Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Facebook Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Twitter Share Downtown Eagle Mobility Improvements: Eagle Road and State Street on Linkedin Email Downtown Eagle Mobility Improvements: Eagle Road and State Street link

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

*Phase 1 of the project is expected to be complete by Fall 2024

The Eagle Road and State Street intersection is the gateway to the City of Eagle and an important part of the downtown core. As a gateway, it serves vehicles, bicyclists and pedestrians of all ages who want to access local businesses, neighborhoods, the elementary school, and the senior center.

The Ada County Highway District (ACHD), working with the City of Eagle, is currently designing improvements to Eagle Road and State Street and the connecting roadway network which includes Olde Park Place, Plaza Drive and Aikens Street.

Goals

The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

*Phase 1 of the project is expected to be complete by Fall 2024

  • March 29, 2024

    Share March 29, 2024 on Facebook Share March 29, 2024 on Twitter Share March 29, 2024 on Linkedin Email March 29, 2024 link
    • Phase 1 - Northeast corner of Eagle and Plaza
      • Removal of obstructions and tree removal ongoing.
      • Utilities relocating.
      • Signal work ongoing.
      • Landscaping wall ongoing.
    • Veolia
      • Locating utilities.
      • Boring complete.
      • Crossing Eagle complete.
      • Stopped at Intersection of Plaza and Eagle.
    • Plaza and Eagle Road Closure - Closed from April 1st – 15th.
      • Veolia tie in water in middle of intersection then proceeding down Plaza.
      • Signal work crossing Eagle Road.
      • Irrigation and conduits crossing Eagle during closure.
    • Eagle Road Closure - April 15th – April 30th.
      • Veolia water line to Aikens.
  • March 27, 2024 - Eagle Road Closure Information and Map

    Share March 27, 2024 - Eagle Road Closure Information and Map on Facebook Share March 27, 2024 - Eagle Road Closure Information and Map on Twitter Share March 27, 2024 - Eagle Road Closure Information and Map on Linkedin Email March 27, 2024 - Eagle Road Closure Information and Map link

    Closure on Eagle Road Beginning Next Week

    EAGLE — Commuters should be prepared for a closure starting next week for ACHD’s Downtown Eagle Mobility Project.

    Beginning Monday, Eagle Road will be closed between Aikens Road and the intersection of Plaza Drive. For the first two weeks, this will include a partial closure of the intersection of Eagle and Plaza.

    The partial intersection closure will provide a safer working environment for crewmembers. While the intersection is partially closed, crews will be in 24-hour operations in order to complete the necessary work as quickly as possible.

    During the partial intersection closure, commuters heading northbound will be able to turn right onto Plaza Drive to get around the closure. Traffic will not be able to turn left onto Plaza. There will also be no access onto Eagle Road from either side of Plaza Drive.

    The entrance to Zamzows and Walgreens will be accessible on Eagle Road. The median has been removed to allow left turns for business access. (see detour map)

    Commuters heading southbound should use State Street (“Old State”) to either Ballantyne Lane or Edgewood Drive to Highway 44.

    The intersection at Plaza and Eagle is expected to reopen in about two weeks, weather dependent. The closure on Eagle Road between Aikens and Plaza is expected to last for one month. An updated map will be shared when the intersection is back open.

    Phase one of ACHD’s Downtown Eagle Mobility Improvements is expected to be complete this fall, with phase two starting after phase one is completed. The goal of the street network improvements is to improve safety and mobility for all users while accommodating future traffic growth and creating a welcoming downtown environment.

    Underground utility work is also being done in tandem with ACHD’s project in an effort to minimize the impact to businesses and residents.

    During the roadwork, access will be maintained to all businesses in downtown Eagle, and businesses are ready and eager to support their customers.


  • March 21, 2024

    Share March 21, 2024 on Facebook Share March 21, 2024 on Twitter Share March 21, 2024 on Linkedin Email March 21, 2024 link
    • Northeast corner of Eagle and Plaza - Removal of obstructions and tree removal ongoing. Utilities relocating. Signal work ongoing. Landscaping wall ongoing.
    • Veolia - Locating utilities. Boring complete. Crossing Eagle with new water line at night. Once tie in is complete will work north to Plaza.
  • March 15, 2024

    Share March 15, 2024 on Facebook Share March 15, 2024 on Twitter Share March 15, 2024 on Linkedin Email March 15, 2024 link
    • Phase 1 - Northeast corner of Eagle and Plaza - Removal of obstructions and tree removal ongoing.
    • Utilities relocating - Signal work ongoing.
    • Veolia - Locating utilities. Boring Complete. Crossing Eagle waiting TC permit approval. Possibly night work. Once tie in is complete will work north of Plaza.
  • March 8, 2024

    Share March 8, 2024 on Facebook Share March 8, 2024 on Twitter Share March 8, 2024 on Linkedin Email March 8, 2024 link
    • Phase 1 - Northeast corner of Eagle and Plaza
    • Removal of obstructions and tree removal ongoing.
    • Utilities relocating.
    • Signal work at Plaza started March 3rd.
    • Placing bases for new signal poles.
    • Veolia Permit approved February 26th.
    • Locating utilities.
    • Removing extruded curb between Eagle and Highway 44.
    • Potholing and boring started the week of March 4th.
  • March 1, 2024

    Share March 1, 2024 on Facebook Share March 1, 2024 on Twitter Share March 1, 2024 on Linkedin Email March 1, 2024 link

    Phase 1 - Northeast corner of Eagle and Plaza

    • A work zone is in place in the middle of Eagle Road, south of Plaza Drive for Veolia water work.
    • One lane in each direction will remain open (A lane on each side of the work zone).
    • Work will continue on the East side of Eagle Road just North of Plaza Drive.
    • Extruded curb is being removed on Eagle Rd. between Plaza Dr. and Highway 44.
    • Contractor is removing obstructions.
    • Utilities are being relocated.
    • Veolia Permit approved February 26th.
    • Signal work starting March 4th.
    • Flagging is needed at Eagle and Plaza starting Monday, March 4th for utility and signal work.
    • Business access will be maintained.

  • February 27, 2024

    Share February 27, 2024 on Facebook Share February 27, 2024 on Twitter Share February 27, 2024 on Linkedin Email February 27, 2024 link

    As construction continues on Eagle Road, please review the updated traffic pattern and information below:

    • A work zone has been added in the middle of Eagle Road, south of Plaza Drive for Veolia water work.
    • One lane in each direction will remain open (A lane on each side of the work zone).
    • Business access will be maintained.
    • Work will continue on the East side of Eagle Road just North of Plaza Drive.


  • February 23, 2024

    Share February 23, 2024 on Facebook Share February 23, 2024 on Twitter Share February 23, 2024 on Linkedin Email February 23, 2024 link
    • Northeast corner of Eagle and Plaza - Removing obstructions.
    • Utilities relocating.
    • Tree removal ongoing.
    • Signal work starting.
    • Veolia waiting for ITD permit prior to starting.
  • February 16, 2024

    Share February 16, 2024 on Facebook Share February 16, 2024 on Twitter Share February 16, 2024 on Linkedin Email February 16, 2024 link
    • Northeast corner of Eagle and Plaza - Removing obstructions.
    • Utilities relocating.
    • Tree removal ongoing.
  • February 14, 2024

    Share February 14, 2024 on Facebook Share February 14, 2024 on Twitter Share February 14, 2024 on Linkedin Email February 14, 2024 link