Locust Grove, Victory to Overland Project Description

  • Widen Locust Grove Rd. to two lanes in each direction, with a center turn lane
  • Add a 10-foot wide, buffered multi-use pathway for pedestrians and bicyclists to share.
  • Install a signalized pedestrian crossing at Time Zone Dr. and relocate the existing crossing at Mastiff St. slightly to the north.
  • Add center island medians at two locations between Sagemoor Drive and Fireside Drive, as well as between Puffin Street and Peacock Street.

Locust Grove and Victory Roundabout Project Description

  • Construct a dual-lane roundabout at the Locust Grove Rd. and Victory Rd. intersection. Two lanes will approach the roundabout and two lanes will go thru the roundabout.
  • Add a 10-foot wide, buffered multi-use pathway for pedestrians and bicyclists to share.
  • Include bike ramps at entrance to roundabout.
  • Add crosswalks at each leg of intersection with two-stage pedestrian crossings.
  • Include a truck apron for larger vehicles to use if necessary.
  • Intersection will be closed for gas, water, power/utility work.

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

Locust Grove, Victory to Overland Project Description

  • Widen Locust Grove Rd. to two lanes in each direction, with a center turn lane
  • Add a 10-foot wide, buffered multi-use pathway for pedestrians and bicyclists to share.
  • Install a signalized pedestrian crossing at Time Zone Dr. and relocate the existing crossing at Mastiff St. slightly to the north.
  • Add center island medians at two locations between Sagemoor Drive and Fireside Drive, as well as between Puffin Street and Peacock Street.

Locust Grove and Victory Roundabout Project Description

  • Construct a dual-lane roundabout at the Locust Grove Rd. and Victory Rd. intersection. Two lanes will approach the roundabout and two lanes will go thru the roundabout.
  • Add a 10-foot wide, buffered multi-use pathway for pedestrians and bicyclists to share.
  • Include bike ramps at entrance to roundabout.
  • Add crosswalks at each leg of intersection with two-stage pedestrian crossings.
  • Include a truck apron for larger vehicles to use if necessary.
  • Intersection will be closed for gas, water, power/utility work.

Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

Project is substantially complete

  • April 14, 2023

    Share April 14, 2023 on Facebook Share April 14, 2023 on Twitter Share April 14, 2023 on Linkedin Email April 14, 2023 link
    • Locust Grove and Victory Intersection - Water line ongoing. Placing subgrade down Victory.
    • Locust Grove - Nine Mile Creek - complete. Installing water line on coast line, will work in North. Subgrading and placing base behind water installation.
  • April 7, 2023

    Share April 7, 2023 on Facebook Share April 7, 2023 on Twitter Share April 7, 2023 on Linkedin Email April 7, 2023 link
    • Locust Grove and Victory intersection - concrete footings placed March 8th. Water line work - ongoing. Idaho Power relocating lines - anticipated complete by April 1st. Box culvert placed March 16th - Wingwalls placed. Backfilling culvert. Placing of the subgrade on the 27th.
    • Locust Grove - Nine Mile Creek - complete.
    • Excavating heading north from Doberman - ongoing. Placing base west side of road.
    • Excavating west side of Locust Grove between Mastiff and Overland - ongoing. Installing waterline on Coastline.
  • March 31, 2023

    Share March 31, 2023 on Facebook Share March 31, 2023 on Twitter Share March 31, 2023 on Linkedin Email March 31, 2023 link
    • Locust Grove and Victory intersection - concrete footings placed March 8th. Water line is ongoing. Idaho Power relocating lines - anticipated complete by April 1st. Box culvert placed March 16th. Wingwalls placed, backfilling culvert week of the 27th.
    • Locust Grove - Nine Mile Creek - Backfill complete. Excavation heading north from Doberman - ongoing. Placing base on west side of the road. Excavating west side of Locust Grove between Mastiff and Overland - ongoing.
  • March 24, 2023

    Share March 24, 2023 on Facebook Share March 24, 2023 on Twitter Share March 24, 2023 on Linkedin Email March 24, 2023 link
    • Locust Grove and Victory Intersection - Concrete footings placed March 8th.
    • Water line - ongoing.
    • Intermountain Gas - ongoing.
    • Idaho power relocating lines - anticipated completion by April 1st.
    • Box culvert placed March 16th.
    • Locust Grove and Nine Mile Creek - Backfill ongoing.
    • Excavation heading north from Doberman - ongoing.
    • Placing base on west side of road.
    • Excavating west side of Locust Grove between Mastiff and Overland - ongoing.

