Garden Street Sidewalks & Bikeway, Albion Street to Greenbelt
This project is substantially complete.
The Ada County Highway District (ACHD) is designing sidewalks for Garden Street between Albion Street and Emerald Street, as well as a bikeway between Albion Street and the Greenbelt. The purpose of this project is to improve safety and increase connectivity for pedestrians and bicyclists. This project now includes Garden Street, Franklin Road to Bethel Street that was designed in 2019.
Project Description
Sidewalk
- Add curb, gutter, and sidewalk on both sides of Garden Street, Albion Street to Emerald Street; Reconstruct some existing sidewalk as necessary.
- Improve pedestrian ramps.
- Add bulb-outs at key locations.
Bikeway
- Add lane markings & wayfinding signage to create a bikeway on Garden Street between Albion Street and the Greenbelt.
- Improve alignment of the Garden Street and Franklin Street intersection and add an enhanced pedestrian/bike signal.
Roadway
- Reconstruct the roadway.
- Replace pipes and the bridge north of Mason Drive.
- Upgrade existing speed humps to "speed cushions", which will ease emergency vehicle access.
- Utility work.
- Most on-street parking will be retained however, some parking will be impacted.
Purpose
- Increase connectivity for pedestrians
- Improve quality of the street
Background
This project was one of several identified in the 2012 Boise Central Bench Neighborhood Bicycle and Pedestrian Plan as a priority for sidewalk completion.
The Ada County Highway District (ACHD) is designing sidewalks for Garden Street between Albion Street and Emerald Street, as well as a bikeway between Albion Street and the Greenbelt. The purpose of this project is to improve safety and increase connectivity for pedestrians and bicyclists. This project now includes Garden Street, Franklin Road to Bethel Street that was designed in 2019.
Project Description
Sidewalk
- Add curb, gutter, and sidewalk on both sides of Garden Street, Albion Street to Emerald Street; Reconstruct some existing sidewalk as necessary.
- Improve pedestrian ramps.
- Add bulb-outs at key locations.
Bikeway
- Add lane markings & wayfinding signage to create a bikeway on Garden Street between Albion Street and the Greenbelt.
- Improve alignment of the Garden Street and Franklin Street intersection and add an enhanced pedestrian/bike signal.
Roadway
- Reconstruct the roadway.
- Replace pipes and the bridge north of Mason Drive.
- Upgrade existing speed humps to "speed cushions", which will ease emergency vehicle access.
- Utility work.
- Most on-street parking will be retained however, some parking will be impacted.
Purpose
- Increase connectivity for pedestrians
- Improve quality of the street
Background
This project was one of several identified in the 2012 Boise Central Bench Neighborhood Bicycle and Pedestrian Plan as a priority for sidewalk completion.
This project is substantially complete.
-
July 19, 2024
Share July 19, 2024 on Facebook Share July 19, 2024 on Twitter Share July 19, 2024 on Linkedin Email July 19, 2024 link- Albion to Franklin
- Landscaping ongoing.
- Franklin to Alpine
- Sidewalk ongoing.
- Curb at Alpine remaining.
- Landscaping ongoing. Alpine Corner ongoing.
- Emerald to Bethel
- Storm drain at Emerald.
- Franklin Intersection
- PHB signal poles installed June 18th. Activated July 10th.
- Alpine to Morris Hill
- Excavation started May 28th.
- ¾” aggregate base placed.
- Curb placed.
- Sidewalk ongoing.
- Concrete intersection being placed July 18th.
- Albion to Franklin
- Landscaping ongoing.
- Franklin to Alpine
- Sidewalk ongoing.
- Curb at Alpine remaining.
- Landscaping ongoing. Alpine Corner ongoing.
- Emerald to Bethel
- Storm drain at Emerald.
- Franklin Intersection
- PHB signal poles installed June 18th. Activated July 10th.
- Alpine to Morris Hill
- Excavation started May 28th.
- ¾” aggregate base placed.
- Curb placed.
- Sidewalk ongoing.
- Concrete intersection being placed July 18th.
This project is substantially complete.
- Albion to Franklin
-
July 12, 2024
Share July 12, 2024 on Facebook Share July 12, 2024 on Twitter Share July 12, 2024 on Linkedin Email July 12, 2024 link- Albion to Franklin - Landscaping ongoing.
- Franklin to Alpine - Sidewalk ongoing. Curb at Alpine remaining. Landscaping ongoing. SW Alpine Corner ongoing.
- Emerald to Bethel - Seepage bed ongoing.
- Franklin Intersection - PHB signal poles installed June 18th. Activated July 10th.
- Alpine to Morris Hill - Excavation started May 28th. ¾” aggregate base placed. Curb placed. Sidewalk ongoing.
- Albion to Franklin - Landscaping ongoing.
