Downtown Eagle Mobility Improvements: Eagle Road and State Street
This project is substantially complete.
The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.
The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.
Goals
The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.
The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.
The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.
Goals
The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.
This project is substantially complete.
-
December 12, 2024
Share December 12, 2024 on Facebook Share December 12, 2024 on Twitter Share December 12, 2024 on Linkedin Email December 12, 2024 linkEagle Road in front of Albertsons
- Culvert being moved pending approval.
- Swale ongoing.
2nd Street and State Street
- Landscaping ongoing.
Eagle Road in front of Albertsons
- Culvert being moved pending approval.
- Swale ongoing.
2nd Street and State Street
- Landscaping ongoing.
This project is substantially complete.
-
December 6, 2024
Share December 6, 2024 on Facebook Share December 6, 2024 on Twitter Share December 6, 2024 on Linkedin Email December 6, 2024 linkEagle Road in front of Albertsons
- Culvert being moved pending approval.
- Swale ongoing.
2nd Street and State Street
- Landscaping ongoing.
Eagle Road in front of Albertsons
- Culvert being moved pending approval.
- Swale ongoing.
2nd Street and State Street
- Landscaping ongoing.
This project is substantially complete.
-
November 22, 2024
Share November 22, 2024 on Facebook Share November 22, 2024 on Twitter Share November 22, 2024 on Linkedin Email November 22, 2024 linkEagle Road in front of Albertsons
- Power pole areas repaired and paved.
- Swale ongoing.
2nd Street and State Street
- Crosswalks being installed.
- Pavers being installed.
- Signal turn on anticipated November 21st.
Eagle Road in front of Albertsons
- Power pole areas repaired and paved.
- Swale ongoing.
2nd Street and State Street
- Crosswalks being installed.
- Pavers being installed.
- Signal turn on anticipated November 21st.
This project is substantially complete.
-
November 15, 2024
Share November 15, 2024 on Facebook Share November 15, 2024 on Twitter Share November 15, 2024 on Linkedin Email November 15, 2024 linkEagle Road in front of Albertsons
- Idaho Power poles relocated.
- Once 2nd street is open, moving back to finish Eagle Rd.
2nd Street and State Street
- State Street open heading east and west.
- Silva Cells installed.
- Signal installed.
- Curb and sidewalk ongoing.
- 2nd Street crosswalk being placed.
Eagle Road in front of Albertsons
- Idaho Power poles relocated.
- Once 2nd street is open, moving back to finish Eagle Rd.
2nd Street and State Street
- State Street open heading east and west.
- Silva Cells installed.
- Signal installed.
- Curb and sidewalk ongoing.
- 2nd Street crosswalk being placed.
This project is substantially complete.
-
November 7, 2024
Share November 7, 2024 on Facebook Share November 7, 2024 on Twitter Share November 7, 2024 on Linkedin Email November 7, 2024 linkEagle Road in front of Albertsons
- Idaho Power poles relocated.
- Once 2nd street is open, moving back to finish Eagle Rd.
2nd Street and State Street
- State Street open heading east and west.
- Silva Cells installed.
- Signal installed.
- Curb and sidewalk ongoing.
- 2nd Street crosswalk being placed.
Eagle Road in front of Albertsons
- Idaho Power poles relocated.
- Once 2nd street is open, moving back to finish Eagle Rd.
2nd Street and State Street
- State Street open heading east and west.
- Silva Cells installed.
- Signal installed.
- Curb and sidewalk ongoing.
- 2nd Street crosswalk being placed.
This project is substantially complete.
-
November 1, 2024
Share November 1, 2024 on Facebook Share November 1, 2024 on Twitter Share November 1, 2024 on Linkedin Email November 1, 2024 linkEagle Road in front of Albertsons
- Idaho Power poles relocated.
- Once 2nd street is open - moving back over to finish Eagle Rd.
2nd Street and State Street
- 2nd and State intersection closed.
- Silva cells installed.
- Signal installed.
- Curb and sidewalk ongoing.
- Asphalt complete.
Eagle Road in front of Albertsons
- Idaho Power poles relocated.
- Once 2nd street is open - moving back over to finish Eagle Rd.