    Interested in viewing the project from above? Click here to view the drone footage of the project.

  • March 17, 2023

    Share March 17, 2023 on Facebook Share March 17, 2023 on Twitter Share March 17, 2023 on Linkedin Email March 17, 2023 link
    • Locust Grove and Victory intersection - concrete footings placed on March 8th. Water line ongoing. Intermountain Gas ongoing. Idaho Power relocating lines - anticipated complete by April 1st. Placing culvert starting March 16th.
    • Locust Grove - Nine Mile Creek - placing rebar for headwalls. Concrete planned for the 9th. Excavation heading north from Doberman - ongoing. Placing base on west side of the road. Excavating west side of Locust Grove between Mastiff and Overland - ongoing.
  • March 10, 2023

    Share March 10, 2023 on Facebook Share March 10, 2023 on Twitter Share March 10, 2023 on Linkedin Email March 10, 2023 link
    • Locust Grove and Victory Intersection - concrete footage placed on March 8th.
    • Water line ongoing.
    • Intermountain Gas ongoing.
    • Idaho Power relocating lines - anticipated complete by April 1st.
    • Placing culvert starting March 16th.
    • Locust Grove - 9 Mile Creek - Placing rebar for headwalls. Concrete planned for March 9th.
    • Excavation heading north on Doberman - ongoing.
    • Placing base on west side of road.
    • Excavating west side of Locust Grove between Mastiff and Overland.
  • March 3, 2023

    Share March 3, 2023 on Facebook Share March 3, 2023 on Twitter Share March 3, 2023 on Linkedin Email March 3, 2023 link
    • Excavating for structure at Ten Mile Creek.
    • Setting forms for footing.
    • Water line ongoing.
    • Intermountain gas ongoing.
    • Idaho Power relocating lines.
    • Locust Grove - Nine Mile Creek - Placing rebar for headwalls.
    • Excavation heading north from Doberman - ongoing.
    • Placing base on west side of the road.
    • Excavating west side of Locust Grove between Mastiff and Overland.

    Interested in reviewing the progress of the project? Review the latest drone footage.

  • February 24, 2023

    Share February 24, 2023 on Facebook Share February 24, 2023 on Twitter Share February 24, 2023 on Linkedin Email February 24, 2023 link
    • Locust Gove and Victory Intersection - excavating for structure at Ten Mile Creek.
    • Setting forms for footing. Water line ongoing. Intermountain Gas ongoing. Idaho Power relocating lines.
    • Locust Grove - Ten Mile Creek - Placing rebar for headwalls.
    • Excavation heading north from Doberman - ongoing. Placing base on west side of road.
    • Placing temporary asphalt north of Mastiff Street.
  • February 17, 2023

    Share February 17, 2023 on Facebook Share February 17, 2023 on Twitter Share February 17, 2023 on Linkedin Email February 17, 2023 link
    • Locust Grove and Victory Intersection - Excavating for structure at Ten Mile Creek.
    • Water line ongoing.
    • Intermountain gas ongoing.
    • Idaho Power relocating lines.
    • Locust Grove - Bridge out at Charlaois starting February 16-18.
    • Local traffic only on Locust Grove.
    • Nine Mile Creek headwalls excavated.
    • Installing Nine Mile culvert during closure.
    • Excavation heading north from Doberman ongoing.
  • February 10, 2023

    Share February 10, 2023 on Facebook Share February 10, 2023 on Twitter Share February 10, 2023 on Linkedin Email February 10, 2023 link
    • Locust Grove intersection - Excavating for structure at Ten Mile Creek.
    • Water line ongoing.
    • Intermountain Gas ongoing. Idaho Power relocating lines.
    • Locust Grove - Closed from Charolais to Victory started January 16th.
    • Nine Mile Creek headwalls excavated.
    • Form footings for headwalls.
    • Footing placed February 7th.
    • Excavation heading north from Doberman ongoing.