Downtown Eagle Mobility Improvements: Eagle Road and State Street

Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Facebook Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Twitter Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Linkedin Email Downtown Eagle Mobility Improvements: Eagle Road and State Street link

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

*Phase 1 of the project is expected to be complete by Fall 2024

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

*Phase 1 of the project is expected to be complete by Fall 2024

  • March 15, 2024

    Share March 15, 2024 on Facebook Share March 15, 2024 on Twitter Share March 15, 2024 on Linkedin Email March 15, 2024 link
    • Phase 1 - Northeast corner of Eagle and Plaza - Removal of obstructions and tree removal ongoing.
    • Utilities relocating - Signal work ongoing.
    • Veolia - Locating utilities. Boring Complete. Crossing Eagle waiting TC permit approval. Possibly night work. Once tie in is complete will work north of Plaza.
  • March 8, 2024

    Share March 8, 2024 on Facebook Share March 8, 2024 on Twitter Share March 8, 2024 on Linkedin Email March 8, 2024 link
    • Phase 1 - Northeast corner of Eagle and Plaza
    • Removal of obstructions and tree removal ongoing.
    • Utilities relocating.
    • Signal work at Plaza started March 3rd.
    • Placing bases for new signal poles.
    • Veolia Permit approved February 26th.
    • Locating utilities.
    • Removing extruded curb between Eagle and Highway 44.
    • Potholing and boring started the week of March 4th.
  • March 1, 2024

    Share March 1, 2024 on Facebook Share March 1, 2024 on Twitter Share March 1, 2024 on Linkedin Email March 1, 2024 link

    Phase 1 - Northeast corner of Eagle and Plaza

    • A work zone is in place in the middle of Eagle Road, south of Plaza Drive for Veolia water work.
    • One lane in each direction will remain open (A lane on each side of the work zone).
    • Work will continue on the East side of Eagle Road just North of Plaza Drive.
    • Extruded curb is being removed on Eagle Rd. between Plaza Dr. and Highway 44.
    • Contractor is removing obstructions.
    • Utilities are being relocated.
    • Veolia Permit approved February 26th.
    • Signal work starting March 4th.
    • Flagging is needed at Eagle and Plaza starting Monday, March 4th for utility and signal work.
    • Business access will be maintained.

  • February 27, 2024

    Share February 27, 2024 on Facebook Share February 27, 2024 on Twitter Share February 27, 2024 on Linkedin Email February 27, 2024 link

    As construction continues on Eagle Road, please review the updated traffic pattern and information below:

    • A work zone has been added in the middle of Eagle Road, south of Plaza Drive for Veolia water work.
    • One lane in each direction will remain open (A lane on each side of the work zone).
    • Business access will be maintained.
    • Work will continue on the East side of Eagle Road just North of Plaza Drive.


  • February 23, 2024

    Share February 23, 2024 on Facebook Share February 23, 2024 on Twitter Share February 23, 2024 on Linkedin Email February 23, 2024 link
    • Northeast corner of Eagle and Plaza - Removing obstructions.
    • Utilities relocating.
    • Tree removal ongoing.
    • Signal work starting.
    • Veolia waiting for ITD permit prior to starting.
  • February 16, 2024

    Share February 16, 2024 on Facebook Share February 16, 2024 on Twitter Share February 16, 2024 on Linkedin Email February 16, 2024 link
    • Northeast corner of Eagle and Plaza - Removing obstructions.
    • Utilities relocating.
    • Tree removal ongoing.
  • February 14, 2024

    Share February 14, 2024 on Facebook Share February 14, 2024 on Twitter Share February 14, 2024 on Linkedin Email February 14, 2024 link

    Interested in reviewing the progress of the project? Watch ACHD's latest drone video.

  • February 9, 2024

    Share February 9, 2024 on Facebook Share February 9, 2024 on Twitter Share February 9, 2024 on Linkedin Email February 9, 2024 link
    • The anticipated start date is February 12th. NE Corner of Plaza and Eagle.
    • Work will begin on the east side of Eagle between Plaza and Aikens, with the northbound lane being restricted and moved into the center lane.
    • One lane of travel will remain open in each direction, and business access will be maintained. Signs will be in place to alert drivers of the new traffic pattern.


  • Construction to start in early February

    Share Construction to start in early February on Facebook Share Construction to start in early February on Twitter Share Construction to start in early February on Linkedin Email Construction to start in early February link

    Construction will begin early February, along with significant water and power utility work. Phase 1 work is expected to be complete by Fall 2024. Phase 2 will follow and is scheduled for completion Fall 2025.

    Phase 1 includes work on the following three road sections:

    • Eagle Road, SH-44 to the canal (just north of Plaza Drive)
    • Plaza Drive, Eagle Road to 2nd Street
    • State Street and 2nd Street intersection

    Access to businesses will remain open at all times. Ingress and egress may be shifted to accommodate construction. If business access will be impacted, the contractor will coordinate with the businesses.

    Work will include, but is not limited to:

    • Temporary closures
    • Lane restrictions
    • Temporary on-street parking restrictions
    • Typical construction noise
    • Dust
    • Equipment backup alarms
    • Ground vibration
    • Veolia water line and other utility work

    Work is anticipated to occur between 7:00 a.m. and 7:00 p.m. Some night and weekend work is expected.

    *Construction schedules are subject to change.

    Learn More!

    Construction Open House

    • January 31, 2024 | 3:00 p.m. to 7:00 p.m.
    • Hilton Garden Inn | 145 E. Riverside Dr., Eagle, ID
    • Visit anytime between 3:00 and 7:00 p.m. Please note this is an informal open house, with no formal presentation.
    • Materials from open house
  • January 12, 2024

    Share January 12, 2024 on Facebook Share January 12, 2024 on Twitter Share January 12, 2024 on Linkedin Email January 12, 2024 link
    • Notice to proceed is anticipated for mid-February.
    • Public Open House, January 31st from 3:00 p.m. - 7:00 p.m. - Hilton Garden Inn, Eagle. Stop by to learn more about the construction project in Eagle.