Linder Road, State Highway 44 to Floating Feather
The Ada County Highway District (ACHD) will be constructing improvements to Linder Road from State Highway 44 to Floating Feather Road starting as early as mid-November. Work is expected to be complete late 2026.*
Project Description
Roadway
- Widening Linder Road to two lanes in each direction, with a center turn lane.
- Adding landscaped medians where appropriate.
- Constructing curb, gutter and a multi-use pathway on both sides of the roadway for pedestrians and bicyclists.
- Retaining the existing signalized pedestrian crossing at Saguaro Dr.
- Installing roadway lighting along Linder Road
- Constructing bioretention swales to manage roadway drainage.
- Reconstructing two separate bridges on Linder.
Linder and Floating Feather Intersection
- Constructing a roundabout at the Linder and Floating Feather intersection.
- The west and south legs will feature two lanes approaching the roundabout, the left lane for thru traffic and left turns, the right lane for right turns only.
- Adding curb, gutter and a detached multi-use pathway with bike ramps.
- Adding crosswalks at each leg of the intersection with two-stage pedestrian crossings and Rectangular Rapid Flashing Beacons (RRFBs).
- A truck apron for larger vehicles to use if necessary.
- Constructing a stormwater basin to manage water drainage from the intersection.
*****Linder Road to open May 2026
*****The intersection of Linder and Floating Feather to close June 2026 for the construction of the Roundabout.
The Ada County Highway District (ACHD) will be constructing improvements to Linder Road from State Highway 44 to Floating Feather Road starting as early as mid-November. Work is expected to be complete late 2026.*
Project Description
Roadway
- Widening Linder Road to two lanes in each direction, with a center turn lane.
- Adding landscaped medians where appropriate.
- Constructing curb, gutter and a multi-use pathway on both sides of the roadway for pedestrians and bicyclists.
- Retaining the existing signalized pedestrian crossing at Saguaro Dr.
- Installing roadway lighting along Linder Road
- Constructing bioretention swales to manage roadway drainage.
- Reconstructing two separate bridges on Linder.
Linder and Floating Feather Intersection
- Constructing a roundabout at the Linder and Floating Feather intersection.
- The west and south legs will feature two lanes approaching the roundabout, the left lane for thru traffic and left turns, the right lane for right turns only.
- Adding curb, gutter and a detached multi-use pathway with bike ramps.
- Adding crosswalks at each leg of the intersection with two-stage pedestrian crossings and Rectangular Rapid Flashing Beacons (RRFBs).
- A truck apron for larger vehicles to use if necessary.
- Constructing a stormwater basin to manage water drainage from the intersection.
*****Linder Road to open May 2026
*****The intersection of Linder and Floating Feather to close June 2026 for the construction of the Roundabout.
-
October 2, 2026
Share October 2, 2026 on Facebook Share October 2, 2026 on X (formerly Twitter) Share October 2, 2026 on Linkedin Email October 2, 2026 linkEast side of Linder Rd to Saguaro
- Sidewalk still remaining.
West side of Linder Rd to Saguaro
- Curb complete from State Street to Saguaro Dr.
- Sidewalk installation ongoing.
- Bottom lift of paving complete.
- Block wall being reset.
Saguaro Dr to Floating Feather
- Pole bases placed and school flashers installed.
- Road base installation ongoing.
- Curb being placed.
Dry Creek Bridge - Complete. Rail installation ongoing.
Floating Feather and Linder Roundabout
- Underground power conduit installation ongoing.
- Finishing the subgrade.
- Curb being placed on roundabout.
- Concrete intersection installation anticipated starting Oct 15th.
East side of Linder Rd to Saguaro
- Sidewalk still remaining.
West side of Linder Rd to Saguaro
- Curb complete from State Street to Saguaro Dr.
- Sidewalk installation ongoing.
- Bottom lift of paving complete.
- Block wall being reset.
Saguaro Dr to Floating Feather
- Pole bases placed and school flashers installed.
- Road base installation ongoing.
- Curb being placed.
Dry Creek Bridge - Complete. Rail installation ongoing.
Floating Feather and Linder Roundabout
- Underground power conduit installation ongoing.
- Finishing the subgrade.
- Curb being placed on roundabout.
- Concrete intersection installation anticipated starting Oct 15th.
-
September 24, 2026
Share September 24, 2026 on Facebook Share September 24, 2026 on X (formerly Twitter) Share September 24, 2026 on Linkedin Email September 24, 2026 linkEast side of Linder Rd to Saguaro
- Sidewalk installation remaining.
