State Street, 8th Street to 4th Street
Share State Street, 8th Street to 4th Street on Facebook
Share State Street, 8th Street to 4th Street on Twitter
Share State Street, 8th Street to 4th Street on Linkedin
Email State Street, 8th Street to 4th Street link
- Reconstruct State Street between 8th and 4th streets.
- Upgrade all three traffic signals on this section of State St.
- Construct bulb-outs for shorter pedestrian crossings and better visibility.
- Add vegetated bioretention facilities for stormwater treatment.
- Upgrade the existing enhanced crosswalk behind the Idaho State Capitol building to an overhead Rectangular Rapid Flashing Beacon.
- Reconstruct State Street between 8th and 4th streets.
- Upgrade all three traffic signals on this section of State St.
- Construct bulb-outs for shorter pedestrian crossings and better visibility.
- Add vegetated bioretention facilities for stormwater treatment.
- Upgrade the existing enhanced crosswalk behind the Idaho State Capitol building to an overhead Rectangular Rapid Flashing Beacon.
-
September 13, 2024
Share September 13, 2024 on Facebook Share September 13, 2024 on Twitter Share September 13, 2024 on Linkedin Email September 13, 2024 link- 8th Street electrical/fiber work ongoing.
- Idaho Power vault needs to be lowered.
- IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and continues to prep road base from 6th to 8th.
- Concrete paving complete between 4th and 5th St. South side of 5th complete.
- Power and fiber for signals nearly complete.
- Sidewalks and ped ramp work started between 4th and 5th.
- Landscapers to follow.
-
September 6, 2024
Share September 6, 2024 on Facebook Share September 6, 2024 on Twitter Share September 6, 2024 on Linkedin Email September 6, 2024 link- 8th Street electrical/fiber work ongoing.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and continues to prep road base from 6th to 8th.
- Concrete paving complete between 4th and 5th St.
- South side of 5th will be paved on Friday September 6th.
- Power and fiber for signals nearly complete.
- Sidewalks and ped ramp work started between 4th and 5th. Landscapers to follow.
-
August 30, 2024
Share August 30, 2024 on Facebook Share August 30, 2024 on Twitter Share August 30, 2024 on Linkedin Email August 30, 2024 link- 8th Street electrical/fiber work ongoing.
- Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and continues to prep road base from 6th to 8th.
- Concrete paving started between 4th and 5th St.
- Power and fiber for signals ongoing.
-
August 23, 2024
Share August 23, 2024 on Facebook Share August 23, 2024 on Twitter Share August 23, 2024 on Linkedin Email August 23, 2024 link- 8th Street electrical/fiber work ongoing – Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and continues to prep road base.
- Prepping for concrete paving complete between 4th and 5th St.
- Contractor will be paving early morning starting August 22nd between 4th and 5th St.
- Power and fiber for signals ongoing.
-
August 15, 2024
Share August 15, 2024 on Facebook Share August 15, 2024 on Twitter Share August 15, 2024 on Linkedin Email August 15, 2024 link- 8th Street electrical/fiber work ongoing.
- Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and continues to prep road base.
- Prepping for concrete paving ongoing – tentatively scheduled for August 21-22nd.
-
August 9, 2024
Share August 9, 2024 on Facebook Share August 9, 2024 on Twitter Share August 9, 2024 on Linkedin Email August 9, 2024 link- 8th Street electrical/fiber work ongoing.
- Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and started to prep for road base while Idaho Power sorts out the vault issue on State and 8th.
- Prepping for concrete paving ongoing.
-
August 2, 2024
Share August 2, 2024 on Facebook Share August 2, 2024 on Twitter Share August 2, 2024 on Linkedin Email August 2, 2024 link- 8th Street electrical/fiber work ongoing – Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and started to prep for road base while Idaho Power sorts out the vault issue on State and 8th.
- Prepping for concrete paving ongoing.
-
July 26, 2024
Share July 26, 2024 on Facebook Share July 26, 2024 on Twitter Share July 26, 2024 on Linkedin Email July 26, 2024 link- Project includes work on State Street between 4th Street and 8th Street
- 8th Street electrical/fiber work ongoing.
- Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered.
- IP working with engineer consultant to retrofit box to meet new grades.
- Contractor completed demo on State and 8th.
- Excavation complete, on the north side, in preparation for base materials.
- Contractor has moved east and started to prep for road base while Idaho Power sorts out the vault issue on State and 8th.
- Project includes work on State Street between 4th Street and 8th Street
-
July 19, 2024
Share July 19, 2024 on Facebook Share July 19, 2024 on Twitter Share July 19, 2024 on Linkedin Email July 19, 2024 link- 8th Street electrical/fiber work ongoing – Fiber swap is scheduled for the weekend of July 20th.
- Contractor completed demo on State and 8th this week.
- Excavation started this week, on the north side, in preparation for base materials.
- Idaho Power underground work is ongoing.
-
July 17, 2024
Share July 17, 2024 on Facebook Share July 17, 2024 on Twitter Share July 17, 2024 on Linkedin Email July 17, 2024 linkAn unforeseen utility conflict has been found at the State Street and 8th Street intersection. It is anticipated to take two months for the utility’s contractor to resolve. ACHD construction crews will now focus on the east end of the project.
The State Street and 4th Street intersection will be paved first and then paving will continue moving west.
As the intersections are paved, ACHD plans to open them to north/south traffic.
Page last updated: 15 Nov 2024, 10:53 AM
State Street 8th to 4th Design
Who's Listening
-
Sr. Project Manager
Phone 208-387-6100 Email projects@achdidaho.org -
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Community and Business Relations Coordinator
Phone 208-387-6100 Email projects@achdidaho.org
Follow Project
Stay informed
Subscribe for project updates
56 members of your community are following this project