The Ada County Highway District (ACHD) will begin repair work in mid-July on the east leg of the Rose Hill and Owyhee roundabout to address a drainage issue. Construction is expected to last approximately one month.*

Why the fix?

Water has been pooling in this area due to outdated design standards, construction survey errors, and a lack of proper drainage when the roundabout was originally built.

What's the solution?

ACHD will install a seepage bed to improve stormwater drainage and prevent future pooling.

Construction Impacts

  • The east leg of the intersection will be closed for the duration of the work
  • Pedestrian detours and sidewalk closures
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts

*Construction schedules may change.

The Ada County Highway District (ACHD) will begin repair work in mid-July on the east leg of the Rose Hill and Owyhee roundabout to address a drainage issue. Construction is expected to last approximately one month.*

Why the fix?

Water has been pooling in this area due to outdated design standards, construction survey errors, and a lack of proper drainage when the roundabout was originally built.

What's the solution?

ACHD will install a seepage bed to improve stormwater drainage and prevent future pooling.

Construction Impacts

  • The east leg of the intersection will be closed for the duration of the work
  • Pedestrian detours and sidewalk closures
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts

*Construction schedules may change.

  • June 13, 2025

    13 Jun 2025
    Share June 13, 2025 on Facebook Share June 13, 2025 on Twitter Share June 13, 2025 on Linkedin Email June 13, 2025 link

    ACHD will begin repair work in mid-July on the east leg of the Rose Hill and Owyhee roundabout to address a drainage issue. Construction is expected to last approximately one month.

  • November 15, 2024

    15 Nov 2024
    Share November 15, 2024 on Facebook Share November 15, 2024 on Twitter Share November 15, 2024 on Linkedin Email November 15, 2024 link
    • Rose Hill and Owyhee intersection is closed for the duration of the project.
    • Pedestrian detour in place for school traffic. Bike lanes are closed as well.
    • Concrete placements complete.
    • Block wall installation complete on three of the four corners.
    • Additional bikeway signage and devices are to be added next week.
    • Asphalt paving is on-going.
  • November 7, 2024

    07 Nov 2024
    Share November 7, 2024 on Facebook Share November 7, 2024 on Twitter Share November 7, 2024 on Linkedin Email November 7, 2024 link
    • Rose Hill and Owyhee intersection is closed for the duration of the project.
    • Pedestrian detour in place for school traffic. Bike lanes are closed as well.
    • Various concrete placements on going.
    • Block wall installation nearly complete on three of the four corners.
    • Additional bikeway signage and devices are to be added next week.
  • November 1, 2024

    01 Nov 2024
    Share November 1, 2024 on Facebook Share November 1, 2024 on Twitter Share November 1, 2024 on Linkedin Email November 1, 2024 link
    • Rose Hill and Owyhee intersection is closed for the duration of the project.
    • Pedestrian detour in place for school traffic. Bike lanes are closed as well.
    • Base material import and grading is complete.
    • Irrigation work complete.
    • Light pole bases and electrical boxes are set.
    • Curb and gutter being placed.
    • Concrete island and various sidewalk/ped ramps have been placed.
  • October 24, 2024

    24 Oct 2024
    Share October 24, 2024 on Facebook Share October 24, 2024 on Twitter Share October 24, 2024 on Linkedin Email October 24, 2024 link
    • Rose Hill and Owyhee intersection is closed for the duration of the project.
    • Pedestrian detour in place for school traffic. Bike lanes are closed as well.
    • Base material import and grading is nearly complete.
    • Irrigation work complete.
    • Light pole bases and electrical boxes are being set.
    • Curb and gutter being placed.
  • October 17, 2024

    17 Oct 2024
    Share October 17, 2024 on Facebook Share October 17, 2024 on Twitter Share October 17, 2024 on Linkedin Email October 17, 2024 link
    • Rose Hill and Owyhee intersection is closed for the duration of the project.
    • Pedestrian detour in place for school traffic. Bike lanes are closed as well.
    • Base material import and grading is nearly complete.
    • Irrigation work complete.
    • Light pole bases and electrical boxes are being set.
    • Curb and gutter being placed.

    Due to unforeseen delays in chip seal operations impacting the project the new target end date for construction completion is late November.

  • October 10, 2024

    10 Oct 2024
    Share October 10, 2024 on Facebook Share October 10, 2024 on Twitter Share October 10, 2024 on Linkedin Email October 10, 2024 link
    • Rose Hill and Owyhee intersection is closed for the duration of the project.
    • Pedestrian detour in place for school traffic.
    • Bike Lanes are closed as well.
    • Base material import and grading is nearly complete.
    • Irrigation work complete.
    • Light pole bases and electrical boxes are being set.
  • October 4, 2024

    04 Oct 2024
    Share October 4, 2024 on Facebook Share October 4, 2024 on Twitter Share October 4, 2024 on Linkedin Email October 4, 2024 link
    • Rose Hill and Owyhee intersection is closed for the duration of the project.
    • Pedestrian detour in place for school traffic. Bike Lanes are closed as well.
    • Thermoplastic and painted pavement markings complete east and west of the roundabout.
    • Contractor is working on grading the road.
    • Irrigation work ongoing.
  • September 26, 2024

    26 Sep 2024
    Share September 26, 2024 on Facebook Share September 26, 2024 on Twitter Share September 26, 2024 on Linkedin Email September 26, 2024 link
    • Rose Hill and Owyhee intersection is closed for the duration of the project.
    • Pedestrian detour in place for school traffic.
    • Thermoplastic and painted pavement markings complete east and west of the roundabout. Minor adjustments to be made.
    • Contractor started importing fill.
    • Irrigation work ongoing.
  • September 20, 2024

    20 Sep 2024
    Share September 20, 2024 on Facebook Share September 20, 2024 on Twitter Share September 20, 2024 on Linkedin Email September 20, 2024 link
    • Rose Hill and Owyhee intersection is closed for the duration of the project.
    • Pedestrian detour in place for school traffic.
    • Thermoplastic and painted pavement markings complete east and west of the roundabout. Minor adjustments to be made.
    • Contractor started demo and excavation.
    • Tree removal complete.
    • Survey set for irrigation and concrete placements.
    • Irrigation work starting this week.