Share July 25, 2025 on Facebook
Share July 25, 2025 on Linkedin
Email July 25, 2025 link
Olde Park
Landscape and brick pavers ongoing
Aikens between 2nd and Eagle
Parking lot ongoing. Landscaping ongoing.
Eagle Rd & State Intersection
Started July 7th. Removal of road and signal equipment. Underground work after removals. Veolia starting potentially July 21st. Underground electrical ongoing.
Share July 18, 2025 on Facebook
Share July 18, 2025 on Linkedin
Email July 18, 2025 link
Olde Park
- Landscape and brick pavers ongoing
Aikens between 2nd and Eagle
- Parking lot ongoing
- Landscaping ongoing
Eagle Rd & State Intersection
- Started July 7th
- Removal of road and signal equipment
- Underground work after removals
- Veolia starting potentially July 21st
Share Pedestrian Detour Route Map on Facebook
Share Pedestrian Detour Route Map on Linkedin
Email Pedestrian Detour Route Map link
Share July 11, 2025 on Facebook
Share July 11, 2025 on Linkedin
Email July 11, 2025 link
Olde Park
- Landscape and brick pavers ongoing
Aikens between 2nd and Eagle
Eagle Rd & State Intersection
- Closure started July 7th. Removal of road and signal equipment. Underground work after removals.
Share Detour Map - Closure July 6th on Facebook
Share Detour Map - Closure July 6th on Linkedin
Email Detour Map - Closure July 6th link
Share July 2, 2025 on Facebook
Share July 2, 2025 on Linkedin
Email July 2, 2025 link
Olde Park
- Landscape and brick pavers ongoing.
Aikens between 2nd and Eagle
- Landscaping ongoing - Parking lot ongoing.
Eagle Rd, Where Phase 1 stopped to Intersection of Eagle and Old State - Complete.
Eagle Rd & State Intersection - Closure - Starting July 7th. Removal of road and signal equipment. Underground work after removals.
Share June 26, 2025 on Facebook
Share June 26, 2025 on Linkedin
Email June 26, 2025 link
Olde Park
- Landscape and brick pavers ongoing
Aikens between 2nd and Eagle
- Landscaping ongoing. Parking lot ongoing. Private contractor working at 128 S. Eagle Rd.
Eagle Rd
- Milling complete. Concrete work ongoing. Paving scheduled for June 26th. Planning on being open for Eagle Fun Days.
The intersection of Eagle and Old State is anticipated to be closed July 7th until the middle of August.
Share June 20, 2025 on Facebook
Share June 20, 2025 on Linkedin
Email June 20, 2025 link
- Olde Park (1A)
- Landscape and brick pavers ongoing
- Aikens between 2nd and Eagle (1B)
- Landscaping ongoing
- Parking lot ongoing
- Eagle Rd, Where Phase 1 stopped to Intersection of Eagle and Old State.
- Starting June 6th, Eagle Road will be closed between Plaza and Old State.
- Veolia working on Tie-overs and testing
- Storm Drain ongoing
- Anticipated paving June 26th
Share June 13, 2025 on Facebook
Share June 13, 2025 on Linkedin
Email June 13, 2025 link
Olde Park
- Landscape and brick pavers ongoing.
Aikens between 2nd and Eagle
Starting June 6th, Eagle Road will be closed between Plaza and Old State. Veolia installing water line. Excavation and storm drain installation.
Share June 6, 2025 on Facebook
Share June 6, 2025 on Linkedin
Email June 6, 2025 link
Olde Park
- Landscape and brick pavers ongoing.
Aikens between 2nd and Eagle
- Placing silva cells.
- Electrical work ongoing.
- Curb and sidewalk ongoing.
- Asphalt paving was done May 29th.
- Road to be opened June 6th after striping and manhole collaring is complete.
Olde Park To Eagle Rd
- Road closure anticipated May 5th - June 6th.
- Silva cells ongoing.
- Prepping and placing sidewalk crossings.
- Paving was done May 30th.
Starting June 6th, Eagle Road will be closed between Plaza and Old State. Veolia installing water line installation. Excavation and storm drain installation.