Phase 2 of the Downtown Eagle Mobility Improvements project is expected to begin next week.
Beginning Monday, Aikens Street in Eagle will be closed from Olde Park Place to east of 1st Street, where the street currently ends. Additionally, Olde Park Place will be closed between State Street (Old State) and Aikens Street.
Business and residential access will be maintained during the closure. To help accommodate local access, 1st Street will temporary become a two-way street from
Aikens Street up to the alley. The alley will temporarily be a one-way alley for eastbound traffic only. (See detour map)
These closures and temporary access points are expected to be in place until spring of 2025.
Share Phase 2 Update - January 23, 2025 on Facebook
Share Phase 2 Update - January 23, 2025 on Linkedin
Email Phase 2 Update - January 23, 2025 link
- Clearing and grubbing Aikens Street for utilities to relocate lines.
- Veolia closed 2nd Street for water tie in.
Share January 23, 2025 on Facebook
Share January 23, 2025 on Linkedin
Email January 23, 2025 link
Eagle Road in front of Albertsons
- Culvert ongoing.
- Swale ongoing.
2nd Street and State Street
Share Eagle Road & State - Phase 2 - Update on Facebook
Share Eagle Road & State - Phase 2 - Update on Linkedin
Email Eagle Road & State - Phase 2 - Update link
- Clearing and grubbing Aikens Street for utilities to relocate lines.
Share January 17, 2025 on Facebook
Share January 17, 2025 on Linkedin
Email January 17, 2025 link
Eagle Road in front of Albertsons
- Culvert being moved pending approval.
- Swale ongoing
2nd Street and State Street.
- Tree grates remaining.
- Decision on crossing ongoing.
Share January 10, 2025 on Facebook
Share January 10, 2025 on Linkedin
Email January 10, 2025 link
Eagle Road in front of Albertsons
- Culvert being moved pending approval.
- Swale ongoing.
2nd Street and State Street
- Tree grates remaining.
- Decision on crossing ongoing.
Share Construction Kick Off Meeting - Public Open House on Facebook
Share Construction Kick Off Meeting - Public Open House on Linkedin
Email Construction Kick Off Meeting - Public Open House link
Please join ACHD Staff and the Contractor on Thursday, January 23rd from 4-7pm at the Residence Inn, 515 S Palmetto Ave, Eagle for a Construction Open House to learn more about the Downtown Eagle Mobility Improvement Project - Phase 2.
Share January 3, 2025 on Facebook
Share January 3, 2025 on Linkedin
Email January 3, 2025 link
Eagle Road in front of Albertsons
- Culvert being moved pending approval
- Swale ongoing
2nd Street and State Street
Share December 20, 2024 on Facebook
Share December 20, 2024 on Linkedin
Email December 20, 2024 link
Eagle Road in front of Albertsons
- Culvert being moved pending approval.
- Swale ongoing.
2nd Street and State Street
Share December 12, 2024 on Facebook
Share December 12, 2024 on Linkedin
Email December 12, 2024 link
Eagle Road in front of Albertsons
- Culvert being moved pending approval.
- Swale ongoing.
2nd Street and State Street