The Ada County Highway District (ACHD) will be reconstructing Ustick Road between Black Cat Road and Ten Mile Road. The purpose of this project is to improve traffic flow and increase safety for all users.
Ustick, Black Cat to Ten Mile
- Widen Ustick Road to two lanes in each direction, with center turn lanes or center medians at key locations.
- Construct curb, gutter, and a 10-foot-wide multi-use pathway with a safety buffer on both sides of the roadway for pedestrian and bicyclists.
- Add a traffic signal at Naomi Avenue.
- Install an enhanced pedestrian crossing across Ustick Road at the Nine Mile Pathway.
- Upgrade stormwater facilities and replace irrigation pipes.
Ustick and Black Cat Intersection
- Widen the Ustick Road and Black Cat Road intersection to include additional through lanes.
- Add dedicated right and left turn lanes on all approaches.
- Install curb, gutter, and multi-use pathways.
The Ada County Highway District (ACHD) will be reconstructing Ustick Road between Black Cat Road and Ten Mile Road. The purpose of this project is to improve traffic flow and increase safety for all users.
Ustick, Black Cat to Ten Mile
- Widen Ustick Road to two lanes in each direction, with center turn lanes or center medians at key locations.
- Construct curb, gutter, and a 10-foot-wide multi-use pathway with a safety buffer on both sides of the roadway for pedestrian and bicyclists.
- Add a traffic signal at Naomi Avenue.
- Install an enhanced pedestrian crossing across Ustick Road at the Nine Mile Pathway.
- Upgrade stormwater facilities and replace irrigation pipes.
Ustick and Black Cat Intersection
- Widen the Ustick Road and Black Cat Road intersection to include additional through lanes.
- Add dedicated right and left turn lanes on all approaches.
- Install curb, gutter, and multi-use pathways.
-
February 28, 2025
28 Feb 2025Share February 28, 2025 on Facebook Share February 28, 2025 on Twitter Share February 28, 2025 on Linkedin Email February 28, 2025 link- Black Cat Road is closed south of Ustick Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
- Irrigation and seepage bed installation is ongoing.
- Roadway and sidewalk demo and prep are ongoing on the north side of Ustick.
- Eight mile irrigation: Excavation for the west side diversion structure complete.
- Utility relocations are nearly complete.
- Temporary precast sections have been set.
- Irrigation work on Nine mile and Rutledge continues.
- Headwall at Rutledge complete.
- Precast box fabrication complete for this season.
-
February 20, 2025
20 Feb 2025Share February 20, 2025 on Facebook Share February 20, 2025 on Twitter Share February 20, 2025 on Linkedin Email February 20, 2025 link- Black Cat Road is closed south of Ustick Road.
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
- Irrigation and seepage bed installation is ongoing.
- Roadway and sidewalk demo and prep is ongoing.
- Eight Mile irrigation box on Black Cat has been demolished.
- Excavation for the west side headwall complete.
- Irrigation work on Nine Mile and Rutledge has started.
- Headwall at Rutledge complete.
- Precast box fabrication complete for this season.
- Southwest corner of Ustick and Black Cat (Eight Mile) irrigation work ongoing.
-
February 14, 2025
14 Feb 2025Share February 14, 2025 on Facebook Share February 14, 2025 on Twitter Share February 14, 2025 on Linkedin Email February 14, 2025 link- Black Cat Road is closed south of Ustick Road.
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
- Irrigation and seepage bed installation is ongoing.
- Roadway and sidewalk demo and prep is ongoing.
- Eight Mile irrigation box on Black Cat has been demolished.
- Excavation for the west side headwall complete.
- Headwall is installed.
- Precast box fabrication ongoing.
- Southwest corner of Ustick and Black Cat irrigation work started.
-
February 7, 2025
07 Feb 2025Share February 7, 2025 on Facebook Share February 7, 2025 on Twitter Share February 7, 2025 on Linkedin Email February 7, 2025 link- Black Cat Road is closed south of Ustick Road.
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
- Irrigation and seepage bed installation is ongoing.
- Roadway and sidewalk demo and prep is ongoing.
- Eight Mile irrigation box on Black Cat has been demolished.
- Excavation for the west side headwall complete.
- Headwall is installed.
- Precast box fabrication ongoing.
-
January 31, 2025
31 Jan 2025Share January 31, 2025 on Facebook Share January 31, 2025 on Twitter Share January 31, 2025 on Linkedin Email January 31, 2025 link- Black Cat Road is closed south of Ustick Road.
