State Street and Pierce Park Lane Intersection

Share State Street and Pierce Park Lane Intersection on Facebook Share State Street and Pierce Park Lane Intersection on Twitter Share State Street and Pierce Park Lane Intersection on Linkedin Email State Street and Pierce Park Lane Intersection link

The Ada County Highway District (ACHD) is designing future improvements for the State Street and Pierce Park Lane Intersection. This project aims to improve safety and connectivity for all users, accommodate future traffic volumes, and incorporate ideas and concerns gathered from the public.

The improvements for State Street and Pierce Park Lane include:

  • Realigning Pierce Park Lane to improve safety and provide better line of sight for drivers
  • Widening State Street within the project limits and add medians where necessary for safety
  • Providing U-turns at multiple locations
  • Adding continuous multi-use pathways for pedestrians and cyclists
  • Adding additional crosswalk on State Street

The Ada County Highway District (ACHD) is designing future improvements for the State Street and Pierce Park Lane Intersection. This project aims to improve safety and connectivity for all users, accommodate future traffic volumes, and incorporate ideas and concerns gathered from the public.

The improvements for State Street and Pierce Park Lane include:

  • Realigning Pierce Park Lane to improve safety and provide better line of sight for drivers
  • Widening State Street within the project limits and add medians where necessary for safety
  • Providing U-turns at multiple locations
  • Adding continuous multi-use pathways for pedestrians and cyclists
  • Adding additional crosswalk on State Street
  • July 2, 2025

    Share July 2, 2025 on Facebook Share July 2, 2025 on Twitter Share July 2, 2025 on Linkedin Email July 2, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone.
    • Contractor is excavating the north side of State Street. Some work is delayed pending utility work. Underground electrical work is on-going.
  • Construction Update: Hertford Way

    Share Construction Update: Hertford Way on Facebook Share Construction Update: Hertford Way on Twitter Share Construction Update: Hertford Way on Linkedin Email Construction Update: Hertford Way link

    As part of the State Street and Pierce Park project, Veolia will be performing utility work in front of Hertford Way next week.

    To maintain local access for residents, and keep Hertford Way open to vehicles, a temporary traffic route will be in place. Northbound drivers will be directed to travel on the LEFT side of the island along Hertford Way at the intersection with State Street. Delineators will be set up to safely guide both northbound and southbound traffic through the area.

    Please follow posted detour signs and use extra caution near the work zone.

    Work is scheduled to begin early next week and is expected to be completed by end of day Thursday, July 3. All work is weather dependent.

  • June 26, 2025

    Share June 26, 2025 on Facebook Share June 26, 2025 on Twitter Share June 26, 2025 on Linkedin Email June 26, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone.
    • Contractor is excavating the north side of State Street. Some work is delayed pending utility work.
    • Underground electrical work is on-going.
  • June 20, 2025

    Share June 20, 2025 on Facebook Share June 20, 2025 on Twitter Share June 20, 2025 on Linkedin Email June 20, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street
    • Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone.
    • Contractor is excavating the north side of State Street. Some work is delayed pending utility work.
    • Underground electrical work is on-going.
  • June 13, 2025

    Share June 13, 2025 on Facebook Share June 13, 2025 on Twitter Share June 13, 2025 on Linkedin Email June 13, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Traffic has been shifted to the south so the contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone.
    • Contractor is excavating the north side of State Street. Some work is delayed pending utility work.
    • Underground electrical work is on-going.
  • June 6, 2025

    Share June 6, 2025 on Facebook Share June 6, 2025 on Twitter Share June 6, 2025 on Linkedin Email June 6, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone.
    • Contractor is excavating the north side of State Street. Some work is delayed pending utility work.
    • Underground electrical work is on-going.
  • May 30, 2025

    Share May 30, 2025 on Facebook Share May 30, 2025 on Twitter Share May 30, 2025 on Linkedin Email May 30, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Traffic has been shifted to the south so the contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone.
    • Contractor is excavating the north side of State Street.
    • Underground electrical work is on-going.
  • May 23, 2025

    Share May 23, 2025 on Facebook Share May 23, 2025 on Twitter Share May 23, 2025 on Linkedin Email May 23, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Traffic has been shifted to the south so the contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone.
    • Contractor is excavating the north side of State Street.
    • Underground electrical work is on-going.
  • May 16, 2025

    Share May 16, 2025 on Facebook Share May 16, 2025 on Twitter Share May 16, 2025 on Linkedin Email May 16, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Traffic has been shifted to the south so the contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone.
    • Contractor is excavating the north side of State Street.
    • Underground electrical work is on-going.
  • May 8, 2025

    Share May 8, 2025 on Facebook Share May 8, 2025 on Twitter Share May 8, 2025 on Linkedin Email May 8, 2025 link
    • Utility relocation work is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Traffic has been shifted to the south so the contractor can construct the north side of State Street.
    • Left turns have been eliminated through the work zone.
    • Carlsbad Way will be closed from April 29th through May 6th for utility work and roadway work.
    • Contractor is excavating the north side of State Street.
    • Underground electrical work is on-going.
Page last updated: 02 Jul 2025, 12:01 PM