2nd Street and State Street
- 2nd and State intersection closed.
- Silva cells installed.
- Signal installed.
- Curb and sidewalk ongoing.
- Asphalt complete.
This project is substantially complete.
-
October 24, 2024
Share October 24, 2024 on Facebook Share October 24, 2024 on Twitter Share October 24, 2024 on Linkedin Email October 24, 2024 linkEagle Road in front of Albertsons
- Idaho Power relocating poles
2nd Street and State Street
- 2nd and State intersection closed.
- Silva Cells installed.
- Light pole bases, conduit and signal work ongoing.
- Flying poles October 24th.
- Curb and sidewalk ongoing.
- Asphalt paving moved to October 29th.
- Idaho Power adjusting lines starting October 28th on 2nd Street.
Eagle Road in front of Albertsons
- Idaho Power relocating poles
2nd Street and State Street
- 2nd and State intersection closed.
- Silva Cells installed.
- Light pole bases, conduit and signal work ongoing.
- Flying poles October 24th.
- Curb and sidewalk ongoing.
- Asphalt paving moved to October 29th.
- Idaho Power adjusting lines starting October 28th on 2nd Street.
This project is substantially complete.
-
October 17, 2024
Share October 17, 2024 on Facebook Share October 17, 2024 on Twitter Share October 17, 2024 on Linkedin Email October 17, 2024 linkEagle Road in front of Albertsons
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st
2nd Street and State Street
- 2nd and State intersection closed
- Silva Cells installed
- Light pole bases, conduit and signal work ongoing
- Curb and sidewalk being prepped
- Curb and sidewalk being placed October 10th – October 22nd
- Asphalt paving anticipated October 24th
Eagle Road in front of Albertsons
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st
2nd Street and State Street
- 2nd and State intersection closed
- Silva Cells installed
- Light pole bases, conduit and signal work ongoing
- Curb and sidewalk being prepped
- Curb and sidewalk being placed October 10th – October 22nd
- Asphalt paving anticipated October 24th
This project is substantially complete.
-
October 10, 2024
Share October 10, 2024 on Facebook Share October 10, 2024 on Twitter Share October 10, 2024 on Linkedin Email October 10, 2024 linkEagle Road in front of Albertsons
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.
2nd Street and State Street
- 2nd and State intersection closed.
- Silva cells being installed.
- Light pole bases, conduit and signal work ongoing.
- Curb and sidewalk being prepped.
- Curb and sidewalk being placed October 10th – October 22nd.
- Asphalt paving anticipated October 24th.
Eagle Road in front of Albertsons
- Waiting on Idaho Power to relocate power poles, anticipated to start the week of October 21st.
2nd Street and State Street
- 2nd and State intersection closed.
- Silva cells being installed.
- Light pole bases, conduit and signal work ongoing.
- Curb and sidewalk being prepped.
- Curb and sidewalk being placed October 10th – October 22nd.
- Asphalt paving anticipated October 24th.
This project is substantially complete.
-
Pedestrian Detour Map
Share Pedestrian Detour Map on Facebook Share Pedestrian Detour Map on Twitter Share Pedestrian Detour Map on Linkedin Email Pedestrian Detour Map link

This project is substantially complete.
Materials from Phase 2 Construction Open House
Drone Footage
-
October 24 2025
-
September 16 2025
-
August 29 2025
-
July 25 2025
-
June 16 2025
Who's Listening
-
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org -
Project Manager
Phone 208-387-6100 Email connect@achdidaho.org
Construction Open House
-
January 23 2025
-
January 31 2024
Materials from Construction Open House
Monthly Public Pop Up
-
August 29 2024
-
July 20 2024
-
June 27 2024
-
May 30 2024
-
April 25 2024
History
The design was the outcome of the Eagle Road and States Street Concept Design, an effort that began in 2012. After working with the community and the City of Eagle to evaluate multiple alternatives, the ACHD Commission approved the City's request to design and construct the Quadrant Alternative. This alternative best balances the need to safely accommodate the expected traffic growth, minimize impacts to adjacent properties and parking, and make downtown Eagle more walkable and bikeable, as well as being respectful of downtown's history and small town feel.





