Linder Road, State Highway 44 to Floating Feather

Share Linder Road, State Highway 44 to Floating Feather on Facebook Share Linder Road, State Highway 44 to Floating Feather on X (formerly Twitter) Share Linder Road, State Highway 44 to Floating Feather on Linkedin Email Linder Road, State Highway 44 to Floating Feather link

The Ada County Highway District (ACHD) will be constructing improvements to Linder Road from State Highway 44 to Floating Feather Road starting as early as mid-November. Work is expected to be complete late 2026.*

Project Description

Roadway

  • Widening Linder Road to two lanes in each direction, with a center turn lane.
  • Adding landscaped medians where appropriate.
  • Constructing curb, gutter and a multi-use pathway on both sides of the roadway for pedestrians and bicyclists.
  • Retaining the existing signalized pedestrian crossing at Saguaro Dr.
  • Installing roadway lighting along Linder Road
  • Constructing bioretention swales to manage roadway drainage.
  • Reconstructing two separate bridges on Linder.

Linder and Floating Feather Intersection

  • Constructing a roundabout at the Linder and Floating Feather intersection.
    • The west and south legs will feature two lanes approaching the roundabout, the left lane for thru traffic and left turns, the right lane for right turns only.
  • Adding curb, gutter and a detached multi-use pathway with bike ramps.
  • Adding crosswalks at each leg of the intersection with two-stage pedestrian crossings and Rectangular Rapid Flashing Beacons (RRFBs).
  • A truck apron for larger vehicles to use if necessary.
  • Constructing a stormwater basin to manage water drainage from the intersection.

*****Linder Road to open May 2026

*****The intersection of Linder and Floating Feather to close June 2026 for the construction of the Roundabout.

The Ada County Highway District (ACHD) will be constructing improvements to Linder Road from State Highway 44 to Floating Feather Road starting as early as mid-November. Work is expected to be complete late 2026.*

Project Description

Roadway

  • Widening Linder Road to two lanes in each direction, with a center turn lane.
  • Adding landscaped medians where appropriate.
  • Constructing curb, gutter and a multi-use pathway on both sides of the roadway for pedestrians and bicyclists.
  • Retaining the existing signalized pedestrian crossing at Saguaro Dr.
  • Installing roadway lighting along Linder Road
  • Constructing bioretention swales to manage roadway drainage.
  • Reconstructing two separate bridges on Linder.

Linder and Floating Feather Intersection

  • Constructing a roundabout at the Linder and Floating Feather intersection.
    • The west and south legs will feature two lanes approaching the roundabout, the left lane for thru traffic and left turns, the right lane for right turns only.
  • Adding curb, gutter and a detached multi-use pathway with bike ramps.
  • Adding crosswalks at each leg of the intersection with two-stage pedestrian crossings and Rectangular Rapid Flashing Beacons (RRFBs).
  • A truck apron for larger vehicles to use if necessary.
  • Constructing a stormwater basin to manage water drainage from the intersection.

*****Linder Road to open May 2026

*****The intersection of Linder and Floating Feather to close June 2026 for the construction of the Roundabout.

  • July 30, 2026

    Share July 30, 2026 on Facebook Share July 30, 2026 on X (formerly Twitter) Share July 30, 2026 on Linkedin Email July 30, 2026 link

    East side of Linder Rd

    • Sidewalk remaining
    • Block wall ongoing.

    West side of Linder Rd

    • Pole bases and conduits being placed.
    • Curb being placed from State Street to Saguaro Dr. Sidewalk ongoing.

    Foothills Bridge - Rail remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Utilities relocating facilities. Subgrading road. Storm drain being installed. Underground power conduit ongoing.


    East side of Linder Rd

    • Sidewalk remaining
    • Block wall ongoing.

    West side of Linder Rd

    • Pole bases and conduits being placed.
    • Curb being placed from State Street to Saguaro Dr. Sidewalk ongoing.

    Foothills Bridge - Rail remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Utilities relocating facilities. Subgrading road. Storm drain being installed. Underground power conduit ongoing.


