The Ada County Highway District (ACHD) will be reconstructing Ustick Road between Black Cat Road and Ten Mile Road. The purpose of this project is to improve traffic flow and increase safety for all users.
Ustick, Black Cat to Ten Mile
- Widen Ustick Road to two lanes in each direction, with center turn lanes or center medians at key locations.
- Construct curb, gutter, and a 10-foot-wide multi-use pathway with a safety buffer on both sides of the roadway for pedestrian and bicyclists.
- Add a traffic signal at Naomi Avenue.
- Install an enhanced pedestrian crossing across Ustick Road at the Nine Mile Pathway.
- Upgrade stormwater facilities and replace irrigation pipes.
Ustick and Black Cat Intersection
- Widen the Ustick Road and Black Cat Road intersection to include additional through lanes.
- Add dedicated right and left turn lanes on all approaches.
- Install curb, gutter, and multi-use pathways.
The Ada County Highway District (ACHD) will be reconstructing Ustick Road between Black Cat Road and Ten Mile Road. The purpose of this project is to improve traffic flow and increase safety for all users.
Ustick, Black Cat to Ten Mile
- Widen Ustick Road to two lanes in each direction, with center turn lanes or center medians at key locations.
- Construct curb, gutter, and a 10-foot-wide multi-use pathway with a safety buffer on both sides of the roadway for pedestrian and bicyclists.
- Add a traffic signal at Naomi Avenue.
- Install an enhanced pedestrian crossing across Ustick Road at the Nine Mile Pathway.
- Upgrade stormwater facilities and replace irrigation pipes.
Ustick and Black Cat Intersection
- Widen the Ustick Road and Black Cat Road intersection to include additional through lanes.
- Add dedicated right and left turn lanes on all approaches.
- Install curb, gutter, and multi-use pathways.
-
October 31, 2025
Share October 31, 2025 on Facebook Share October 31, 2025 on Twitter Share October 31, 2025 on Linkedin Email October 31, 2025 link- Black Cat Road is open north of Ustick Road.
- Black Cat Road is closed south of Ustick Road.
- Naomi has reopened on the south side to Ustick Road for school access.
- Ustick remains open: Traffic has been shifted onto new pavement on the north side of Ustick – one lane in each direction remains open. Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish. Eightmile and Ninemile irrigation: o Irrigation work started again on October 20th at both Eightmile and Ninemile. The remaining precast box sections for Eightmile are planning to be delivered end of October. Curb and gutter and sidewalk placements ongoing on the north/south side of Ustick.
- Asphalt paving portions of the north side of Ustick complete (bottom lift only).
- City of Meridian sewer line installation continues near Black Cat, on the south side of Ustick. Waiting on irrigation work to complete before sewer and water can be completed.
- Excavation activities are complete on the south side of Ustick.
- Grade prep on the south side of Ustick ongoing.
- Concrete paving south side of Ustick and Black Cat started October 8th and is on-going.
-
October 24, 2025
Share October 24, 2025 on Facebook Share October 24, 2025 on Twitter Share October 24, 2025 on Linkedin Email October 24, 2025 link- Black Cat Road is open north of Ustick Road.
- Black Cat Road is closed south of Ustick Road.
- Naomi has reopened on the south side to Ustick Road for school access. Ustick remains open:Traffic has been shifted onto new pavement on the north side of Ustick – one lane in each direction remains open.
- Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish
- Eightmile and Ninemile irrigation: Irrigation work started again on October 20th at both Eightmile and Ninemile. The remaining precast box sections for Eightmile are planning to be delivered end of October.
- Curb and gutter and sidewalk placements ongoing on the north/south side of Ustick.
- Asphalt paving portions of the north side of Ustick complete (bottom lift only).
- City of Meridian sewer line installation continues near Black Cat, on the south side of Ustick. Waiting on irrigation work to complete before sewer and water can be completed.
- Excavation activities are complete on the south side of Ustick.
- Grade prep on the south side of Ustick ongoing.
- Concrete paving south side of Ustick and Black Cat started October 8th and is on-going
-
October 17, 2025
Share October 17, 2025 on Facebook Share October 17, 2025 on Twitter Share October 17, 2025 on Linkedin Email October 17, 2025 link- Black Cat Road is open north of Ustick Road.
- Black Cat Road is closed south of Ustick Road.
- Naomi has reopened on the south side to Ustick Road for school access.