West side of Linder Rd to Saguaro
- Curb installation complete from State Street to Saguaro Dr.
- Sidewalk installation ongoing.
- Bottom lift of paving complete.
- Block wall being reset.
Saguaro Dr to Floating Feather
- Pole bases are placed and school flashers are installed.
- Road base installation ongoing.
- Curb being placed.
Dry Creek Bridge - Complete. Rail installation ongoing.
Floating Feather and Linder Roundabout
- Storm drain has been installed.
- Underground power conduit installation is ongoing.
- Finishing subgrade.
- Curb being placed at the roundabout.
East side of Linder Rd to Saguaro
- Sidewalk installation remaining.
West side of Linder Rd to Saguaro
- Curb installation complete from State Street to Saguaro Dr.
- Sidewalk installation ongoing.
- Bottom lift of paving complete.
- Block wall being reset.
Saguaro Dr to Floating Feather
- Pole bases are placed and school flashers are installed.
- Road base installation ongoing.
- Curb being placed.
Dry Creek Bridge - Complete. Rail installation ongoing.
Floating Feather and Linder Roundabout
- Storm drain has been installed.
- Underground power conduit installation is ongoing.
- Finishing subgrade.
- Curb being placed at the roundabout.
-
September 17, 2026
Share September 17, 2026 on Facebook Share September 17, 2026 on X (formerly Twitter) Share September 17, 2026 on Linkedin Email September 17, 2026 linkEast side of Linder Rd to Saguaro
- Sidewalk installation remaining.
- Block wall installation ongoing.
West side of Linder Rd to Saguaro
- Curb complete from State Street to Saguaro Dr.
- Sidewalk installation is ongoing.
- Bottom lift of paving is complete.
- Block wall is being reset.
Saguaro Dr to Floating Feather
- Pole bases placed and school flashers are installed.
- Road base installation ongoing.
Dry Creek Bridge - Complete. Rail installation ongoing.
Floating Feather and Linder Roundabout
- Storm drain is installed.
- Underground power conduit installation ongoing.
- Sewer line installation for the adjacent development is complete.
- Finishing subgrade.
- Forming and placing sidewalk.
East side of Linder Rd to Saguaro
- Sidewalk installation remaining.
- Block wall installation ongoing.
West side of Linder Rd to Saguaro
- Curb complete from State Street to Saguaro Dr.
- Sidewalk installation is ongoing.
- Bottom lift of paving is complete.
- Block wall is being reset.
Saguaro Dr to Floating Feather
- Pole bases placed and school flashers are installed.
- Road base installation ongoing.
Dry Creek Bridge - Complete. Rail installation ongoing.
Floating Feather and Linder Roundabout
- Storm drain is installed.
- Underground power conduit installation ongoing.
- Sewer line installation for the adjacent development is complete.
- Finishing subgrade.
- Forming and placing sidewalk.
-
September 11, 2026
Share September 11, 2026 on Facebook Share September 11, 2026 on X (formerly Twitter) Share September 11, 2026 on Linkedin Email September 11, 2026 linkEast side of Linder Rd
- Sidewalk remaining.
- Block wall installation ongoing.
- SH-44 block wall ongoing.
West side of Linder Rd
- Curb being placed from State Street to Saguaro Dr. - complete.
- Sidewalk installation ongoing.
- Bottom lift complete.
Saquaro Dr to Floating Feather
- Pole bases placed.
- Road base ongoing.
- School flashers installed.
Dry Creek Bridge - Complete. Rail installation ongoing.
Floating Feather and Linder Roundabout
- Utilities relocating facilities.
- Road sub-graded.
- Storm drain installed.
- Underground power conduit installation ongoing.
- Development will install Sewer line starting August 7th - Ongoing.
- Forming and placing sidewalk once sewer is complete.
East side of Linder Rd
- Sidewalk remaining.
- Block wall installation ongoing.
- SH-44 block wall ongoing.
West side of Linder Rd
- Curb being placed from State Street to Saguaro Dr. - complete.
- Sidewalk installation ongoing.
- Bottom lift complete.
Saquaro Dr to Floating Feather
- Pole bases placed.
- Road base ongoing.
- School flashers installed.
Dry Creek Bridge - Complete. Rail installation ongoing.
Floating Feather and Linder Roundabout
- Utilities relocating facilities.
- Road sub-graded.
- Storm drain installed.
- Underground power conduit installation ongoing.
