Downtown Eagle Mobility Improvements: Eagle Road and State Street

Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Facebook Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Twitter Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Linkedin Email Downtown Eagle Mobility Improvements: Eagle Road and State Street link

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

*Phase 1 of the project is expected to be complete by Fall 2024

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

*Phase 1 of the project is expected to be complete by Fall 2024

  • September 20, 2024

    Share September 20, 2024 on Facebook Share September 20, 2024 on Twitter Share September 20, 2024 on Linkedin Email September 20, 2024 link

    Eagle Road in front of Albertsons

    • Pavement markings remaining.
    • Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.


    2nd Street and State Street

    • Started September 3rd - Underground work first. Veolia ongoing.
    • Signal pole bases being placed.
    • One way traffic on State St. - East bound only first stage.
    • Century Link lowering facilities.


  • September 13, 2024

    Share September 13, 2024 on Facebook Share September 13, 2024 on Twitter Share September 13, 2024 on Linkedin Email September 13, 2024 link

    Eagle Road in front of Albertsons

    • Pavement markings remaining.
    • Waiting on Idaho Power to relocate power poles, anticipated to start the week of Sept 30th.

    2nd Street and State Street

    • Started September 3rd.
    • Underground work first - Veolia ongoing.
    • Signal pole bases being placed.
    • One way traffic on State St. - East bound only traffic.
    • Century Link lowering utilities.


  • September 6, 2024

    Share September 6, 2024 on Facebook Share September 6, 2024 on Twitter Share September 6, 2024 on Linkedin Email September 6, 2024 link

    Front of Albertsons

    • Pavement markings remaining.
    • Waiting on Idaho Power to relocate power poles.


    2nd Street and State Street

    • Work started September 3rd.
    • Underground work is being done first - Veolia working nights.
    • Signal pole bases being placed.
    • One way traffic on State St. East bound only.
  • August 30, 2024

    Share August 30, 2024 on Facebook Share August 30, 2024 on Twitter Share August 30, 2024 on Linkedin Email August 30, 2024 link
    • Front of Albertsons - Pavement markings remaining. Waiting on Idaho Power to relocate power poles.
    • 2nd Street and State Street. Anticipating starting September 3rd. Underground work will start first. One way traffic on State State (Old State) - East bound only first stage.
  • Detour Map & Information - Old State & 2nd Street

    Share Detour Map & Information - Old State & 2nd Street on Facebook Share Detour Map & Information - Old State & 2nd Street on Twitter Share Detour Map & Information - Old State & 2nd Street on Linkedin Email Detour Map & Information - Old State & 2nd Street link

    2nd Street and Old State Street

    • Anticipating starting September 3rd - Underground work first.
    • Detour and map information below.
    • Lane restrictions on Old State at 2nd Street. Street closed on 2nd just north of Old State at the intersection.
    • Eastbound traffic only on Old State.
    • Westbound traffic on Old State must use Plaza Drive for Business access.


  • August 23, 2024

    Share August 23, 2024 on Facebook Share August 23, 2024 on Twitter Share August 23, 2024 on Linkedin Email August 23, 2024 link

    Eagle Road between Plaza and Aikens

    • Veolia has closed Aikens for water change over - August 19th - 23rd - Ongoing.

    Front of Albertsons

    • Concrete islands.
    • Pavement markings remaining.

    2nd Street and State Street

    • Anticipating starting September 3rd.
    • Underground work will start first.


  • August 15, 2024

    Share August 15, 2024 on Facebook Share August 15, 2024 on Twitter Share August 15, 2024 on Linkedin Email August 15, 2024 link

    Eagle Road between Plaza and Aikens

    • Veolia will close Aikens for water change over. Anticipated August 19th – 23rd.

    Front of Albertsons

    • Concrete islands. Pavement markings remaining.

    2nd Street and State Street.

    • Anticipating starting September 3rd - Underground work first.
  • August 9, 2024

    Share August 9, 2024 on Facebook Share August 9, 2024 on Twitter Share August 9, 2024 on Linkedin Email August 9, 2024 link

    Eagle Road between Plaza and Aikens

    • Veolia will close Aikens for water change over - Anticipated August 19th – 25th. Please see detour map below.

    Front of Albertsons

    • Will continue working on Plaza side
    • Retaining wall ongoing.
    • North side of Plaza started July 19th.
    • One approach at a time.
    • Albertsons approach started August 5th - ongoing. Please review the map below.

    2nd Street and State Street

    • Anticipated to start September 3rd.
    • Underground work will happen first.


    Please review the map below with the information about the closure on Eagle at Aikens.

    Please contact Veolia directly if you have concerns.

    Veolia - 208.749.8189


    Please review the map below on how to enter and exit the the grocery store and shops on Plaza.


  • August 2, 2024

    Share August 2, 2024 on Facebook Share August 2, 2024 on Twitter Share August 2, 2024 on Linkedin Email August 2, 2024 link

    Eagle Road between Plaza and Aikens

    • Veolia will need to close Aikens for water change over - Anticipated end of August.

    Front of Albertsons

    • Will be working on Plaza side.
    • Retaining wall ongoing - North side of Plaza started July 19th - One approach at a time.
    • Albertsons approach anticipating starting August 5th.

    Eagle and Plaza Intersection

    • Paving on Eagle complete.
    • Signal at Eagle and Plaza was turned on July 18th.


  • July 26, 2024

    Share July 26, 2024 on Facebook Share July 26, 2024 on Twitter Share July 26, 2024 on Linkedin Email July 26, 2024 link

    Eagle Road between Plaza and Aikens

    • Veolia will need to close Eagle Road at Aikens for water change over. Anticipated August 5th for a week - night work only.

    Front of Albertsons

    • Working on Plaza side.
    • Retaining wall construction ongoing.
    • North side of Plaza started July 19th - One approach at a time.

    Eagle and Plaza Intersection

    • Paving on Eagle complete.
    • Signal at Eagle and Plaza was turned on July 18th.
Page last updated: 15 Nov 2024, 10:45 AM