- Ustick remains open: o Traffic has been shifted onto new pavement on the north side of Ustick – one lane in each direction remains open.
- Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish. Eightmile irrigation: o Irrigation is complete for the season. The remaining precast box sections are planning to be delivered end of October.
- Curb and gutter and sidewalk placements ongoing on the north/south side of Ustick. Asphalt paving portions of the north side of Ustick complete (bottom lift only). City of Meridian sewer line installation continues near Black Cat, on the south side of Ustick. Waiting on irrigation work to complete before sewer and water can be completed.
- Excavation activities are ongoing on the south side of Ustick.
- Grade prep on the south side of Ustick ongoing.
- Concrete paving south side of Ustick and Black Cat started October 8th and is on-going.
-
October 10, 2025
Share October 10, 2025 on Facebook Share October 10, 2025 on Twitter Share October 10, 2025 on Linkedin Email October 10, 2025 link- Black Cat Road is open north of Ustick Road.
- Black Cat Road is closed south of Ustick Road.
- Naomi has reopened on the south side to Ustick Road for school access.
- Ustick remains open: Traffic has been shifted onto new pavement on the north side of Ustick – one lane in each direction remains open. Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish Eightmile irrigation: Irrigation is complete for the season. The remaining precast box sections are planning to be delivered end of October. Curb and gutter and sidewalk placements ongoing on the north/south side of Ustick. Asphalt paving portions of the north side of Ustick complete (bottom lift only).
- City of Meridian sewer line installation continues near Black Cat, on the south side of Ustick. Waiting on irrigation work to complete before sewer and water can be completed.
- Excavation activities are ongoing on the south side of Ustick.
- Grade prep on the south side of Ustick ongoing.
- Concrete paving south side of Ustick and Black Cat started October 8th and is on-going.
-
October 2, 2025
Share October 2, 2025 on Facebook Share October 2, 2025 on Twitter Share October 2, 2025 on Linkedin Email October 2, 2025 link- Black Cat Road is open north of Ustick Road.
- Black Cat Road is closed south of Ustick Road.
- Naomi has reopened on the south side to Ustick Road for school access.
- Ustick remains open: Traffic has been shifted onto new pavement on the north side of Ustick – one lane in each direction remains open. Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
- Eightmile irrigation: Irrigation is complete for the season. Curb and gutter and sidewalk placements ongoing on the north/south side of Ustick. Asphalt paving portions of the north side of Ustick complete (bottom lift only). City of Meridian sewer line installation continues near Black Cat, on the south side of Ustick. Excavation activities are ongoing on the south side of Ustick.
- Grade prep on the south side of Ustick ongoing.
-
September 26, 2025
Share September 26, 2025 on Facebook Share September 26, 2025 on Twitter Share September 26, 2025 on Linkedin Email September 26, 2025 link- Black Cat Road is open north of Ustick Road.
- Black Cat Road is closed south of Ustick Road.
- Naomi has reopened on the south side to Ustick Road for school access.
- Ustick remains open: Traffic has been shifted onto new pavement on the north side of Ustick – one lane in each direction remains open. Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish. Eightmile irrigation: Irrigation is complete for the season. Curb and gutter and sidewalk placements ongoing on the north/south side of Ustick. Asphalt paving portions of the north side of Ustick complete (bottom lift only). City of Meridian sewer line installation continues near Black Cat, on the south side of Ustick. Excavation activities are ongoing on the south side of Ustick.
-
September 19, 2025
Share September 19, 2025 on Facebook Share September 19, 2025 on Twitter Share September 19, 2025 on Linkedin Email September 19, 2025 link- Black Cat Road is open north of Ustick Road.
- Black Cat Road is closed south of Ustick Road.
- Naomi has reopened on the south side to Ustick Road for school access.
- Ustick remains open: Traffic has been shifted onto new pavement on the north side of Ustick – one lane in each direction remains open. Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish. Eightmile irrigation: Irrigation is complete for the season. Curb and gutter and sidewalk placements ongoing on the north/south side of Ustick. Asphalt paving portions of the north side of Ustick complete (bottom lift only). City of Meridian sewer line installation continues near Black Cat, on the south side of Ustick. Excavation activities are ongoing on the south side of Ustick.
-
September 12, 2025
Share September 12, 2025 on Facebook Share September 12, 2025 on Twitter Share September 12, 2025 on Linkedin Email September 12, 2025 link- Black Cat Road is open north of Ustick Road.