- Development will install Sewer line starting August 7th - Ongoing.
- Forming and placing sidewalk once sewer is complete.
-
September 3, 2026
Share September 3, 2026 on Facebook Share September 3, 2026 on X (formerly Twitter) Share September 3, 2026 on Linkedin Email September 3, 2026 linkEast side of Linder Rd
- Sidewalk remaining.
- Block wall ongoing.
- SH-44 block wall ongoing.
West side of Linder Rd
- Curb being placed from State Street to Saguaro Dr. - complete.
- Sidewalk ongoing.
- Bottom lift complete.
Saquaro Dr to Floating Feather
- Pole bases being placed.
- Road base ongoing.
- School Flashers installed.
Foothills Bridge - Rail installed.
Dry Creek Bridge - Complete. Rail ongoing.
Floating Feather and Linder Roundabout
- Utilities relocating facilities.
- Road sub-graded.
- Storm drain installed.
- Underground power conduit ongoing.
- Development will install sewer line starting August 7th - Ongoing.
- Forming and placing sidewalk once sewer is complete.
East side of Linder Rd
- Sidewalk remaining.
- Block wall ongoing.
- SH-44 block wall ongoing.
West side of Linder Rd
- Curb being placed from State Street to Saguaro Dr. - complete.
- Sidewalk ongoing.
- Bottom lift complete.
Saquaro Dr to Floating Feather
- Pole bases being placed.
- Road base ongoing.
- School Flashers installed.
Foothills Bridge - Rail installed.
Dry Creek Bridge - Complete. Rail ongoing.
Floating Feather and Linder Roundabout
- Utilities relocating facilities.
- Road sub-graded.
- Storm drain installed.
- Underground power conduit ongoing.
- Development will install sewer line starting August 7th - Ongoing.
- Forming and placing sidewalk once sewer is complete.
-
August 28, 2026
Share August 28, 2026 on Facebook Share August 28, 2026 on X (formerly Twitter) Share August 28, 2026 on Linkedin Email August 28, 2026 link- East side of Linder Rd
- Sidewalk remaining
- Block wall ongoing
- West side of Linder Rd
- Pole bases and conduits being placed
- Curb being placed from State Street to Saguaro Dr.
- complete
- Sidewalk ongoing
- Bottom lift complete
- Saquaro Dr to Floating Feather
- Pole Bases being placed
- Road based ongoing
- Foothills Bridge
- Rail installed
- Dry Creek Bridge
- Complete
- Floating Feather and Linder Roundabout
- Utilities relocating facilities.
- Road sub-graded
- Storm drain installed
- Underground power conduit ongoing
- Development will install Sewer line starting August 7th
- Ongoing
- Forming and placing sidewalk once sewer is complete
- East side of Linder Rd
- Sidewalk remaining
- Block wall ongoing
- West side of Linder Rd
- Pole bases and conduits being placed
- Curb being placed from State Street to Saguaro Dr.
- complete
- Sidewalk ongoing
- Bottom lift complete
- Saquaro Dr to Floating Feather
- Pole Bases being placed
- Road based ongoing
- Foothills Bridge
- Rail installed
- Dry Creek Bridge
- Complete
- Floating Feather and Linder Roundabout
- Utilities relocating facilities.
- Road sub-graded
- Storm drain installed
- Underground power conduit ongoing
- Development will install Sewer line starting August 7th
- Ongoing
- Forming and placing sidewalk once sewer is complete
- East side of Linder Rd
-
August 20, 2026
Share August 20, 2026 on Facebook Share August 20, 2026 on X (formerly Twitter) Share August 20, 2026 on Linkedin Email August 20, 2026 linkEast side of Linder Rd - Sidewalk installation remaining. Block wall installation ongoing.
West side of Linder Rd - Pole bases and conduits are being placed. The curb being placed from State Street to Saguaro Dr. is complete. Sidewalk installation is ongoing. Bottom lift is complete.
Saquaro Dr to Floating Feather - Pole bases are being placed. Road base installation is ongoing.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Utilities relocating facilities. Road is sub-graded. Storm drain is installed. Underground power conduit installation is ongoing. Development will install sewer line starting August 7th - Ongoing. Forming and placing sidewalk once sewer is complete.
East side of Linder Rd - Sidewalk installation remaining. Block wall installation ongoing.
West side of Linder Rd - Pole bases and conduits are being placed. The curb being placed from State Street to Saguaro Dr. is complete. Sidewalk installation is ongoing. Bottom lift is complete.