- Franklin to Alpine - Sidewalk ongoing. Curb at Alpine remaining. Landscaping ongoing. SW Alpine Corner ongoing.
- Emerald to Bethel - Seepage bed ongoing.
- Franklin Intersection - PHB signal poles installed June 18th. Activated July 10th.
- Alpine to Morris Hill - Excavation started May 28th. ¾” aggregate base placed. Curb placed. Sidewalk ongoing.
This project is substantially complete.
-
June 28, 2024
Share June 28, 2024 on Facebook Share June 28, 2024 on Twitter Share June 28, 2024 on Linkedin Email June 28, 2024 link- Albion to Franklin - Landscaping ongoing.
- Franklin to Alpine - Sidewalk ongoing. Curb at Alpine remaining - Landscaping ongoing.
- Emerald to Bethel - Storm drain work ongoing. Anticipated complete by June 26th. Veolia placing services.
- Franklin Intersection - PHB signal poles installed June 18th.
- Alpine to Morris Hill - Excavation started May 28th. ¾” aggregate base placed. Curb being cut. Curb being placed started June 24th.
- Albion to Franklin - Landscaping ongoing.
- Franklin to Alpine - Sidewalk ongoing. Curb at Alpine remaining - Landscaping ongoing.
- Emerald to Bethel - Storm drain work ongoing. Anticipated complete by June 26th. Veolia placing services.
- Franklin Intersection - PHB signal poles installed June 18th.
- Alpine to Morris Hill - Excavation started May 28th. ¾” aggregate base placed. Curb being cut. Curb being placed started June 24th.
This project is substantially complete.
-
June 21, 2024
Share June 21, 2024 on Facebook Share June 21, 2024 on Twitter Share June 21, 2024 on Linkedin Email June 21, 2024 linkAlbion to Franklin - Landscaping ongoing.
Franklin to Alpine - Sidewalk ongoing. Curb at Alpine remaining. Landscaping ongoing.
Emerald to Bethel - Storm drain work ongoing. Anticipated complete by June 26th. Veolia placing services.
Franklin Intersection - PHB signal poles installed June 18th.
Alpine to Morris Hill - Excavation started May 28th. ¾” placed. Curb being cut. Curb being placed started June 24th.
Albion to Franklin - Landscaping ongoing.
Franklin to Alpine - Sidewalk ongoing. Curb at Alpine remaining. Landscaping ongoing.
Emerald to Bethel - Storm drain work ongoing. Anticipated complete by June 26th. Veolia placing services.
Franklin Intersection - PHB signal poles installed June 18th.
Alpine to Morris Hill - Excavation started May 28th. ¾” placed. Curb being cut. Curb being placed started June 24th.
This project is substantially complete.
-
June 14, 2024
Share June 14, 2024 on Facebook Share June 14, 2024 on Twitter Share June 14, 2024 on Linkedin Email June 14, 2024 link- Albion to Franklin
- Landscaping ongoing
- Franklin to Alpine
- Sidewalk ongoing
- Curb at Alpine remaining
- Landscaping ongoing
- Emerald to Bethel
- Storm drain work ongoing.
- Veolia placing services
- Franklin Intersection
- Irrigation complete
- PHB signal work ongoing
- Alpine to Morris Hill
- Excavation started May 28th
- ¾” placed
- Curb being cut off
- Albion to Franklin
- Landscaping ongoing
- Franklin to Alpine
- Sidewalk ongoing
- Curb at Alpine remaining
- Landscaping ongoing
- Emerald to Bethel
- Storm drain work ongoing.
- Veolia placing services
- Franklin Intersection
- Irrigation complete
- PHB signal work ongoing
- Alpine to Morris Hill
- Excavation started May 28th
- ¾” placed
- Curb being cut off
This project is substantially complete.
- Albion to Franklin
-
June 7, 2024
Share June 7, 2024 on Facebook Share June 7, 2024 on Twitter Share June 7, 2024 on Linkedin Email June 7, 2024 link- Albion to Franklin
- Landscaping ongoing
- Franklin to Alpine
- Sidewalk ongoing
- Curb at Alpine remaining
- Landscaping ongoing
- Emerald to Bethel
- Storm drain work ongoing
- Veolia placing services
- Franklin Intersection
- Irrigation complete
- PHB signal work ongoing
- Alpine to Morris Hill
- Excavation started May 28th
- ¾” placed
- Albion to Franklin
- Landscaping ongoing
- Franklin to Alpine
- Sidewalk ongoing
- Curb at Alpine remaining
- Landscaping ongoing
- Emerald to Bethel
- Storm drain work ongoing
- Veolia placing services
- Franklin Intersection
- Irrigation complete
- PHB signal work ongoing
- Alpine to Morris Hill
- Excavation started May 28th
- ¾” placed
This project is substantially complete.