  • July 23, 2026

    Share July 23, 2026 on Facebook Share July 23, 2026 on X (formerly Twitter) Share July 23, 2026 on Linkedin Email July 23, 2026 link

    East side of Linder Rd

    • Sidewalk remaining.
    • Block wall ongoing.

    West side of Linder Rd

    • Pole bases and conduits being placed.
    • Curb being placed from State Street to Saguaro Dr.
    • Sidewalk ongoing.

    Foothills Bridge - Rail remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Utilities relocating facilities. Subgrading road. Storm drain being installed. Underground power conduit ongoing.


    East side of Linder Rd

    • Sidewalk remaining.
    • Block wall ongoing.

    West side of Linder Rd

    • Pole bases and conduits being placed.
    • Curb being placed from State Street to Saguaro Dr.
    • Sidewalk ongoing.

    Foothills Bridge - Rail remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Utilities relocating facilities. Subgrading road. Storm drain being installed. Underground power conduit ongoing.


  • July 17, 2026

    Share July 17, 2026 on Facebook Share July 17, 2026 on X (formerly Twitter) Share July 17, 2026 on Linkedin Email July 17, 2026 link

    East side of Linder Rd

    • Sidewalk remaining
    • Block wall ongoing

    West side of Linder Rd

    • Excavation and concrete removal
    • Storm drain ongoing
    • Pole bases and conduits being placed

    Foothills Bridge

    • Rail remaining

    Dry Creek Bridge - Complete

    Floating Feather and Linder Roundabout

    • Utilities relocating facilities
    • Subgrading road Pavement Preservation and ADA

    East side of Linder Rd

    • Sidewalk remaining
    • Block wall ongoing

    West side of Linder Rd

    • Excavation and concrete removal
    • Storm drain ongoing
    • Pole bases and conduits being placed

    Foothills Bridge

    • Rail remaining

    Dry Creek Bridge - Complete

    Floating Feather and Linder Roundabout

    • Utilities relocating facilities
    • Subgrading road Pavement Preservation and ADA
  • July 9, 2026

    Share July 9, 2026 on Facebook Share July 9, 2026 on X (formerly Twitter) Share July 9, 2026 on Linkedin Email July 9, 2026 link

    East side of Linder Rd

    • Sidewalk remaining.
    • Block wall ongoing.

    West side of Linder Rd

    • Excavation and concrete removal.
    • Storm drain ongoing.
    • Pole bases and conduits being placed.

    Foothills Bridge - Rail remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Utilities relocating facilities. Subgrading the road.

    East side of Linder Rd

    • Sidewalk remaining.
    • Block wall ongoing.

    West side of Linder Rd

    • Excavation and concrete removal.
    • Storm drain ongoing.
    • Pole bases and conduits being placed.

    Foothills Bridge - Rail remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Utilities relocating facilities. Subgrading the road.

  • July 1, 2026

    Share July 1, 2026 on Facebook Share July 1, 2026 on X (formerly Twitter) Share July 1, 2026 on Linkedin Email July 1, 2026 link

    East side of Linder Rd

    • Sidewalk remaining.
    • Block wall ongoing.

    West side of Linder Rd

    • Excavation and concrete removal.
    • Storm drain ongoing.
    • Pole bases and conduits being placed.

    Foothills Bridge - Rail remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Veolia working on new water line. Intersection closure started May 18th. Utilities relocating facilities.


    East side of Linder Rd

    • Sidewalk remaining.
    • Block wall ongoing.

    West side of Linder Rd

    • Excavation and concrete removal.
    • Storm drain ongoing.
    • Pole bases and conduits being placed.

    Foothills Bridge - Rail remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Veolia working on new water line. Intersection closure started May 18th. Utilities relocating facilities.


  • June 26, 2026

    Share June 26, 2026 on Facebook Share June 26, 2026 on X (formerly Twitter) Share June 26, 2026 on Linkedin Email June 26, 2026 link

    East side of Linder Rd

    • Sidewalk remaining.
    • Block wall ongoing.

    West side of Linder Rd

    • Excavation and concrete removal.
    • Storm drain ongoing.
    • Pole bases and conduits being placed.

    Foothills Bridge - Rail remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Veolia working on new water line. Intersection closure started May 18th. Utilities relocating facilities.