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
- Irrigation and seepage bed installation is ongoing.
- Roadway and sidewalk demo and prep is ongoing.
- Eight mile irrigation box on Black Cat has been demolished.
- Excavation for the west side headwall to start this week.
- Precast box fabrication ongoing.
-
January 23, 2025
23 Jan 2025Share January 23, 2025 on Facebook Share January 23, 2025 on Twitter Share January 23, 2025 on Linkedin Email January 23, 2025 link- Black Cat Road is closed south of Ustick Road.
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
- Irrigation and seepage bed installation is ongoing.
- Roadway and sidewalk demo and prep is ongoing.
- Eight mile irrigation box on Black Cat has been demolished.
- Excavation for the west side headwall to start this week.
- Precast box fabrication ongoing.
-
January 17, 2025
17 Jan 2025Share January 17, 2025 on Facebook Share January 17, 2025 on Twitter Share January 17, 2025 on Linkedin Email January 17, 2025 link- Black Cat Road is closed south of Ustick Road.
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
- Irrigation and seepage bed installation is ongoing.
- Roadway and sidewalk demo and prep is ongoing.
- Eight mile irrigation box on Black Cat has been demolished.
- Excavation for the west side headwall to start this week.
- Precast box fabrication started this week.
-
January 10, 2024
10 Jan 2025Share January 10, 2024 on Facebook Share January 10, 2024 on Twitter Share January 10, 2024 on Linkedin Email January 10, 2024 link- Black Cat Road is closed south of Ustick Road.
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
- Irrigation and seepage bed installation is ongoing.
- Roadway and sidewalk demo and prep is ongoing.
- Eight Mile irrigation box on Black Cat has been demolished.
- Excavation for the west side headwall to start this week.
- Precast box fabrication started this week.
-
January 3, 2025
03 Jan 2025Share January 3, 2025 on Facebook Share January 3, 2025 on Twitter Share January 3, 2025 on Linkedin Email January 3, 2025 link- Black Cat Road is closed south of Ustick Road.
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
- Irrigation and seepage bed installation is ongoing.
- Roadway and sidewalk demo and prep is ongoing.
- Eight Mile irrigation box on Black Cat has been demolished.
-
December 20, 2024
20 Dec 2024Share December 20, 2024 on Facebook Share December 20, 2024 on Twitter Share December 20, 2024 on Linkedin Email December 20, 2024 link- Black Cat Road is closed south of Ustick Road.
- Temporary asphalt for the new traffic pattern on the south side of Ustick complete.
- Traffic will shift this week.
- Irrigation and seepage bed install ongoing.
- Roadway and sidewalk demo and prep ongoing.
- Eight mile irrigation box on Black Cat has been demolished.
Page last updated: 02 May 2025, 10:24 AM
Follow Project
Stay informed
Subscribe for project updates
54 members of your community are following this project
Spring 2023 Public Outreach
-
Spring 2023 Public Outreach
-
Infographic, Spring 2023 Outreach (Ustick, Black Cat to Ten Mile) (222 KB) (pdf)
-
Comment Summary, Spring 2023 (Ustick, Black Cat to Ten Mile) (1.29 MB) (pdf)
-
Informational Slides (Ustick, Black Cat to Ten Mile) (18.9 MB) (pdf)
-
Project Design (Ustick, Black Cat to Ten Mile) (11.6 MB) (pdf)
-
Typical Sections (Ustick, Black Cat to Ten Mile) (559 KB) (pdf)
-
Timeline
-
2021
Ustick Road, Black Cat Road to Ten Mile Road has finished this stageDesign started
-
Fall 2022
Ustick Road, Black Cat Road to Ten Mile Road has finished this stagePublic input opportunity #1
-
Spring 2023
Ustick Road, Black Cat Road to Ten Mile Road has finished this stagePublic input opportunity #2
-
2024
Ustick Road, Black Cat Road to Ten Mile Road has finished this stageBegin purchasing property necessary for project
-
November 2024
Ustick Road, Black Cat Road to Ten Mile Road is currently at this stageStart construction
-
Spring 2026
this is an upcoming stage for Ustick Road, Black Cat Road to Ten Mile RoadFinish construction
Related projects
Who's Listening
-
Senior Project Manager
Phone 208-387-6100 Email projects@achdidaho.org (External link) -
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org (External link) -
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org (External link)