Saquaro Dr to Floating Feather - Pole bases are being placed. Road base installation is ongoing.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Utilities relocating facilities. Road is sub-graded. Storm drain is installed. Underground power conduit installation is ongoing. Development will install sewer line starting August 7th - Ongoing. Forming and placing sidewalk once sewer is complete.
-
August 14, 2026
Share August 14, 2026 on Facebook Share August 14, 2026 on X (formerly Twitter) Share August 14, 2026 on Linkedin Email August 14, 2026 linkEast side of Linder Rd
- Sidewalk remaining.
- Block wall ongoing.
West side of Linder Rd
- Pole bases and conduits being placed.
- Curb being placed from State Street to Saguaro Dr. - Complete.
- Sidewalk ongoing.
- Bottom lift paving anticipated week of August 10th.
Saquaro Dr to Floating Feather
- Pole Bases being placed.
- Road based ongoing.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout
- Utilities relocating facilities.
- Road sub-graded.
- Storm drain being installed.
- Underground power conduit ongoing.
- Development will install sewer line starting August 7th.
- Forming and placing sidewalk once sewer is complete.
East side of Linder Rd
- Sidewalk remaining.
- Block wall ongoing.
West side of Linder Rd
- Pole bases and conduits being placed.
- Curb being placed from State Street to Saguaro Dr. - Complete.
- Sidewalk ongoing.
- Bottom lift paving anticipated week of August 10th.
Saquaro Dr to Floating Feather
- Pole Bases being placed.
- Road based ongoing.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout
- Utilities relocating facilities.
- Road sub-graded.
- Storm drain being installed.
- Underground power conduit ongoing.
- Development will install sewer line starting August 7th.
- Forming and placing sidewalk once sewer is complete.
-
August 7, 2026
Share August 7, 2026 on Facebook Share August 7, 2026 on X (formerly Twitter) Share August 7, 2026 on Linkedin Email August 7, 2026 link- East side of Linder Rd
- Sidewalk remaining
- Block wall ongoing
- West side of Linder Rd
- Pole bases and conduits being placed
- Curb being placed from State Street to Saguaro Dr.
- Sidewalk ongoing
- Bottom lift paving anticipated week of August 10th
- Foothills Bridge
- Rail remaining
- Dry Creek Bridge
- Complete
- Floating Feather and Linder Roundabout
- Utilities relocating facilities.
- Road Subgraded
- Storm drain being installed
- Underground power conduit ongoing
- Development will install Sewer line starting August 7th
- Forming and placing sidewalk once sewer is complete
- East side of Linder Rd
- Sidewalk remaining
- Block wall ongoing
- West side of Linder Rd
- Pole bases and conduits being placed
- Curb being placed from State Street to Saguaro Dr.
- Sidewalk ongoing
- Bottom lift paving anticipated week of August 10th
- Foothills Bridge
- Rail remaining
- Dry Creek Bridge
- Complete
- Floating Feather and Linder Roundabout
- Utilities relocating facilities.
- Road Subgraded
- Storm drain being installed
- Underground power conduit ongoing
- Development will install Sewer line starting August 7th
- Forming and placing sidewalk once sewer is complete
- East side of Linder Rd
-
July 30, 2026
Share July 30, 2026 on Facebook Share July 30, 2026 on X (formerly Twitter) Share July 30, 2026 on Linkedin Email July 30, 2026 linkEast side of Linder Rd
- Sidewalk remaining
- Block wall ongoing.
West side of Linder Rd
- Pole bases and conduits being placed.
- Curb being placed from State Street to Saguaro Dr. Sidewalk ongoing.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Utilities relocating facilities. Subgrading road. Storm drain being installed. Underground power conduit ongoing.
East side of Linder Rd
- Sidewalk remaining
- Block wall ongoing.
West side of Linder Rd
- Pole bases and conduits being placed.
- Curb being placed from State Street to Saguaro Dr. Sidewalk ongoing.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Utilities relocating facilities. Subgrading road. Storm drain being installed. Underground power conduit ongoing.
- Road closures are expected during construction
- Lane restrictions and shifts with flaggers to direct traffic
- Neighborhood traffic calming will be in place to discourage cut-through traffic on residential streets
- General construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts and maintain access
-
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org -
Project Manager
Phone 208-387-6100 Email projects@achdidaho.org -
Construction Coordinator
Phone 208-387-6100 Email connect@achdidaho.org