- Black Cat Road is closed south of Ustick Road.
- Naomi has reopened on the south side to Ustick Road for school access.
- Ustick remains open: Traffic has been shifted onto new pavement on the north side of Ustick – one lane in each direction remains open. Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish. Eightmile irrigation: Irrigation is complete for the season. Curb and gutter and sidewalk placements ongoing on the north/south side of Ustick. Asphalt paving portions of the north side of Ustick complete (bottom lift only). City of Meridian sewer line installation continues near Black Cat, on the south side of Ustick. Excavation activities have started on the south side of Ustick.
-
September 5, 2025
Share September 5, 2025 on Facebook Share September 5, 2025 on Twitter Share September 5, 2025 on Linkedin Email September 5, 2025 link- Black Cat Road is open north of Ustick Road.
- Black Cat Road is closed south of Ustick Road.
- Naomi has reopened on the south side to Ustick Road for school access.
- Ustick remains open: Traffic has been shifted onto new pavement on the north side of Ustick – one lane in each direction remains open. Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish
- Eightmile irrigation: Irrigation is complete for the season. Curb and gutter and sidewalk placements ongoing on the north/south side of Ustick. Asphalt paving portions of the north side of Ustick complete (bottom lift only). City of Meridian sewer line installation continues near Black Cat, on the south side of Ustick. Excavation activities have started on the south side of Ustick.
-
August 25, 2025
Share August 25, 2025 on Facebook Share August 25, 2025 on Twitter Share August 25, 2025 on Linkedin Email August 25, 2025 link- Black Cat Road is open north of Ustick Road.
- Black Cat Road is closed south of Ustick Road.
- Naomi is closed on the south side to Ustick Road; anticipate to re-open the week of September 2nd.
- Ustick remains open: Traffic has been shifted onto new pavement on the north side of Ustick – one lane in each direction remains open. Irrigation and seepage bed installation is nearly complete – waiting for south Black Cat access to finish.
- Eightmile irrigation: o Irrigation is complete for the season. Irrigation work, apart from Ninemile, is nearly complete in preparation for the City’s sewer bypass.
- Rutledge has been sleeved for sewer line install.
- Curb and gutter and sidewalk placements ongoing on the north/south side of Ustick.
- Contractor is focusing on the Naomi intersection. School has been notified that the intersection will not be open by the start of School. Targeting the end of August or early September for reopening.
- Seepage bed install at Naomi is complete.
- Prepping for curb gutter sidewalk for placements this week.
- Intersection will be reopened on Tuesday, 9/2, before school starts.
- Asphalt paving portions of the north side of Ustick complete (bottom lift only).
- City of Meridian sewer line installation continues near Black Cat, on the south side of Ustick.
Page last updated: 30 Jan 2026, 10:11 AM
Follow Project
Stay informed
Subscribe for project updates
68 members of your community are following this project
Spring 2023 Public Outreach
-
Spring 2023 Public Outreach
-
Infographic, Spring 2023 Outreach (Ustick, Black Cat to Ten Mile) (222 KB) (pdf)
-
Comment Summary, Spring 2023 (Ustick, Black Cat to Ten Mile) (1.29 MB) (pdf)
-
Informational Slides (Ustick, Black Cat to Ten Mile) (18.9 MB) (pdf)
-
Project Design (Ustick, Black Cat to Ten Mile) (11.6 MB) (pdf)
-
Typical Sections (Ustick, Black Cat to Ten Mile) (559 KB) (pdf)
-
Timeline
-
2021
Ustick Road, Black Cat Road to Ten Mile Road has finished this stageDesign started
-
Fall 2022
Ustick Road, Black Cat Road to Ten Mile Road has finished this stagePublic input opportunity #1
-
Spring 2023
Ustick Road, Black Cat Road to Ten Mile Road has finished this stagePublic input opportunity #2
-
2024
Ustick Road, Black Cat Road to Ten Mile Road has finished this stageBegin purchasing property necessary for project
-
November 2024
Ustick Road, Black Cat Road to Ten Mile Road is currently at this stageStart construction
-
Spring 2026
this is an upcoming stage for Ustick Road, Black Cat Road to Ten Mile RoadFinish construction
Related projects
Who's Listening
-
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org -
Supervisor, Capital Projects
Phone 208-387-6100 Email connect@achdidaho.org