Downtown Eagle Mobility Improvements: Eagle Road and State Street

Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Facebook Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Twitter Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Linkedin Email Downtown Eagle Mobility Improvements: Eagle Road and State Street link

This project is substantially complete. 

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

This project is substantially complete. 

  • November 7, 2025

    Share November 7, 2025 on Facebook Share November 7, 2025 on Twitter Share November 7, 2025 on Linkedin Email November 7, 2025 link

    This project is substantially complete

  • October 31, 2025

    Share October 31, 2025 on Facebook Share October 31, 2025 on Twitter Share October 31, 2025 on Linkedin Email October 31, 2025 link
    • Project Substantially complete.
    • State Street and 2nd Street - Night closure to replace crosswalk with colored concrete on October 30th.
    • Eagle Rd - Eagle Arch Sign being installed November 6-7th. Road Closed from 9am – 4 pm.
  • Nest Quest!

    Share Nest Quest! on Facebook Share Nest Quest! on Twitter Share Nest Quest! on Linkedin Email Nest Quest! link

    Ready, set, soar! πŸ¦…


    The Nest Quest begins Saturday, November 1! Join in the fun for this month long adventure to rediscover Downtown Eagle, support your favorite local businesses, and learn about the recent improvements made to the downtown core.

    Fly solo or flock together with friends! Follow the steps below to complete fun quests and rack up points. You could even win prizes from local shops and restaurants!

    πŸ‘‰ Download the GooseChase app
    πŸ”Ž Join β€œNest Quest” or use code R6F9V2
    πŸ“… Play throughout November

    See you on the Quest!

  • Save the Date: Ribbon Cutting November 13

    Share Save the Date: Ribbon Cutting November 13 on Facebook Share Save the Date: Ribbon Cutting November 13 on Twitter Share Save the Date: Ribbon Cutting November 13 on Linkedin Email Save the Date: Ribbon Cutting November 13 link

    We are so excited to celebrate the completion of the Downtown Eagle Mobility Improvements Project!

    The Ada County Highway District invites businesses and community members are invited to a formal Ribbon Cutting to mark the completion of the project.

    Mark your calendars for Thursday, November 13th, at 3pm. The ceremony will take place near the new City of Eagle sign, which will be installed next week (November 6-7).

    Formal invite and more information to follow- stay tuned!

  • October 24, 2025 - New Traffic Pattern

    Share October 24, 2025 - New Traffic Pattern on Facebook Share October 24, 2025 - New Traffic Pattern on Twitter Share October 24, 2025 - New Traffic Pattern on Linkedin Email October 24, 2025 - New Traffic Pattern link

  • October 24, 2025

    Share October 24, 2025 on Facebook Share October 24, 2025 on Twitter Share October 24, 2025 on Linkedin Email October 24, 2025 link

    Aikens between 2nd and Eagle

    • Landscaping is ongoing. Water tie-in is required for basin.
    • Water tie in started October 22nd with an anticipated time frame of 4 days.

    State Street, Eagle to 2nd Street

    • Brick pavers ongoing on both sides.
    • Asphalt paving complete.
    • Colored concrete installed

    State and 2nd Intersection

    • Replacing crosswalk with concrete.
    • After 2nd Street is complete.


  • October 17, 2025

    Share October 17, 2025 on Facebook Share October 17, 2025 on Twitter Share October 17, 2025 on Linkedin Email October 17, 2025 link

    Aikens between 2nd and Eagle

    Landscaping is ongoing. Water tie-in is required for basin. Tie in Anticipated starting week of Oct 20th once State St. is open.

    State Street, Eagle to 2nd Street

    Brick Pavers ongoing on both sides. Sidewalk started on north side. Silva Cells being installed. Paving complete. Colored concrete crosswalks being installed.

  • October 10, 2025

    Share October 10, 2025 on Facebook Share October 10, 2025 on Twitter Share October 10, 2025 on Linkedin Email October 10, 2025 link

    Aikens between 2nd and Eagle

    • Landscaping is ongoing. Water tie-in is required for basin.

    Eagle Rd & State Intersection

    • Signal turned on September 11th

    .State Street, Eagle to 2nd Street

    • Road closed starting September 2nd
    • Curb placed on south side
    • Brick Pavers ongoing on side
    • Sidewalk started on north side
    • Silva Cells being installed
    • Weather permitting – Paving October 10th
    • Colored concrete crosswalks will be installed after pavement
  • October 2, 2025

    Share October 2, 2025 on Facebook Share October 2, 2025 on Twitter Share October 2, 2025 on Linkedin Email October 2, 2025 link

    Aikens between 2nd and Eagle

    • Landscaping ongoing.
    • Water tie in required for basin.

    Eagle Rd & State Intersection

    • Signal turn on Sept 11th.

    State Street, Eagle to 2nd St - Road closed starting September 2nd. Curb placed on south side. Brick Pavers ongoing on side. Sidewalk started on North side. Silva Cells being installed.


  • September 26, 2025

    Share September 26, 2025 on Facebook Share September 26, 2025 on Twitter Share September 26, 2025 on Linkedin Email September 26, 2025 link

    Aikens between 2nd and Eagle

    • Landscaping ongoing
    • Water tie in required for basin

    Eagle Rd & State Intersection

    • Signal turn on Sept 11th

    State Street, Eagle to 2nd St

    • Road closed starting September 2nd
    • Curb being placed on south side
    • Sidewalk ongoing between Eagle and 1st Street
    • Underground electrical ongoing
    • Silva Cells being installed