    East side of Linder Rd

    • Sidewalk remaining.
    • Block wall ongoing.

    West side of Linder Rd

    • Excavation and concrete removal.
    • Storm drain ongoing.
    • Pole bases and conduits being placed.

    Foothills Bridge - Rail remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Veolia working on new water line. Intersection closure started May 18th. Utilities relocating facilities.

  • June 18, 2026

    Share June 18, 2026 on Facebook Share June 18, 2026 on X (formerly Twitter) Share June 18, 2026 on Linkedin Email June 18, 2026 link

    East side of Linder Rd

    • Sidewalk remaining.
    • Block wall construction ongoing.

    West side of Linder Rd

    • Excavation and concrete removal.
    • Storm drain installation ongoing.
    • Pole bases and conduits being placed.

    Foothills Bridge - Rail installation remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Veolia working on new water line. Intersection closure started May 18th. Utilities relocating facilities.


    East side of Linder Rd

    • Sidewalk remaining.
    • Block wall construction ongoing.

    West side of Linder Rd

    • Excavation and concrete removal.
    • Storm drain installation ongoing.
    • Pole bases and conduits being placed.

    Foothills Bridge - Rail installation remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Veolia working on new water line. Intersection closure started May 18th. Utilities relocating facilities.


  • June 12, 2026

    Share June 12, 2026 on Facebook Share June 12, 2026 on X (formerly Twitter) Share June 12, 2026 on Linkedin Email June 12, 2026 link

    East side of Linder Rd

    • Sidewalk remaining.
    • Block wall ongoing.

    West side of Linder Rd

    • Excavation and concrete removal.
    • Storm drain ongoing.
    • Pole bases and conduits being placed.

    Foothills Bridge - Rail remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Veolia working on the new water line. Intersection closure started May 18th. Utilities relocating facilities.


    East side of Linder Rd

    • Sidewalk remaining.
    • Block wall ongoing.

    West side of Linder Rd

    • Excavation and concrete removal.
    • Storm drain ongoing.
    • Pole bases and conduits being placed.

    Foothills Bridge - Rail remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Veolia working on the new water line. Intersection closure started May 18th. Utilities relocating facilities.


  • June 5, 2026

    Share June 5, 2026 on Facebook Share June 5, 2026 on X (formerly Twitter) Share June 5, 2026 on Linkedin Email June 5, 2026 link

    East side of Linder Rd

    • Sidewalk remaining. Installation of block wall ongoing.

    West side of Linder Rd

    • Excavation and concrete removal. Storm drain ongoing.

    Foothills Bridge

    • Rail remaining.

    Dry Creek Bridge

    • Complete.

    Floating Feather and Linder Roundabout

    • Veolia working on new water line.
    • Intersection closure started May 18th.
    • Utilities relocating facilities.


    East side of Linder Rd

    • Sidewalk remaining. Installation of block wall ongoing.

    West side of Linder Rd

    • Excavation and concrete removal. Storm drain ongoing.

    Foothills Bridge

    • Rail remaining.

    Dry Creek Bridge

    • Complete.

    Floating Feather and Linder Roundabout

    • Veolia working on new water line.
    • Intersection closure started May 18th.
    • Utilities relocating facilities.


  • May 29, 2026

    Share May 29, 2026 on Facebook Share May 29, 2026 on X (formerly Twitter) Share May 29, 2026 on Linkedin Email May 29, 2026 link

    East side of Linder Rd - Sidewalk remaining. Block wall installation ongoing.

    West side of Linder Rd - Excavation and concrete removal. Storm drain ongoing.

    Foothills Bridge - Rail remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Veolia is working on the new water line. The intersection closure started May 18th. Utilities are relocating facilities.

    East side of Linder Rd - Sidewalk remaining. Block wall installation ongoing.

    West side of Linder Rd - Excavation and concrete removal. Storm drain ongoing.

    Foothills Bridge - Rail remaining.

    Dry Creek Bridge - Complete.

    Floating Feather and Linder Roundabout - Veolia is working on the new water line. The intersection closure started May 18th. Utilities are relocating facilities.

Page last updated: 30 Jul 2026, 01:29 PM