Downtown Eagle Mobility Improvements: Eagle Road and State Street
The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.
The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.
Goals
The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.
The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.
The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.
Goals
The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.
-
November 22, 2024
Share November 22, 2024 on Facebook Share November 22, 2024 on Twitter Share November 22, 2024 on Linkedin Email November 22, 2024 link22 Nov 2024Eagle Road in front of Albertsons
- Power pole areas repaired and paved.
- Swale ongoing.
2nd Street and State Street
- Crosswalks being installed.
- Pavers being installed.
- Signal turn on anticipated November 21st.
-
November 15, 2024
Share November 15, 2024 on Facebook Share November 15, 2024 on Twitter Share November 15, 2024 on Linkedin Email November 15, 2024 link15 Nov 2024Eagle Road in front of Albertsons
- Idaho Power poles relocated.
- Once 2nd street is open, moving back to finish Eagle Rd.
2nd Street and State Street
- State Street open heading east and west.
- Silva Cells installed.
- Signal installed.
- Curb and sidewalk ongoing.
- 2nd Street crosswalk being placed.
-
November 7, 2024
Share November 7, 2024 on Facebook Share November 7, 2024 on Twitter Share November 7, 2024 on Linkedin Email November 7, 2024 link07 Nov 2024Eagle Road in front of Albertsons
- Idaho Power poles relocated.
- Once 2nd street is open, moving back to finish Eagle Rd.
2nd Street and State Street
- State Street open heading east and west.
- Silva Cells installed.
- Signal installed.
- Curb and sidewalk ongoing.
- 2nd Street crosswalk being placed.
-
November 1, 2024
Share November 1, 2024 on Facebook Share November 1, 2024 on Twitter Share November 1, 2024 on Linkedin Email November 1, 2024 link01 Nov 2024Eagle Road in front of Albertsons
- Idaho Power poles relocated.
- Once 2nd street is open - moving back over to finish Eagle Rd.
2nd Street and State Street
- 2nd and State intersection closed.
- Silva cells installed.
- Signal installed.
- Curb and sidewalk ongoing.
- Asphalt complete.
-
October 24, 2024
Share October 24, 2024 on Facebook Share October 24, 2024 on Twitter Share October 24, 2024 on Linkedin Email October 24, 2024 link24 Oct 2024Eagle Road in front of Albertsons
- Idaho Power relocating poles
2nd Street and State Street
- 2nd and State intersection closed.
- Silva Cells installed.
- Light pole bases, conduit and signal work ongoing.
- Flying poles October 24th.
- Curb and sidewalk ongoing.
- Asphalt paving moved to October 29th.
- Idaho Power adjusting lines starting October 28th on 2nd Street.
-
October 17, 2024
Share October 17, 2024 on Facebook Share October 17, 2024 on Twitter Share October 17, 2024 on Linkedin Email October 17, 2024 link17 Oct 2024Eagle Road in front of Albertsons
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st
2nd Street and State Street
- 2nd and State intersection closed
- Silva Cells installed
- Light pole bases, conduit and signal work ongoing
- Curb and sidewalk being prepped
- Curb and sidewalk being placed October 10th – October 22nd
- Asphalt paving anticipated October 24th
-
October 10, 2024
Share October 10, 2024 on Facebook Share October 10, 2024 on Twitter Share October 10, 2024 on Linkedin Email October 10, 2024 link10 Oct 2024Eagle Road in front of Albertsons
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.
2nd Street and State Street
- 2nd and State intersection closed.
- Silva cells being installed.
- Light pole bases, conduit and signal work ongoing.
- Curb and sidewalk being prepped.
- Curb and sidewalk being placed October 10th – October 22nd.
- Asphalt paving anticipated October 24th.
-
Pedestrian Detour Map
Share Pedestrian Detour Map on Facebook Share Pedestrian Detour Map on Twitter Share Pedestrian Detour Map on Linkedin Email Pedestrian Detour Map link04 Oct 2024 -
October 4, 2024
Share October 4, 2024 on Facebook Share October 4, 2024 on Twitter Share October 4, 2024 on Linkedin Email October 4, 2024 link04 Oct 2024Eagle Road in front of Albertsons
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.
2nd Street and State Street
- 2nd and State intersection closed starting September 25th.
- Signal pole bases being placed.
- Concrete removed on North side.
- Storm drain complete.
- Silva Cells being installed.
- Light pole bases, conduit and signal work ongoing.
- Curb and sidewalk being prepped.
-
September 26, 2024
Share September 26, 2024 on Facebook Share September 26, 2024 on Twitter Share September 26, 2024 on Linkedin Email September 26, 2024 link26 Sep 2024Eagle Road in front of Albertsons
- Pavement markings remaining.
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.
2nd Street and State Street
- 2nd and State intersection closed starting September 25th.
- Signal pole bases being placed.
- Concrete removed on north side.
- Storm drain and Veola water work ongoing.
- Historic lights being removed September 30th.
- Electrical conduit being placed afterwards.
Related projects
Live Projects
Materials from Phase 2 Construction Open House
Construction Open House
-
January 23 2025
-
January 31 2024
Monthly Public Pop Up
-
August 29 2024
-
July 20 2024
-
June 27 2024
-
May 30 2024
-
April 25 2024
Drone Footage
-
March 11 2025
-
November 13 2024
-
October 10 2024
-
September 13 2024
-
August 23 2024
Materials from Construction Open House
Follow Project
Who's Listening
-
Sr. Project Manager
Phone 208-387-6100 Email projects@achdidaho.org (External link) -
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org (External link) -
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org (External link)
History
The design was the outcome of the Eagle Road and States Street Concept Design, an effort that began in 2012. After working with the community and the City of Eagle to evaluate multiple alternatives, the ACHD Commission approved the City's request to design and construct the Quadrant Alternative. This alternative best balances the need to safely accommodate the expected traffic growth, minimize impacts to adjacent properties and parking, and make downtown Eagle more walkable and bikeable, as well as being respectful of downtown's history and small town feel.