- Albion to Franklin
-
May 31, 2024
Share May 31, 2024 on Facebook Share May 31, 2024 on Twitter Share May 31, 2024 on Linkedin Email May 31, 2024 link- Albion to Franklin - Sidewalk ongoing. Paving complete. Landscaping remaining.
- Franklin to Alpine - Sidewalk ongoing. Curb at Alpine remaining. Landscaping ongoing.
- Emerald to Bethel - Storm drain work ongoing. Veolia placing services.
- Franklin Intersection - Irrigation complete. PHB signal work ongoing.
- Alpine to Morris Hill - Excavation started May 28th.
- Albion to Franklin - Sidewalk ongoing. Paving complete. Landscaping remaining.
- Franklin to Alpine - Sidewalk ongoing. Curb at Alpine remaining. Landscaping ongoing.
- Emerald to Bethel - Storm drain work ongoing. Veolia placing services.
- Franklin Intersection - Irrigation complete. PHB signal work ongoing.
- Alpine to Morris Hill - Excavation started May 28th.
This project is substantially complete.
-
May 23, 2024
Share May 23, 2024 on Facebook Share May 23, 2024 on Twitter Share May 23, 2024 on Linkedin Email May 23, 2024 link- Albion to Franklin - Sidewalk ongoing. Paving complete.
- Emerald to Bethel - Storm drain work ongoing. Veolia placing services.
- Franklin Intersection - Irrigation complete. PHB signal work started.
- Alpine to Morris Hill - Excavation starting.
- Albion to Franklin - Sidewalk ongoing. Paving complete.
- Emerald to Bethel - Storm drain work ongoing. Veolia placing services.
- Franklin Intersection - Irrigation complete. PHB signal work started.
- Alpine to Morris Hill - Excavation starting.
This project is substantially complete.
-
May 16, 2024
Share May 16, 2024 on Facebook Share May 16, 2024 on Twitter Share May 16, 2024 on Linkedin Email May 16, 2024 link- Veolia utility work - Main line being placed.
- Working between Bethel and Emerald - Services ongoing.
- Albion to Franklin - Sidewalk ongoing. Paving started May 16th.
- Emerald to Bethel - Storm drain work ongoing.
- Franklin Intersection - Irrigation complete. PHB signal work started.
- Veolia utility work - Main line being placed.
- Working between Bethel and Emerald - Services ongoing.
- Albion to Franklin - Sidewalk ongoing. Paving started May 16th.
- Emerald to Bethel - Storm drain work ongoing.
- Franklin Intersection - Irrigation complete. PHB signal work started.
This project is substantially complete.
-
May 10, 2024
Share May 10, 2024 on Facebook Share May 10, 2024 on Twitter Share May 10, 2024 on Linkedin Email May 10, 2024 link- Veolia utility work - Main line being placed. Boring completed. Working between Bethel and Emerald.
- Albion to Franklin - Sidewalk ongoing. Paving anticipated April 15th.
- Emerald to Bethel - Storm drain work ongoing.
- Franklin Intersection - Irrigation Complete. PHB signal work started.
- Veolia utility work - Main line being placed. Boring completed. Working between Bethel and Emerald.
- Albion to Franklin - Sidewalk ongoing. Paving anticipated April 15th.
- Emerald to Bethel - Storm drain work ongoing.
- Franklin Intersection - Irrigation Complete. PHB signal work started.
This project is substantially complete.
Who's Listening
-
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Supervisor, Capital Projects
Phone 208-387-6100 Email connect@achdidaho.org
Timeline
-
2019
Garden Street Sidewalks & Bikeway, Albion Street to Greenbelt has finished this stageDesign for Garden Street, Franklin Road to Bethel Street completed.
-
Fall 2021
Garden Street Sidewalks & Bikeway, Albion Street to Greenbelt has finished this stageDesign started on Garden Street Sidewalk and Bikeway, Albion to Greenbelt.
-
Fall 2022
Garden Street Sidewalks & Bikeway, Albion Street to Greenbelt has finished this stageGather public input
-
Late 2022/early 2023
Garden Street Sidewalks & Bikeway, Albion Street to Greenbelt has finished this stageFinalize design
-
2023
Garden Street Sidewalks & Bikeway, Albion Street to Greenbelt has finished this stageBegin purchasing property necessary for project.
-
Late Fall 2023 (Fiscal Year 2024)
Garden Street Sidewalks & Bikeway, Albion Street to Greenbelt is currently at this stageStart construction
-
Summer 2024
this is an upcoming stage for Garden Street Sidewalks & Bikeway, Albion Street to GreenbeltConstruction complete.
Fall 2022 Virtual Neighborhood Meeting - watch the recording
-
November 09 2022