albertsons
- Culvert ongoing.
- Swale ongoing.
Phase 2
- Clearing and grubbing Aikens Street for utilities to relocate lines.
- Veolia working on Aikens installing new waterline.
- Eagle Sewer starting Feb 3rd on 2nd Street.
This project is substantially complete.
-
Phase 2- Aikens and Olde Park Place Closures
Share Phase 2- Aikens and Olde Park Place Closures on Facebook Share Phase 2- Aikens and Olde Park Place Closures on Twitter Share Phase 2- Aikens and Olde Park Place Closures on Linkedin Email Phase 2- Aikens and Olde Park Place Closures linkPhase 2 of the Downtown Eagle Mobility Improvements project is expected to begin next week.Beginning Monday, Aikens Street in Eagle will be closed from Olde Park Place to east of 1st Street, where the street currently ends. Additionally, Olde Park Place will be closed between State Street (Old State) and Aikens Street.These closures and temporary access points are expected to be in place until spring of 2025.
Phase 2 of the Downtown Eagle Mobility Improvements project is expected to begin next week.Beginning Monday, Aikens Street in Eagle will be closed from Olde Park Place to east of 1st Street, where the street currently ends. Additionally, Olde Park Place will be closed between State Street (Old State) and Aikens Street.These closures and temporary access points are expected to be in place until spring of 2025.
This project is substantially complete.
-
Phase 2 Update - January 23, 2025
Share Phase 2 Update - January 23, 2025 on Facebook Share Phase 2 Update - January 23, 2025 on Twitter Share Phase 2 Update - January 23, 2025 on Linkedin Email Phase 2 Update - January 23, 2025 link- Clearing and grubbing Aikens Street for utilities to relocate lines.
- Veolia closed 2nd Street for water tie in.
- Clearing and grubbing Aikens Street for utilities to relocate lines.
- Veolia closed 2nd Street for water tie in.
This project is substantially complete.
-
January 23, 2025
Share January 23, 2025 on Facebook Share January 23, 2025 on Twitter Share January 23, 2025 on Linkedin Email January 23, 2025 linkEagle Road in front of Albertsons
- Culvert ongoing.
- Swale ongoing.
2nd Street and State Street
- Tree grates remaining.
Eagle Road in front of Albertsons
- Culvert ongoing.
- Swale ongoing.
2nd Street and State Street
- Tree grates remaining.
This project is substantially complete.
-
Eagle Road & State - Phase 2 - Update
Share Eagle Road & State - Phase 2 - Update on Facebook Share Eagle Road & State - Phase 2 - Update on Twitter Share Eagle Road & State - Phase 2 - Update on Linkedin Email Eagle Road & State - Phase 2 - Update link- Clearing and grubbing Aikens Street for utilities to relocate lines.
- Clearing and grubbing Aikens Street for utilities to relocate lines.
This project is substantially complete.
-
January 17, 2025
Share January 17, 2025 on Facebook Share January 17, 2025 on Twitter Share January 17, 2025 on Linkedin Email January 17, 2025 linkEagle Road in front of Albertsons
- Culvert being moved pending approval.
- Swale ongoing
2nd Street and State Street.
- Tree grates remaining.
- Decision on crossing ongoing.
Eagle Road in front of Albertsons
- Culvert being moved pending approval.
- Swale ongoing
2nd Street and State Street.
- Tree grates remaining.
- Decision on crossing ongoing.
This project is substantially complete.
-
January 10, 2025
Share January 10, 2025 on Facebook Share January 10, 2025 on Twitter Share January 10, 2025 on Linkedin Email January 10, 2025 linkEagle Road in front of Albertsons
- Culvert being moved pending approval.
- Swale ongoing.
2nd Street and State Street
- Tree grates remaining.
- Decision on crossing ongoing.
Eagle Road in front of Albertsons
- Culvert being moved pending approval.
- Swale ongoing.
2nd Street and State Street
- Tree grates remaining.
- Decision on crossing ongoing.
This project is substantially complete.
-
Construction Kick Off Meeting - Public Open House
Share Construction Kick Off Meeting - Public Open House on Facebook Share Construction Kick Off Meeting - Public Open House on Twitter Share Construction Kick Off Meeting - Public Open House on Linkedin Email Construction Kick Off Meeting - Public Open House linkPlease join ACHD Staff and the Contractor on Thursday, January 23rd from 4-7pm at the Residence Inn, 515 S Palmetto Ave, Eagle for a Construction Open House to learn more about the Downtown Eagle Mobility Improvement Project - Phase 2.
Please join ACHD Staff and the Contractor on Thursday, January 23rd from 4-7pm at the Residence Inn, 515 S Palmetto Ave, Eagle for a Construction Open House to learn more about the Downtown Eagle Mobility Improvement Project - Phase 2.
This project is substantially complete.
-
January 3, 2025
Share January 3, 2025 on Facebook Share January 3, 2025 on Twitter Share January 3, 2025 on Linkedin Email January 3, 2025 linkEagle Road in front of Albertsons
- Culvert being moved pending approval
- Swale ongoing
2nd Street and State Street
- Landscaping ongoing
Eagle Road in front of Albertsons
- Culvert being moved pending approval
- Swale ongoing
2nd Street and State Street
- Landscaping ongoing
This project is substantially complete.
-
December 20, 2024
Share December 20, 2024 on Facebook Share December 20, 2024 on Twitter Share December 20, 2024 on Linkedin Email December 20, 2024 linkEagle Road in front of Albertsons
- Culvert being moved pending approval.
- Swale ongoing.
2nd Street and State Street
- Landscaping ongoing.
Eagle Road in front of Albertsons
- Culvert being moved pending approval.
- Swale ongoing.
2nd Street and State Street
- Landscaping ongoing.
This project is substantially complete.
Materials from Phase 2 Construction Open House
Drone Footage
-
October 24 2025
-
September 16 2025
-
August 29 2025
-
July 25 2025
-
June 16 2025
Who's Listening
-
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org -
Project Manager
Phone 208-387-6100 Email connect@achdidaho.org
Construction Open House
-
January 23 2025
-
January 31 2024
Materials from Construction Open House
Monthly Public Pop Up
-
August 29 2024
-
July 20 2024
-
June 27 2024
-
May 30 2024
-
April 25 2024
History
The design was the outcome of the Eagle Road and States Street Concept Design, an effort that began in 2012. After working with the community and the City of Eagle to evaluate multiple alternatives, the ACHD Commission approved the City's request to design and construct the Quadrant Alternative. This alternative best balances the need to safely accommodate the expected traffic growth, minimize impacts to adjacent properties and parking, and make downtown Eagle more walkable and bikeable, as well as being respectful of downtown's history and small town feel.